ID Task Task Name Duration Start Finish Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half

h Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode S O N D J FMAM J J A S ON D J FMAM J J A S O N D J FMAM J J A S
1 IFM TRANSFORMATION PLAN (ROAD MAP) 726 days Fri 20/10/17 Fri 31/07/20

2 Internal Peer Challenge of Strategy 11 days Fri 20/10/17 Fri 03/11/17

3 Project Opportunity Framing 5 days Mon 06/11/17Fri 10/11/17

4 JV Partner Engagement 10 days Mon 13/11/17Fri 24/11/17

5 Development of Tender Document 15 days Mon 04/12/17Fri 22/12/17

6 Part A/Tender Strategy 14 days Tue 09/01/18 Fri 26/01/18

7 Tendering (Technical) 23 days Mon 19/02/18Wed 21/03/18

8 Tendering (Commercial) 29 days Mon 23/04/18Thu 31/05/18

9 Award 10 days Fri 15/06/18 Thu 28/06/18

10 Premobilisation 21 days Tue 03/07/18 Tue 31/07/18

11 Contract Start 523 days Wed 01/08/18Fri 31/07/20

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: Project1 Milestone Inactive Milestone Start-only


Date: Mon 30/10/17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress