BAR CHART SCHEDULE

DESIGN AND BUILD CONTRACTOR FOR


HANG NADIM INTERNATIONAL AIRPORT DEVELOPMENT PROJECT AT BATAM
ID Task Name Duration Start Finish
Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Zone 73 88 days Fri 11/08/23 Tue 07/11/23 11/08 07/11
2 Shop Drawing 7 days Tue 15/08/23 Tue 22/08/23 15/08 22/08
3 Material Approval 7 days Tue 15/08/23 Tue 22/08/23 15/08 22/08
4 Purchase Order 77 days Wed 23/08/23 Tue 07/11/23 23/08 07/11
5 Administration 7 days Fri 11/08/23 Sat 19/08/23 11/08 19/08
6 Hoarding Installation 3 days Sun 20/08/23 Tue 22/08/23 20/08 22/08
7 Construction 60 days Wed 23/08/23 Sat 21/10/23 23/08 21/10
8 Demolition 10 days Wed 23/08/23 Fri 01/09/23 23/08 01/09
9 Partition 10 days Thu 12/10/23 Sat 21/10/23 12/10 21/10
10 Ceiling 10 days Mon 02/10/23 Wed 11/10/23 02/10 11/10
11 Plumbing 10 days Sat 02/09/23 Mon 11/09/23 02/09 11/09
12 Electrical 10 days Tue 12/09/23 Thu 21/09/23 12/09 21/09
13 VAC 8 days Fri 22/09/23 Fri 29/09/23 22/09 29/09
14 Fire Fighting 12 days Sat 30/09/23 Wed 11/10/23 30/09 11/10
15 Electronics 10 days Mon 02/10/23 Wed 11/10/23 02/10 11/10

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline

Milestone Inactive Summary Start-only Critical

Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

You might also like