Professional Documents
Culture Documents
CONSTRUCTION
CONTRACTS
Week 3 UE-405
Contract:
• An agreement between the organization and an
outside provider of a service or materials is
a contract.
• To limit misunderstandings and make them more
legally binding, contracts are usually written
documents that describe the obligations of both parties
and are signed by those with authority to represent the
interests of the parties.
Types of contracts
• The legal contracts that support the procurement
plan consist of two general types of contract:
• the fixed-price and
• the cost-reimbursable contracts
Fixed-Price Contracts
• The fixed-price contract is a legal agreement
between the project organization and an entity
(person or company) to provide goods or services
to the project at an agreed-on price.
• The contract usually details the quality of the goods or
services, the timing needed to support the project, and
the price for delivering goods or services.
• For commodities and goods and services where the
scope of work is very clear and not likely to
change, the fixed price contract offers a predictable
cost.
Fixed-Price Contracts
• Fixed-price contracts require the availability of at
least two or more suppliers that have the
qualifications and performance histories that assure
the needs of the project can be met.
• The other requirement is a scope of work that is
most likely not going to change.
• Developing a clear scope of work based on good
information, creating a list of highly qualified
bidders, and developing a clear contract that
reflects that scope of work are critical aspects of a
good fixed-priced contract.
Fixed-total-cost Contract
• If the service provider is responsible for
incorporating all costs, including profit, into the
agreed-on price, it is a fixed-total-cost contract.
• The contractor assumes the risks for unexpected
increases in labor and materials that are needed to
provide the service or materials and in the materials
and timeliness needed.
Fixed-price Contract With Price
Adjustment
• The fixed-price contract with price adjustment is
used for unusually long projects that span years.
• The most common use of this type of contract is the
inflation-adjusted price.
• In some countries, the value of its local currency can
vary greatly in a few months, which affects the cost of
local materials and labor.
• In periods of high inflation, the client assumes risk of
higher costs due to inflation, and the contract price is
adjusted based on an inflation index.
• The volatility of certain commodities can also be
accounted for in a price adjustment contract.
Fixed-price With Incentive Fee
• The fixed-price with incentive fee is a contract type
that provides an incentive for performing on the
project above the established baseline in the
contract.
• The contract might include an incentive for
completing the work on an important milestone for
the project.
• Often contracts have a penalty clause if the work is
not performed according to the contract.
• For example, if the new software is not completed
in time to support the implementation of the
training, the contract might penalize the software
Fixed Unit Price Contract
• If the service or materials can be measured in
standard units, but the amount needed is not known
accurately, the price per unit can be fixed—a fixed
unit price contract.
• The project team assumes the responsibility of
estimating the number of units used.
• If the estimate is not accurate, the contract does not
need to be changed, but the project will exceed the
budgeted cost.
Table of Fixed Price Contracts and
Characteristics
Cost-Reimbursable Contracts
• In a cost-reimbursable contract, the organization
agrees to pay the contractor for the cost of
performing the service or providing the goods.
Cost-reimbursable contracts are also known as
cost-plus contracts.
• Cost-reimbursable contracts are most often used
when the scope of work or the costs for performing
the work are not well known.
• The project uses a -reimbursable contract to pay the
contractor for allowable expenses related to
performing the work.
• Since the cost of the project is reimbursable, the
Cost-Reimbursable Contracts
• When the costs of the work are not well known, a
cost-reimbursable contract reduces the amount of
money the bidders place in the bid to account for
the risk associated with potential increases in costs.
• The contractor is also less motivated to find ways to
reduce the cost of the project unless there are
incentives for supporting the accomplishment of
project goals.
• Cost-reimbursable contracts require good
documentation of the costs that occurred on the
project to assure that the contractor gets paid for all
the work performed and to assure that the
Cost-reimbursable Contract With A
Fixed Fee
• A cost-reimbursable contract with a fixed fee
provides the contractor with a fee, or profit amount,
that is determined at the beginning of the contract
and does not change.
