MOTORTRADE NATIONWIDE CORPORATION

CALAPAN, ORIENTAL MINDORO


SP Racks - Third Ace Construction
ID WORK DESCRIPTION Duration Start Finish
27 Feb '22 06 Mar '22 13 Mar '22 20 Mar '22 27 Mar '22
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1
2 GENERAL REQUIREMENTS 7 days? Wed 23/03/22 Thu 31/03/22
3 Site Inspection and Measurement 2 days? Tue 01/03/22 Wed 02/03/22
4 Purchasing and Fabrication 5 days Wed 23/03/22 Tue 29/03/22
5 Installation and Setup 4 days Tue 29/03/22 Fri 01/04/22
6 Mobilization and Demobilization 2 days Wed 30/03/22 Thu 31/03/22

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Project: GANTT CHART FOR SP RA
Date: Mon 21/02/22 Summary Duration-only Progress
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only

Page 1