You are on page 1of 4

ID Task Name Duration Start 2 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov

Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '2
May 8 May 15 May 22 May 29 Jun 5 Jun 12 Jun 19 Jun 26 Jul 3 Jul 10 Jul 17 Jul 24 Jul 31 Aug 7 Aug 14 Aug 21 Aug 28 Sep 4 Sep 11 Sep 18 Sep 25 Oct 2 Oct 9 Oct 16 Oct 23 Oct 30
1
2 WTP (J & K) 98 days Wed 6/15/22
3 WTP Civil Works 73 days Wed 6/15/22
4 Piling 1 day Wed 6/15/22
5 Earthworks 2 days Thu 6/16/22
6 Excavation to approx. 1.5 m underground 2 days Thu 6/16/22
7 Pilecap, Tie Beam Work 25 days Sat 6/18/22
8 Cutting square pile 30x30 3 days Sat 6/18/22
9 Sand layer 1 day Mon 6/20/22
10 Lean concrete 2 days Tue 6/21/22
11 Formwork with bricks and wood 2 days Thu 6/23/22
12 Reinforcement work - pilecap and tie beam 4 days Sat 6/25/22

13 Concrete pouring 1 day Wed 6/29/22


14 Column reinforcement 3 days Thu 6/30/22
15 Formwork for column 3 days Sun 7/3/22
16 Concrete pouring 1 day Wed 7/6/22
17 Brick wall for 'hollow construction' 5 days Thu 7/7/22
18 WTP Beam and Wall to EL +3.10 19 days Thu 7/7/22
19 Formwork 5 days Thu 7/7/22
20 Reinforcement work 4 days Tue 7/12/22
21 Puddle pipe and water stop installation 1 day Sat 7/16/22
22 Formwork for wall (0.6 m high) 3 days Sat 7/16/22
23 Concrete pouring 1 day Tue 7/19/22
24 Taking off formwork 2 days Sat 7/23/22
25 Wall Structure From EL. +3.10 to +5.50 18 days Wed 7/20/22
26 Reinforcement work 5 days Wed 7/20/22
27 Puddle pipe and water stop installation 1 day Mon 7/25/22
28 Formwork 6 days Tue 7/26/22
29 Concrete pouring 1 day Mon 8/1/22
30 Taking off formwork 2 days Fri 8/5/22
31 Wall Structure From EL. +5.50 to +8.20 18 days Tue 8/2/22
(top of concrete)
32 Reinforcement work 5 days Tue 8/2/22
33 Formwork 7 days Sun 8/7/22
34 Concrete pouring 1 day Sat 8/13/22
35 Taking off formwork 2 days Wed 8/17/22
36 WTP Walkway & internal structure works 10 days Sun 8/14/22
37 Leak test 5 days Fri 8/19/22
38 Roof Work 15 days Sun 8/14/22
39 Roof steel structure 10 days Sun 8/14/22
40 Roof cover installation 5 days Wed 8/24/22

Task Project Summary Manual Task Start-only Deadline

Project: Draft schedule KIK Split Inactive Task Duration-only Finish-only Progress
Date: Wed 6/15/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Name Duration Start 2 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '2
May 8 May 15 May 22 May 29 Jun 5 Jun 12 Jun 19 Jun 26 Jul 3 Jul 10 Jul 17 Jul 24 Jul 31 Aug 7 Aug 14 Aug 21 Aug 28 Sep 4 Sep 11 Sep 18 Sep 25 Oct 2 Oct 9 Oct 16 Oct 23 Oct 30
41 Mechanical & Piping Installation 23 days Wed 8/24/22
42 Flocculator and clarifier valves installation 3 days Wed 8/24/22

43 Clarifier plate settler and support installation 4 days Sat 8/27/22

44 Filter nozzle slab installation 5 days Wed 8/31/22


45 Filter nozzle installation 4 days Mon 9/5/22
46 Filter sand installation 6 days Wed 9/7/22
47 Filter backwash gutter installation 3 days Mon 9/12/22
48 Filter face piping and valve installation 10 days Sat 8/27/22
49 WTP interconnecting piping 4 days Tue 9/6/22
50 Coagulator mixer installation 2 days Sat 9/10/22
51 Flocculator penstock installation 4 days Sun 9/11/22
52 Electrical & Instrument Installation 25 days Wed 8/24/22
53 Cable tray installation 5 days Wed 8/24/22
54 Cable laying 6 days Mon 8/29/22
55 Instrument installation ‐ LT, actuator sets 3 days Sun 9/4/22
56 Cable termination and tests 10 days Thu 9/8/22
57
58 Water Reservoir (M) 100 daysThu 6/16/22
59 Reservoir Civil Works 90 days Thu 6/16/22
60 Piling 18 days Thu 6/16/22
61 Earthwork 18 days Sat 6/18/22
62 Excavation foundation (Pile cap & Tie 18 days Sat 6/18/22
Beam)
63 Pilecap & Tie Beam +0.15, Wall to +1.10 13 days Tue 6/21/22
64 Cutting square pile 30x30 2 days Tue 6/21/22
65 Sand layer & lean concrete 1 day Thu 6/23/22
66 Formwork with bricks and wood 2 days Fri 6/24/22
67 Reinforcement work 5 days Sun 6/26/22
68 Concrete pouring 1 day Sun 7/3/22
69 Pilecap & Tie Beam +1.35, Wall to +1.95 36 days Thu
(0.6 m) 6/30/22
70 Cutting square pile 30x30 8 days Thu 6/30/22
71 Sand layer 1 day Fri 7/8/22
72 Lean concrete 2 days Sat 7/9/22
73 Formwork with bricks and wood 6 days Mon 7/11/22
74 Reinforcement work 7 days Sat 7/16/22
75 Puddle pipe and water stop installation 1 day Sat 7/23/22
76 Formwork for wall (0.6 m high) 5 days Sun 7/24/22
77 Concrete pouring 1 day Fri 7/29/22
78 Taking off formwork 2 days Tue 8/2/22

Task Project Summary Manual Task Start-only Deadline

Project: Draft schedule KIK Split Inactive Task Duration-only Finish-only Progress
Date: Wed 6/15/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Name Duration Start 2 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '2
May 8 May 15 May 22 May 29 Jun 5 Jun 12 Jun 19 Jun 26 Jul 3 Jul 10 Jul 17 Jul 24 Jul 31 Aug 7 Aug 14 Aug 21 Aug 28 Sep 4 Sep 11 Sep 18 Sep 25 Oct 2 Oct 9 Oct 16 Oct 23 Oct 30
79 Wall Structure From EL. +1.95 to +4.30 17 days Sat 7/30/22
80 Reinforcement work 6 days Sat 7/30/22
81 Formwork 5 days Fri 8/5/22
82 Concrete pouring 1 day Wed 8/10/22
83 Taking off formwork 2 days Sat 8/13/22
84 Concrete Top Slab 22 days Mon 8/15/22
85 Formwork 10 days Mon 8/15/22
86 Reinforcement work 6 days Thu 8/25/22
87 Concrete pouring 1 day Wed 8/31/22
88 Taking off formwork 2 days Sun 9/4/22
89 Leak test 5 days Tue 9/6/22
90 Piping Installation 5 days Thu 9/15/22
91 Inlet ‐ outlet piping and valve installation 5 days Thu 9/15/22
92 Electrical & Instrument Installation 2 days Sat 9/17/22
93 Instrument (LT) and cabling installation 2 days Sat 9/17/22
94
95 Pump House & Water Meter Building (N) 116.25 d Mon 6/6/22
96 Piling 0 days Sun 7/3/22 7/3
97 Concrete Work 21 days? Mon 6/6/22
98 Cutting square pile 30x30 2 days Sun 6/19/22
99 Sand layer & lean concrete 1 day Tue 6/21/22
100 Formwork for bottom slab 2 days Wed 6/22/22
101 Reinforcement work 5 days Fri 6/24/22
102 Puddle pipe and water stop installation 1 day Wed 6/29/22
103 Formwork for wall up to +1.10 (0.95 m high) 3 days Thu 6/30/22

104 Concrete pouring 1 day Sun 7/3/22


105 Wall +1.10 to +1.95 12 days Sat 7/23/22
106 Wall +1.65 to +4.30 (top of Reservoir) ‐ 1 side  16 days Sun 7/31/22
only
107 Column, beam, floor slab for panel room and  14 days Mon 8/15/22
water meter room
108 Brick wall work 6 days Mon 8/29/22
109 Building ME work (lighting, cabling etc.) 5 days Thu 9/1/22
110 Roof work ‐ suggest: zincalum roof 14 days Fri 9/2/22
111 Door & Window work 7 days Tue 9/6/22
112 Finishing ‐ building 5 days Mon 9/12/22
113 Painting 5 days Sat 9/17/22
114 Mechanical Installation 23 days Sun 9/4/22
115 Piping installation 23 days Sun 9/4/22
116 Pumps installation 3 days Wed 9/7/22
117 Blowers installation 3 days Sat 9/10/22

Task Project Summary Manual Task Start-only Deadline

Project: Draft schedule KIK Split Inactive Task Duration-only Finish-only Progress
Date: Wed 6/15/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
ID Task Name Duration Start 2 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '2
May 8 May 15 May 22 May 29 Jun 5 Jun 12 Jun 19 Jun 26 Jul 3 Jul 10 Jul 17 Jul 24 Jul 31 Aug 7 Aug 14 Aug 21 Aug 28 Sep 4 Sep 11 Sep 18 Sep 25 Oct 2 Oct 9 Oct 16 Oct 23 Oct 30
118 Air compressor installation 2 days Mon 9/12/22
119 Electrical Instrument Installation 5 days Sat 9/17/22
120 Flowmeter installation 5 days Sat 9/17/22
121 Cabling and termination 5 days Sat 9/17/22
122
123 Chlorine Building (O) 116 daysSun 6/19/22
136
137 Guard House (A) 19 days Wed 5/25/22
144
145 Sludge Pond (L) 51 days Sun 8/14/22
154
155 Office (B) 94 days Thu 5/19/22
193
194 Upper Storage Chemical Tank 45 days Wed 6/1/22
205
206 Power House (E) 73 days Sun 6/26/22
219
220 Diesel Fuel Tank (F) 50 days Wed 7/13/22
223
224 Screw Press Building (G) 91.25 dayMon 6/6/22
236
237 Filtrate Pond (H) 32 days Tue 7/26/22
241
242 Catwalk/ sky walk (I) 67.25 dayMon 7/4/22
248
249 Landscape & Fence 42 days Mon 7/25/22
256
257 Fire Fighting/Hydrant 65 days Mon 6/20/22
260
261 PRECOMM & COMMISSIONING 15 days Sun 10/9/22

Task Project Summary Manual Task Start-only Deadline

Project: Draft schedule KIK Split Inactive Task Duration-only Finish-only Progress
Date: Wed 6/15/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4

You might also like