WWTP Odor Control Preliminary Project Schedule (Medium-term Scheme)

ID Task Name Duration Start Finish 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
O N D J F M A M J J A S O N D J F M A M J J A S O N D
1
2 1 Terms of Reference 1 mon Mon 2/5/18 Fri 3/2/18
3
4 2 Contract Administration 85 days Mon 2/5/18 Fri 6/1/18 Contract Administration
5 2.1 Bid-out for 75 days Mon 2/5/18 Fri 5/18/18
Construction
6 2.1.1 Work Order 1 wk Mon 2/5/18 Mon 2/12/18
Requisition Preparation &
Approval

7 2.1.2 Service Number 1 wk Mon 2/12/18 Mon 2/19/18


Request & Shopping Cart
Creation
8 2.1.3 Shopping Cart 2 wks Mon 2/19/18 Mon 3/5/18
Approval
9 2.1.4 Pre-bid Meeting & 1 wk Mon 3/5/18 Fri 3/9/18
Submission of Bids
10 2.1.5 Technical & 1 mon Mon 3/12/18 Fri 4/6/18
Commercial Proposal by
Contractors
11 2.1.6 Evaluation & 1 mon Mon 4/9/18 Fri 5/4/18
Approval of Technical Bid
Proposals
12 2.1.7 Evaluation & 2 wks Mon 5/7/18 Fri 5/18/18
Approval of Commercial
Bid Proposals
13 2.2 Award of Construction 10 days Mon 5/21/18 Fri 6/1/18
Contract
14 2.2.1 Award of Contract & 1 wk Mon 5/21/18 Fri 5/25/18
PO Creation
15 2.2.2 Pre-Construction 2 wks Mon 5/21/18 Fri 6/1/18
Meeting up to
Contractor's Submission
of Requirements

16
17 3 EPC Contract 390 days Mon 5/28/18 Fri 11/22/19 EPC Contract
18 3.1 Engineering 80 days Mon 5/28/18 Fri 9/14/18
19 3.1.1 Basic Engineering 2 mons Mon 5/28/18 Fri 7/20/18
20 3.1.2 Detailed Engineering2 mons Mon 7/23/18 Fri 9/14/18
21 3.2 Procurement 180 days Mon 9/17/18 Fri 5/24/19
22 3.2.1 Material 1 mon Mon 9/17/18 Fri 10/12/18
Procurement
23 3.2.2 Delivery of Materials160 days Mon 10/15/18 Fri 5/24/19
24 3.2.2.1 Pressure Vessel 30
(Fabrication
wks & Mon
Delivery)
10/15/18 Fri 5/10/19
25 3.2.2.2 Blower 8 mons Mon 10/15/18 Fri 5/24/19
26 3.2.2.3 Motor & Power Cable
24 wks Mon 10/15/18 Fri 3/29/19
27 3.2.2.4 Piping 14 wks Mon 10/15/18 Fri 1/18/19
28 3.2.2.5 Pressure Safety 28
Valve
wks Mon 10/15/18 Fri 4/26/19
29 3.2.2.6 Cover & 3 mons Mon 10/15/18 Fri 1/4/19
Structural Steel
30 3.2.3 Bonds & Insurances 2 wks Mon 9/17/18 Fri 9/28/18

31 3.2.4 Construction 2 wks Mon 9/17/18 Fri 9/28/18


Permits & Licenses

32 3.3 Construction 300 days Mon 10/1/18 Fri 11/22/19


33 3.3.1 Preliminaries 20 days Mon 10/1/18 Fri 10/26/18
34 3.3.1.1 Temporary 1 mon Mon 10/1/18 Fri 10/26/18
Facilities & Utilities
35 3.3.1.2 Mobilization 1 mon Mon 10/1/18 Fri 10/26/18
36 3.3.2 Earthworks 180 days Mon 10/29/18 Fri 7/5/19
37 3.3.2.1 Demolition Works
2 mons Mon 10/29/18 Fri 12/21/18
38 3.3.2.2 Excavation 2 mons Mon 11/26/18 Fri 1/18/19
39 3.3.2.3 Gravel Bedding 1 mon Mon 12/24/18 Fri 1/18/19
40 3.3.2.4 Backfilling 2 mons Mon 5/13/19 Fri 7/5/19
41 3.3.2.5 Disposal 1 mon Mon 6/10/19 Fri 7/5/19
42 3.3.3 Concreting & 100 days Mon 1/21/19 Fri 6/7/19
Structural Works
43 3.3.3.1 Foundation 3 mons Mon 1/21/19 Fri 4/12/19
Footing
44 3.3.3.2 Footing Tie-Beam
3 mons Mon 2/18/19 Fri 5/10/19
45 3.3.3.3 Pedestal 3 mons Mon 3/18/19 Fri 6/7/19
46 3.3.4 Structural Steel 130 days Mon 4/29/19 Fri 10/25/19
Works
47 3.3.4.1 Fabrication of 3 mons Mon 4/29/19 Fri 7/19/19
Structural Steel
48 3.3.4.2 Erection & 5 mons Mon 6/10/19 Fri 10/25/19
Installation of Cover

49 3.3.4.3 Auxiliary Works 2 mons Mon 9/2/19 Fri 10/25/19


50 3.3.5 Mechanical & Electrical
75 days
Works Mon 6/10/19 Fri 9/20/19
51 3.3.5.1 Pressure 1 mon Mon 6/10/19 Fri 7/5/19
Vessel Erection
52 3.3.5.2 Blower & Motor Installation
1 mon Mon 6/24/19 Fri 7/19/19
53 3.3.5.3 Power Cable Routing
2 wks Mon 7/8/19 Fri 7/19/19
54 3.3.5.4 Piping Fabrication
3 mons
& Erection Mon 7/1/19 Fri 9/20/19
55 3.3.6 Post Construction 40 days Mon 9/30/19 Fri 11/22/19

56 3.3.6.1 Painting 1 mon Mon 9/30/19 Fri 10/25/19


57 3.3.6.2 Commissioning 1 mon Mon 10/28/19 Fri 11/22/19
58 3.3.6.3 Demobilization 2 wks Mon 11/11/19 Fri 11/22/19

Prepared by: M. A. Del Mundo