1 362 days Tue 09/08/22 Sun 20/08/23 09/08 20/08
NEW AHM PLANT PAKET 2
2 PREPARATION 13 days Tue 09/08/22 Sun 21/08/22 09/08 21/08
3 DIECASTING BUILDING 341 days Mon 22/08/22 Sat 12/08/23 22/08 12/08
4 A. STRUCTURE 228 days Mon 22/08/22 Thu 06/04/23 22/08 06/04
5 1. PILECAP & BEAM 75 days Mon 22/08/22 Fri 04/11/22 22/08 04/11
6 2. STEEL STRUCTURE (BY OTHERS) 75 days Fri 14/10/22 Tue 27/12/22 14/10 27/12
7 3. ROOF 90 days Fri 04/11/22 Wed 01/02/23 04/11 01/02
8 4. SLAB BASEMENT 90 days Wed 21/09/22 Mon 19/12/22 21/09 19/12
9 5. RETAINING WALL 90 days Wed 12/10/22 Mon 09/01/23 12/10 09/01
10 6. SLAB FIRST FLOOR 100 days Fri 25/11/22 Sat 04/03/23 25/11 04/03
11 7. COLUMN COMPOSITE 90 days Sun 25/12/22 Fri 24/03/23 25/12 24/03
12 8. COLUMN OFFICE 30 days Wed 15/02/23 Thu 16/03/23 15/02 16/03
13 9. ROOF SLAB (OFFICE) 30 days Wed 08/03/23 Thu 06/04/23 08/03 06/04
14 B. ARCHITECTURE 202 days Sun 08/01/23 Sat 12/08/23 08/01 12/08
15 1. FASCIA 45 days Tue 21/02/23 Thu 06/04/23 21/02 06/04
16 2. DINDING LUAR PRECAST 75 days Sun 08/01/23 Thu 23/03/23 08/01 23/03
17 3. DINDING LUAR SANDWICH PANEL 60 days Mon 30/01/23 Thu 30/03/23 30/01 30/03