I WTP INLET 1 Pemasangan flowmeter, turbidity meter, pH meter, kabel dll No subcont Not Yet
2 Pasang jalur dan valve sampling air baku dan pipa gardening Harian ME Anto Not Yet
3 Finish Box Chumber Subcont Minardi M. Fajar AB Not Yet
4 Koneksi Pipa HDPE WTP 2 Subcont Minardi Anto Not Yet
II RESERVOIR 1 Pelepasan/Pembongkaran Begesting Atap Di Dalam Reservoar Subcont Buchori Wasta Close
2 Water Proofing Lantai dan Dinding Bagian Dalam Serta Atap Subcon Dwi Karya Wasta On Proggress
3 Pemasangan U-Ditch 60x60 dan 30x30 Subcont Minardi Wasta On Proggress
Pengecoran Rabat Beton Keliling Reservoar Antara U-Ditch Dengan
4 Harian Sipil Wasta Not Yet
Dinding Reservoir
5 Pengurukan Tanah Kembali Harian Sipil Wasta Not Yet
6 Pemasangan Penstock Clear Well Harian ME Anto Close
7 Pemasangan Tutup Manhole (10 set) CV. Wira Jaya Wasta Not Yet
8 Pemasangan Tangga Monyet (10 set) Harian ME Anto Close
9 Pemasangan Pipa Overflow Subcont Minardi Wasta Close
10 Pengecatan Dinding Luar Mandor Yono Wasta Not Yet
11 Pemasangan Level Transmitter dan Level Switch No Subcont Not Yet
12 Scred Dak Atap Mandor Yono Wasta Not Yet
III PUMP HOUSE 1 Perapihan Lantai, Atap dan Dinding Beton Mandor Yono M. Fajar AB On Proggress
+ PANEL ROOM
+ WATERMETER ROOM 2 Finishing Expose Dinding, Lantai dan Atap Bagian Bawah Mandor Yono M. Fajar AB On Proggress
3 Epooxy Coating Lantai Dalam Pump Room No Subcont Not Yet
Pasang tangga besi, railing dan Finishingnya (area antara Pump Room -
4 CV. Wira Jaya M. Fajar AB Not Yet
Panel Room)
5 Pasang Dinding Bata dan Finishing plester acian Mandor Yono M. Fajar AB Close
Pasang Dinding dan plester acian Parapet tinggi 1,2 m' Antara
6 Mandor Yono M. Fajar AB Not Yet
Watermeter Room - Pump Room
7 Pengecoran Rabat Beton Bagian Luar PUMP HOUSE Mandor Yono M. Fajar AB Not Yet
8 Pengurukan Tanah Kembali Harian Sipil M. Fajar AB Not Yet
9 Pengecatan dinding dan Atap Beton. Mandor Yono M. Fajar AB Not Yet
10 Pemasangan U -Ditch keliling 30x30 Subcont Minardi M. Fajar AB On Proggress
11 Pasang Kusen, Pintu-pintu + Ventilasi/jalusi CV. Wira Jaya M. Fajar AB Not Yet
Pasang Pompa-pompa Distribusi, Backwash, Service Water, Chlorine
12 Subcont Minardi M. Fajar AB On Proggress
Booster
13 Pasang Kompresor, Air Dryer, Air Receiver Tank dan Aksesoris Subcont Minardi M. Fajar AB Not Yet
14 Pasang Air Blower dan Aksesoris Subcont Minardi M. Fajar AB Not Yet
15 Pasang Pipa-pipa Air, Udara dan Kelengkapannya Subcont Minardi M. Fajar AB Not Yet
16 Pasang Hoist Crane + Girder + Konsol dan Kelengkapannya Subcont Minardi M. Fajar AB Not Yet
17 Pasang Instalasi Lampu Penerangan Lengkap Box Panelnya Harian ME Anto Not Yet
18 Pasang MCC-02, Local Panel No Subcont Not Yet
19 Pasang Kabel Power Lengkap Box Panelnya No Subcont Not Yet
20 Pasang Kabel Kontrol, Kabel Data Dengan Kelengkapannya No Subcont Not Yet
21 Pasang Lampu2 Penerangan, Stop Kontak dll Harian ME Anto Not Yet
Pasang flowmeter, turbidity meter, pressure transmitter, residual
22 No Subcont Not Yet
chlorine analyzer dan kabel-kabel
23 Pasang Grill Penutup Cable Trench di Ruang Panel No Subcont Not Yet
24 Pasang Exhaust Fan Harian ME Anto Not Yet
25 Pasang Grounding 1 Set Subcont Minardi M. Fajar AB Not Yet
26 Marking Jalur Pipa dan Kabel Harian ME Anto Not Yet
27 Cat Dinding Luar dan Dalam Mandor Yono M. Fajar AB On Proggress
IV CLORINE BUILDING 1 Pemasangan dinding bata dan plesteran, acian Mandor Yono M. Fajar AB Close
2 Perapihan kolom dan atap beton (expose) Mandor Yono M. Fajar AB On Proggress
3 Finishing lantai (epoxy) No Subcont Not Yet
4 Pengecatan dinding dan atap beton Mandor Yono M. Fajar AB Not Yet
5 Pasang lampu2 penerangan Harian ME Anto Not Yet
6 Pasang pipa menuju Chlorine Building dari Pump House Subcont Minardi M. Fajar AB Not Yet
Pasang pipa keluar Chlorine Building ke titik injeksi Flowmeter Chamber
7 Subcont Minardi M. Fajar AB Not Yet
dan Filter Outlet pipe menuju Reservoir
8 Pasang rabat keliling dan u-ditch keliling Subcont Minardi M. Fajar AB Not Yet
9 Instalasi pipa drain area scarabel Harian ME Anto Not Yet
CATATAN: PEMASANGAN SISTEM ME OLEH VENDOR METITO
VII SCREW PRESS BUILDING 1 Pasang tangga, Railing di lantai - 2 CV. Wira Jaya M. Fajar AB Not Yet
2 Finishing dan Pengecatan Mandor Yono M. Fajar AB Close
3 Setting screw press, sambung perpipaan, kabel, panel dll Subcont Minardi M. Fajar AB Not Yet
4 Pemasangan pipa2 mesin, sistem polimer, effluent Subcont Minardi M. Fajar AB Not Yet
5 Tangga + platform untuk preparasi polimer dan inspeksi screw press No Subcont Not Yet
VIII POWER HOUSE HOUSE 1 Setting mesin genset Subcont Minardi Mulyono Not Yet
2 Setting panel ke M/C Genset Subcont Minardi Mulyono Not Yet
3 Pasang U-DITCH Subcont Minardi Mulyono Close
4 Cor beton Rabat (belakang) Mandor Yono M. Fajar AB Close
5 Cor Akses Ram Mandor Yono M. Fajar AB Not Yet
6 Pasang lampu2 penerangan Harian ME Anto Close
IX CHEMICAL STORAGE AREA 1 Pasang U-DITCH 30x30 keliling Subcont Minardi Mulyono Not Yet
2 Cor beton Rabat Keliling Mandor Yono Mulyono Close
3 Pengecatan dinding dan kolom2 Mandor Yono Mulyono Close
4 Ekspose Kolom & Dak plafond Mandor Yono Mulyono Close
5 Pasang tangga ke lantai -2 , platform dan railing CV. Wira Jaya M. Fajar AB Not Yet
6 Pasang lampu2 penerangan Harian ME Anto Not Yet
7 Pasang level switch, JB, kabel dll Harian ME Anto Not Yet
8 Marking jalur pipa dan kabel Harian ME Anto Close
Pasang plafon gipsum (area internal) dan plafon GRC (area external dan
X OFFICE BUILDING 1 Mandor Yono Ipan Close
Office)
2 Pemasangan plinth dan nat keramik lantai dan dinding Mandor Yono Ipan Close
3 Pasang closet, wastafel, sink, kran, floor drain dan accessoris Mandor Yono Ipan On Proggress
4 Perbaiki posisi tangki Air bersih /Toren dan pasang pipa Mandor Yono Ipan Close
5 Pasang Parapet Area Tangki air Bersih Mandor Yono Ipan Close
6 Pasang pompa booster, tangki pressure dan perpipaan Harian ME Anto Not Yet
7 Pasang keramik eksterior area bawah kanopi Mandor Yono Ipan Not Yet
8 Cat dinding dan Plafon Mandor Yono Ipan Close
9 Pasang Kusen, Pintu dan Jendela besi dan aluminium CV. Wira Jaya Ipan On Proggress
10 Pasang Atap Canopi CV. Wira Jaya Ipan On Proggress
11 Pasang U-DITCH Subcont Minardi Ipan Close
12 Pasang Rabat Beton Mandor Yono Ipan Close
13 Pasang pipa2 instalasi air bersih dan air kotor Mandor Yono Ipan Close
14 Pasang bioseptic tank + sumur resapan + pipa buangan Harian Sipil Ipan Not Yet
15 Pasang stiker anti slip tangga Harian ME Anto Not Yet
16 Pasang tangga ke tandon, parapet dak lantai 3 (area tandon) Harian ME Anto Not Yet
17 Pasang handrail area tangga CV. Wira Jaya Ipan Not Yet
18 Pasang lampu2 penerangan beserta saklar Harian ME Anto Close
19 Pasang stopkontak, exit sign Harian ME Anto Close
20 Pasang AC dan exhaust fan Harian ME Anto On Proggress
21 Pasang jalur sampling air baku dan air produk Harian ME Anto Not Yet
22 Sambung jalur pipa air bersih dan air kotor Office Harian ME Anto Close
23 Pasang panel MCC-01, panel lokal dosing, JB dll Harian ME Anto Not Yet
24 Pasang kabel, tray,support dll Harian ME Anto Not Yet
25 Pasang grounding 1 set Subcont Minardi Anto Not Yet
Pasang level switch Chemical Area, perpipaan untuk sistem permanen
26 Subcont Minardi Anto Close
(sekarang baru untuk temporary)
27 Pasang emergency shower and eye wash Harian ME Anto Close
28 Pasang SCADA Vendor Metito Not Yet
29 Pasang sistem PABX Harian ME Anto Close
30 Pasang CCTV dan kabel 6 titik Harian ME Anto Close
31 Pasang fire alarm system di office Harian ME Anto Close
32 Marking jalur pipa dan kabel Harian ME Anto Close
XI GUARD HOUSE 1 Pasang kusen pintu dan jendela CV. Wira Jaya Mulyono On Proggress
2 Pengecatan dinding dan plafon Mandor Yono Mulyono Close
3 Pasang listrik penerangan, stop kontak, AC Harian ME Anto Close
4 Pasang U-DITCH keliling Subcont Minardi Mulyono Close
5 Pasang keramik lantai dan dinding Mandor Yono Mulyono Close
6 Pasang closet, wastafel, kran dan pemipaanya Mandor Yono Mulyono On Proggress
XII SLUDGE POND 1 Pasang Sludge Pump, guide drail, chain, pipa, kabel dll Subcont Minardi Wasta Not Yet
2 Pasang level switch, kabel, JB dll Subcont Minardi Wasta Not Yet
3 Cat gawangan untuk maintenance pompa Subcont Minardi Wasta Not Yet
4 Pasang pipa jalur sludge pump ke screw press Subcont Minardi Partono On Proggress
5 Marking jalur pipa dan kabel Harian ME Anto Not Yet
XIII FUEL DIESEL TANK 1 Pasang pipa jalur solar ke day tank Genset Subcont Minardi Mulyono Not Yet
2 Cat Ulang Pondasi Harian Sipil Mulyono Close
XIV FIRE PUMP BUILDING 1 Pasang kolom baja, bondek dan balok atap baja CV. Wira Jaya M. Fajar AB Close
2 Pembesian Atap Mandor Yono M. Fajar AB On Proggress
3 Cor atap bangunan Mandor Yono M. Fajar AB Not Yet
4 Pasang dinding bata + Plester acian Mandor Yono M. Fajar AB Not Yet
5 Pasang kusen, pintu jendela, penerangan CV. Wira Jaya M. Fajar AB Not Yet
6 Pasang grounding 1 set Subcont Minardi M. Fajar AB Not Yet
7 Pasang u-ditch keliling Subcont Minardi M. Fajar AB On Proggress
8 Pasang kabel menuju bangunan Harian ME Anto Not Yet
CATATAN: PEMASANGAN SISTEM ME OLEH VENDOR METITO
