ID Task Task Name Duration Start Finish Qtr 1, 2023 Qtr 2, 2023

Mode Dec Jan Feb Mar Apr May Jun


1 TANK FARM 99 days Sat 2/4/23 Sat 5/13/23
2 START 0 days Sat 2/4/23 Sat 2/4/23 2/4
3 PREPARATION 16 days Sat 2/4/23 Sun 2/19/23
4 Methode, RA & JSA 3 days Sat 2/4/23 Mon 2/6/23
5 Mobilisasi alat + inspeksi 2 days Tue 2/7/23 Wed 2/8/23
6 Excavation (130 m3) 4 days Thu 2/9/23 Sun 2/12/23
7 Dewatering 6 days Thu 2/9/23 Tue 2/14/23
8 Shoring galian 5 days Thu 2/9/23 Mon 2/13/23
9 Mobilisasi material 5 days Thu 2/9/23 Mon 2/13/23
10 Mobilisasi alat + inspeksi 2 days Sun 2/12/23 Mon 2/13/23
11 Pemadatan tanah stamper (per 30 cm) 6 days Tue 2/14/23 Sun 2/19/23
12 CONSTRUCTION 90 days Mon 2/13/23 Sat 5/13/23
13 Foundation Raft 18 days Mon 2/13/23 Thu 3/2/23
14 Compection 4 days Mon 2/13/23 Thu 2/16/23
15 DCT test 1 day Fri 2/17/23 Fri 2/17/23
16 Lean concrete 1 day Sat 2/18/23 Sat 2/18/23
17 Reinforcement bar 7 days Sun 2/19/23 Sat 2/25/23
18 Formwork 4 days Sun 2/26/23 Wed 3/1/23
19 Pouring concrete 1 day Thu 3/2/23 Thu 3/2/23
20 Foot Plate 22 days Mon 2/13/23 Mon 3/6/23
21 Excavation 5 days Mon 2/13/23 Fri 2/17/23
22 Cutting bore pile 6 days Sat 2/18/23 Thu 2/23/23
23 Compection 5 days Tue 2/21/23 Sat 2/25/23
24 Lean concrete 2 days Sun 2/26/23 Mon 2/27/23
25 Reinforcement bar foot plate 4 days Tue 2/28/23 Fri 3/3/23
26 Formwork foot plate 2 days Sat 3/4/23 Sun 3/5/23
27 Pouring concrete foot plate 1 day Mon 3/6/23 Mon 3/6/23
28 Tie Beam & Pedestal #1 5 days Tue 3/7/23 Sat 3/11/23
29 Reinforcement bar tei beam & pedestal 2 days Tue 3/7/23 Wed 3/8/23

30 Formwork tie beam & pedestal 2 days Thu 3/9/23 Fri 3/10/23
31 Pouring concrete tie beam & pedestal 1 day Sat 3/11/23 Sat 3/11/23
32 Slab 10 days Sun 3/12/23 Tue 3/21/23
33 Reinforcement bar slab 4 days Sun 3/12/23 Wed 3/15/23
34 Formwork slab 2 days Thu 3/16/23 Fri 3/17/23
35 Pouring concrete slab 1 day Sat 3/18/23 Sat 3/18/23
36 Finishing slab 1 day Sun 3/19/23 Sun 3/19/23
37 Joint sealant 2 days Mon 3/20/23 Tue 3/21/23
38 Pedestal #2 8 days Sun 3/19/23 Sun 3/26/23
39 Reinforcement bar pedestal 2 days Sun 3/19/23 Mon 3/20/23
40 Setting anchore 3 days Tue 3/21/23 Thu 3/23/23
41 Formwork pedestal 3 days Tue 3/21/23 Thu 3/23/23
42 Pouring concrete pedestal 1 day Fri 3/24/23 Fri 3/24/23
43 Finishing pedestal 2 days Sat 3/25/23 Sun 3/26/23
44 Bund Wall 9 days Sat 3/25/23 Sun 4/2/23
45 Reinforcement bar pedestal 4 days Sat 3/25/23 Tue 3/28/23
46 Formwork pedestal 2 days Wed 3/29/23 Thu 3/30/23
47 Pouring concrete pedestal 1 day Fri 3/31/23 Fri 3/31/23
48 Finishing pedestal 2 days Sat 4/1/23 Sun 4/2/23
49 Steel Structure Work 22 days Sat 4/22/23 Sat 5/13/23
50 Column 5 days Sat 4/22/23 Wed 4/26/23
51 Beam 5 days Sat 4/22/23 Wed 4/26/23
52 Bracing 5 days Sat 4/22/23 Wed 4/26/23
53 Grouting pedestal 2 days Thu 4/27/23 Fri 4/28/23
54 Install tank farm 7 days Sat 4/29/23 Fri 5/5/23
55 Roof 2 days Sat 5/6/23 Sun 5/7/23
56 Platform 4 days Mon 5/8/23 Thu 5/11/23
57 Stair 2 days Fri 5/12/23 Sat 5/13/23
58 Finish 0 days Sat 5/13/23 Sat 5/13/23 5/13

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Tank Farm
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 2/4/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1