Cost-reimbursable Contract With A
Percentage Fee
• A cost-reimbursable contract with a percentage fee
pays the contractor for costs plus a percentage of
the costs, such as 5% of total allowable costs. The
contractor is reimbursed for allowable costs and is
paid a fee.
Cost-reimbursable Contract With A
Incentive Fee
• A cost-reimbursable contract with an incentive fee
is used to encourage performance in areas critical
to the project.
• Often the contract attempts to motivate contractors
to save or reduce project costs.
• The use of the cost reimbursable contract with an
incentive fee is one way to motivate cost reduction
behaviors.
Cost-reimbursable Contract With A
Award Fee
• A cost-reimbursable contract with award fee
reimburses the contractor for all allowable costs
plus a fee that is based on performance criteria.
• The fee is typically based on goals or objectives
that are more subjective.
• An amount of money is set aside for the contractor
to earn through excellent performance, and the
decision on how much to pay the contractor is left
to the judgment of the project team.
• The amount is sufficient to motivate excellent
performance.
Time And Materials (T&M).
• On small activities that have a high uncertainty, the
contractor might charge an hourly rate for labor,
plus the cost of materials, plus a percentage of the
total costs.
• This type of contract is called time and materials
(T&M).
• Time is usually contracted on an hourly rate basis
and the contractor usually submits time sheets and
receipts for items purchased on the project. The
project reimburses the contractor for the time spent
based on an agreed-on rate and the actual cost of
the materials.
Table of Contract Types and
Characteristics
• To minimize the risk to the project, the contract
typically includes a not-to-exceed amount, which
means the contract can only charge up to the agreed
amount.
• The final cost of the work is not known until
sufficient information is available to complete a
more accurate estimate.
CONSTRUCTION
PLANNING AND
SCHEDULING
Developing Preliminary Schedules
• Knowing the tentative dates when all the key events
are going to occur is critical to the overall success
of the project.
• Schedules are time-based plans.
• Most construction projects involve many design
professionals, financial institutions, contractors,
and end users, all of whom are keenly interested in
knowing upfront as to when they will be involved
in the project and for how long.
• These answers can only be provided through the
use of preliminary schedules.
Types of Preliminary Schedules
• Three separate but distinct preliminary schedules
are important for effective control on most
multiple-facility projects. These include:
Activity Duration ES EF LS LF TF FF
A 1 0 1 0 1 0 0
B 6 1 7 1 7 0 0
C 8 1 9 2 10 1 0
D 6 7 13 7 13 0 0
E 3 9 12 10 13 1 1
F 1 13 14 13 14 0 0
A PDM Project Network With Precedence Relationships
Without Imposed Time Constraints
Forward Pass Calculations
Backward Pass Calculations
Revised Concept of Free Float
Activity Float Calculations
Activity Duration ES EF LS LF TF FF*
A 20 0 20 0 20 0 0
B 10 16 26 33 43 17 0
C 10 20 30 20 30 0 0
D 17 7 24 29 46 22 0
E 15 23 38 40 55 17 17
F 8 35 43 35 43 0 0
G 5 26 31 43 48 17 0
H 6 20 26 42 48 22 5
I 4 53 57 53 57 0 0
J 9 31 40 48 57 17 17
Important Inferences from CPM Time Computations on Networks
Without Imposed Constraints (Examples 1 and 2)
A 1 0 1 -2 -1 -2 0
B 6 1 7 -1 5 -2 0
C 8 1 9 0 8 -1 0
D 6 7 13 5 11 -2 0
E 3 9 12 8 11 -1 1
F 1 13 14 11 12 -2 0
Inferences
• In consequence to the imposed constraint, we are
forced into having a negative total float of –2 along
path A-B-D-F, which is the critical path.
• This, of course, indicates that 3 days must be saved
somehow if we are to finish on time. The concept
of negative float gives a useful rule for interpreting
a network analysis of a project with imposed dates:
• All negative floats must be eliminated by speeding-
up the corresponding activities, if the required
completion date is to be met.
• Since total float can be either negative, zero, or
positive, the critical path is the “path with the least
• Activity Symbol Duration Predecessor
(Days)
Project Start A 0
Mobilization B 7 A
Site Clearance C 3 B (SS+5)
Layout & D 2 C
Marking
Excavation E 10 D
Foundation F 20 E (SS+12)
Plinth Beams G 5 F (FF+3)
Columns H 10 G (FS–2)
Beams/ Slabs I 30 H (FS–3)
Block Masonry J 20 I (FS+15)
Plaster K 20 J (FF+30)
CONSTRUCTION TIME
PLANNING AND
SCHEDULING
INTRODUCTION
• Construction Time Planning is the first step in the
construction planning process.
• It includes the planning effort required to facilitate
timely completion of a project.
• Construction Time Scheduling provides a working
time-table of project activities for completion of the
project within specified time.
• It is a direct consequence of the construction time
planning process.
Steps Involved In Construction
Time Planning
• The steps involved in construction time planning
and scheduling process are:
1. Develop Project Work Breakdown Structures
(WBS)
2. Develop Activity List
3. Estimate Activity Durations
4. Establish Activity Logic Relationships
5. Define Project Base Calendars
6. Develop Project Time Schedule
7. Analyze and Adjust Project Time Schedule
Project Work Breakdown Structures
(WBS)
Key Idea
WBS provides the foundation for defining work as it
relates to project objective and establishes the structure
for managing the work to its completion.
• Examples are:
• Erect concrete columns,
• Run electrical conduits, or
• Install sanitary fixtures.
• Duration is 10 days.
• Calendar time is 12 days (Mon-Fri, Sat, Sun, Mon-
Fri).
ESTABLISHMENT OF ACTIVITY
DURATION
• Activity duration can be estimated with the aid of a
computer (e.g., by using excel spreadsheet or
project management software) or with manual
techniques.
• Manual techniques are often more effective on
smaller projects.
• Manual and automated techniques may also be used
in combination.
INPUTS TO ACTIVITY
DURATION ESTIMATION
• Quantity of Work
• Execution Methodology
• Resource Requirement
• Resource Productivities
• Time Contingency
Quantity of Work
• The amount of work that needs to be performed;
e.g. 10,000 cft of excavation, 2000 cft of
concreting, 1000 sq-ft of block masonry, etc. This
information is obtained from detailed BOQ or work
estimates in conjunction with construction
drawings.
Execution Methodology
• The execution methodology drives the resource
requirement on the activity.
• For example, the activity of placing concrete in the
foundation of a large building can be done in any of the
following ways – manually, using crane and bucket
arrangement, pumping by concrete pumps or
transporting by a conveyor system The time and cost
for each of these methods will differ considerably.
• The choice of the method of execution of an
activity depends upon
• the past experience,
• the market availability of appropriate resources,
Resource Requirement
• What type of resources (manpower, equipment and
material) are required and in what quantity?
• Resource estimates are normally made using the
planning norms developed from:
• Organizational records of previous projects
• Project team knowledge and experience
• Commercially available databases (if any)
• Expert advice
Resource Productivities
• The capabilities of the humans and equipment
resources assigned to activities – e.g. if both are
assigned full-time, a senior staff member can
generally be expected to complete a given activity
in less time than a junior staff member.
• Resource productivity is normally determined
from:
• Organizational records of previous projects
• Project team knowledge and experience
• Commercially available databases (if any)
• Expert advice
• Field research
Time Contingency
• This includes any possible time variation that
needs to be incorporated for any anticipated and
unanticipated interruptions, e.g.
• Interruptions might include a phone call with a
question to be answered, an equipment breakdown,
power interrupts, random events of nature, untimely
delivery of material, bad weather forecasts,
absenteeism, strikes, etc. Few of these interruptions
may be anticipated (e.g. bad weather forecast,
procession, strike etc.) while others may be
unanticipated (e.g. random event of nature).
TECHNIQUES FOR ACTIVITY
DURATION ESTIMATION
• The following techniques can be used for initial
planning estimates:
• One-time estimate
• Three-times estimate
One-time estimate
• In most of the construction works, it is generally possible to assess the
duration of an activity with reasonable certainty by using
• organizational planning data records,
• experience,
• commercially available databases, or
• expert advice.
• The one-time estimate for activity durations is usually used for Production
activities.
Example
How many hours will be needed to excavate 10,000
cu-ft with the provided data?
• Excavator’s Productivity = 1000 cu-ft/hr
• Number of Excavators = 2
anticipating performance.
PRECONSTRUCTION
PLANNING
• The success of a project largely depends on sound
planning, aimed at developing a workable program
that will achieve project goals.
• It forms the standard upon which the project control
system is based and by which future performance is
judged.
PRECONSTRUCTION
PLANNING AREAS
• The manager's preconstruction planning can be
divided into following:
• Area and Site Investigation
• Project Feasibility Studies
• Development of Project Scope Statement
• Project Priority Definition
• Drawings and Specifications Review
• Development of Project Preliminary Work Plan
Sample Project
• Consider a 100 unit housing colony construction
project in North Karachi to be developed by the
city development organization. The scope of the
project includes construction of 100 residential
houses. The value of works is estimated to be Rs.
160 million and the project is to be contracted to
complete in 36 months using fast track approach
(design, procurement and construction). The
residential accommodation falls in four
construction categories (25 units in each category):
Category A – Double storey one unit houses with
high class finish; Category B – Double storey one
AREA AND SITE
INVESTIGATION
AREA SITE
Review local work practices and jurisdiction
•
•
Ascertain key local prices for standard items
Ascertain local equipment rental prices drainage, existing
• Obtain climate information for use in
developing weather constraints
structures,
• Screen local contractor capabilities, workload,
and interests which will be helpful in deciding
accessibility, etc.)
on recommended contractors
• Visit other local contacts - key local contractors • Utilities Serving Site
and other knowledgeable local industry
representatives (Electricity, gas, water,
• Visit other projects noting productivity, favored
methods, favored materials, subcontractors, sewers, etc.)
etc.
• Interference with
PROJECT FEASIBILITY
STUDIES
Need Analysis Requirement Analysis
Constrain X
Enhance X
Reduce X
Because time is important for benefit reaps, the construction manager may be instructed to take
advantage of every opportunity to reduce completion time.
In doing so, going over budget is acceptable though not desirable.
At the same time, the original quality requirements cannot be compromised.
During the course of a project, priorities may change. The client may suddenly need the
project completed one month sooner, or new client directives may emphasize cost saving
initiatives. The MANAGER needs to be vigilant in order to anticipate and confirm changes in
priorities and make appropriate adjustments.
Project Priority Matrix
• Constrain on all three criterion (time, cost and
quality) would put the construction manager in a
highly inflexible position.
• It is extremely rare that everything would go nearly
perfect on a project and no major problems or
setbacks are encountered.
• Construction managers are often forced to make
tough decisions that benefit one criterion while
compromising the other two.
• The purpose of priority matrix is to define and
agree on what the priorities and constraints of the
project are so that right decisions can be made.
DRAWINGS AND
SPECIFICATIONS REVIEW
• The manager should ensure that all necessary
drawings and specifications are provided in
completion to the contractors.
• Drawings
• Construction drawings should elaborately show the
location, dimensions, and details of the work to be
performed.
• They should preferably be organized and numbered
according to specialty, such as structural, electrical,
and mechanical.
SPECIFICATIONS REVIEW
• The two basic ways in which the requirements for a
particular work may be specified are by method
specification or by performance specification.
SPECIFICATIONS
• A method specification states the precise equipment
and procedure to be used in performing a
construction work.
• Use of method specifications will enhance control .
• A performance specification specifies only the
result to be achieved and leaves to the contractor
the choice of equipment and method.
• Use of performance specifications will provide more
value engineering opportunities.
DEVELOPMENT OF PROJECT
PRELIMINARY WORK PLAN
• After the manager has obtained a thorough knowledge of area
and job-site conditions that will affect performance of the
work, preparation of the preliminary work plan for the project
can begin.
• An early work plan for overall project execution is important
in creating a team effort among the designer, owner, and
manager, and it forms the basis for planning that will continue
throughout the project as additional information becomes
available.
CONSTRUCTION
PLANNING &
MANAGEMENT
Week 1 UE-405
CONSTRUCTION PROJECTS
• A project is a temporary endeavor consisting of a
sequence of connected activities undertaken by
limited resources to create a unique product or
service that must be completed within specified
time, within budget, and according to specification.
Temporary Endeavor
• Temporary means that every project has a definite
beginning and a definite end.
• The end is reached when the project’s objectives
have been achieved, or when it becomes clear that
the project objectives will not or cannot be met and
the project is terminated.
• Temporary does not necessarily mean short in
duration (many projects last for years), nor it
applies to the product or service created (many
projects are undertaken to create lasting results
• for example, a project to erect a national monument
will create a result expected to last for centuries).
Sequence of Connected Activities
• A project comprises of a number of activities that
must be completed in some specified order, or
sequence.
• An activity is a defined chunk of work.
• The sequence of the activities is based on technical
requirements.
• Activities within a project are interconnected.
• To determine the connectedness, it is helpful to
think in terms of inputs and outputs.
• The output of one activity or set of activities
becomes the input to another activity or set of
Undertaken by limited resources
• Projects have resource limits, such as a limited
amount of people, materials or equipment that are
dedicated to the project.
Unique Product or Service
• Unique means that the product or service is
different in some distinguishing way from all
similar products or services.
• A product or service may be unique even if the
category it belongs to is large.
• For example, many thousands of office buildings have
been developed but each individual facility is unique –
different location, different owner, different design,
different contractor, and so on.
• The presence of repetitive elements does not
change the fundamental uniqueness of the project.
• For example, a real estate development project may
Within Specified Time
• Projects have a specified completion date. This date
can be self-imposed by management or externally
specified by a client or government agency.
Within Budget
• Projects have cash inflow constraints. The source of
finance may be public funds, bank loans or private
investments.
According to Specification
• The client expects a certain level of functionality
and quality from the project.
• These expectations can be self-imposed, such as the
specification of the project completion date, or
client-specified, such as use of wall paper for wall
finishing in a bungalow, or law imposed, such as
environmental considerations.
PROJECT SUCCESS
PARAMETERS
• Five constraints operate on every project:
• Quality/ Performance
• Resources
• Time
• Cost
Quality/ Performance
• Two types of quality are part of every project.
• The first is product quality.
• This refers to the quality of the deliverable from the project.
• The second type of quality is process quality,
• The quality of the project management process itself.
• A sound quality management program not only contributes
to customer satisfaction, but also helps organizations use
their resources more effectively and efficiently by reducing
waste and rework.
• The payoff is a higher probability of successfully
completing the project in accordance with customer
requirements.
• Quality to be achieved in accomplishing tasks is
normally stated in terms of standard specifications.
Resources
• Resources are assets, such as people, equipment,
physical facilities, or materials, which have limited
availabilities, can be scheduled, or can be leased
from an outside party.
• Resources are central to the scheduling of project
activities and the orderly completion of the project
in their availability as well as productivity.
• Productivity, in its broader sense, measures the
ratio of planned effort of resources to produce a
unit quantity of work divided by the actual effort of
resources employed to achieve this unit of work.
Time
• The client specifies a timeframe or deadline date
within which the project must be completed. This
may be due to several reasons:
• The capital turnover (revenue) forecasted to be realized
from early facility completion (e.g. shopping mall,
school)
• The need of the client to occupy, use or rent the facility
on a particular timeframe (e.g. bungalow).
• A public client requiring completion of the project by a
particular deadline so as to open it to service for public
(e.g. road, bridge, hospital).
Cost
• Cost is the expenditure which the client has agreed
to commit for creating the desired construction
facility.
• Cost is a major consideration throughout the project
management life cycle.
• It is best thought of as the budget that has been
established for the project. This is particularly
important for projects that create deliverables that
are sold either commercially or to an external
customer. Cost is a major element in leading the
client to a go/ no-go decision.