1 Proposal Writing 3 days Mon 27/06/22
2 Literature Review 4 days Mon 27/06/22
3 Problem statement 1 day Wed 29/06/22
4 Justification 1 day Mon 27/06/22
5 Method Design 9 days Tue 28/06/22
6 Experimentation 28 days Tue 05/07/22
7 Result Analysis 2 days Fri 12/08/22
8 Documentation 4 days Tue 16/08/22
9 Draft and Revise Final 6 days Mon
Report 22/08/22
10 Project Presentation 1 day Thu 01/09/22