XV LANDSCAPE Pasang penangkal petir + pondasi + grounding 1 set Harian Sipil Ipan Not Yet
Pasang PJU (14 set) + panel + kabel No Subcont Not Yet
Buat jalan akses lebar 5 m + u-ditch, kanstin, paving block dll PT. Setia Ipan On Proggress
Buat dan pasang pagar keliling + pondasi No Subcont On Proggress
Jembatan antara Office - WTP CV. Wira Jaya Ipan On Proggress
Tanaman landscape No Subcont Not Yet
Paving block, trotoar dll Subcont Minardi Ipan Not Yet
DAFTAR PEKERJAAN YANG HARUS DIKEBUT DAN STATUSNYA
9. Pasang tulang ikan, lantai nozzle dan support, pasang nozzle, media
10. Pasang elbow pipa backwash ND 200 (tidak ada barangnya)
11. Pasang manhole WTP2
12. Selesaikan pasangan batu kali di bawah WTP (sisa 1 meter)
13. Pemasangan Atap
14. Pemasangan U-DITCH
15. Pengurukan tanah kembali
16. Pasang Railing
17. Pasang Grill penutup Flocculator - Break Tank
18. Pasang lampu2 penerangan
19. Pasang aktuator + limit switch valve
20. Pasang jalur angin untuk valve
21. Pasang panel selector switch, JB, kabel2
22. Marking jalur pipa dan kabel
X BANG. OFFICE 1. Pasang plafon gipsum (area internal) dan plafon GRC (area external
dan Office)
2. Pemasangan plinth dan nat keramik lantai dan dinding
3. Pasang closet, wastafel, sink, kran, floor drain dan accessoris
4. Perbaiki posisi tangki Air bersih /Toren dan pasang pipa
5. Pasang pompa booster, tangki pressure dan perpipaan
6. Pasang keramik eksterior area bawah kanopi
7. Cat dinding dan Plafon
8. Pasang Kusen, Pintu dan Jendela besi dan aluminium
9. Pasang Atap Canopi
10. Pasang U-DITCH
11. Pasang Rabat Beton
12. Pasang pipa2 instalasi air bersih dan air kotor
13. Pasang bioseptic tank + sumur resapan + pipa buangan
14. Pasang stiker anti slip tangga
15. Pasang tangga ke tandon, parapet dak lantai 3 (area tandon)
16. Pasang handrail area tangga
17. Pasang lampu2 penerangan beserta saklar
18. Pasang stopkontak, exit sign
19. Pasang AC dan exhaust fan
20. Pasang jalur sampling air baku dan air produk
21. Sambung jalur pipa air bersih dan air kotor Office
22. Pasang panel MCC-01, panel lokal dosing, JB dll
23. Pasang kabel, tray,support dll
24. Pasang grounding 1 set
25. Pasang level switch Chemical Area, perpipaan untuk sistem
permanen (sekarang baru untuk temporary)
26. Pasang emergency shower and eye wash
27. Pasang SCADA
28. Pasang sistem PABX
29. Pasang CCTV dan kabel 6 titik
30. Pasang fire alarm system di office
31. Marking jalur pipa dan kabel
XII SLUDGE POND 1. Pasang Sludge Pump, guide drail, chain, pipa, kabel dll
2. Pasang level switch, kabel, JB dll
3. Cat gawangan untuk maintenance pompa
4. Pasang pipa jalur sludge pump ke screw press
5. Marking jalur pipa dan kabel
XIII FUEL DIESEL TANK 1. Pasang pipa jalur solar ke day tank Genset
XIV FIRE PUMP BUILDING 1. Pasang kolom baja, bondek dan balok atap baja
2. Cor atap bangunan
3. Pasang dinding bata
4. Pasang kusen, pintu jendela, penerangan
5. Pasang grounding 1 set
6. Pasang u-ditch keliling
7. Pasang kabel menuju bangunan
CATATAN: PEMASANGAN SISTEM ME OLEH VENDOR METITO