30 Formwork tie beam & pedestal 2 days Thu 3/9/23 Fri 3/10/23
31 Pouring concrete tie beam & pedestal 1 day Sat 3/11/23 Sat 3/11/23
32 Slab 10 days Sun 3/12/23 Tue 3/21/23
33 Reinforcement bar slab 4 days Sun 3/12/23 Wed 3/15/23
34 Formwork slab 2 days Thu 3/16/23 Fri 3/17/23
35 Pouring concrete slab 1 day Sat 3/18/23 Sat 3/18/23
36 Finishing slab 1 day Sun 3/19/23 Sun 3/19/23
37 Joint sealant 2 days Mon 3/20/23 Tue 3/21/23
38 Pedestal #2 8 days Sun 3/19/23 Sun 3/26/23
39 Reinforcement bar pedestal 2 days Sun 3/19/23 Mon 3/20/23
40 Setting anchore 3 days Tue 3/21/23 Thu 3/23/23
41 Formwork pedestal 3 days Tue 3/21/23 Thu 3/23/23
42 Pouring concrete pedestal 1 day Fri 3/24/23 Fri 3/24/23
43 Finishing pedestal 2 days Sat 3/25/23 Sun 3/26/23
44 Bund Wall 9 days Sat 3/25/23 Sun 4/2/23
45 Reinforcement bar pedestal 4 days Sat 3/25/23 Tue 3/28/23
46 Formwork pedestal 2 days Wed 3/29/23 Thu 3/30/23
47 Pouring concrete pedestal 1 day Fri 3/31/23 Fri 3/31/23
48 Finishing pedestal 2 days Sat 4/1/23 Sun 4/2/23
49 Steel Structure Work 22 days Sat 4/22/23 Sat 5/13/23
50 Column 5 days Sat 4/22/23 Wed 4/26/23
51 Beam 5 days Sat 4/22/23 Wed 4/26/23
52 Bracing 5 days Sat 4/22/23 Wed 4/26/23
53 Grouting pedestal 2 days Thu 4/27/23 Fri 4/28/23
54 Install tank farm 7 days Sat 4/29/23 Fri 5/5/23
55 Roof 2 days Sat 5/6/23 Sun 5/7/23
56 Platform 4 days Mon 5/8/23 Thu 5/11/23
57 Stair 2 days Fri 5/12/23 Sat 5/13/23
58 Finish 0 days Sat 5/13/23 Sat 5/13/23 5/13
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Tank Farm
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 2/4/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress