ID Task Name Duration Start Finish Qtr 3, 2018 Qtr 4, 2018
Jun Jul Aug Sep Oct
40 5.3. CALCULATION 11 days Fri 9/14/18 Mon 9/24/18
41 Cable Sizing 11 days Fri 9/14/18 Mon 9/24/18
42 5.4. DRAWING 10 days Mon 9/3/18Wed 9/12/18
43 Electrical Equipment Layout 10 days Mon 9/3/18 Wed 9/12/18
44 5.5. MATERIAL TAKE OFF 3 days Thu 9/13/18Sat 9/15/18
45 Material Take Off 3 days Thu 9/13/18Sat 9/15/18
46 6. INSTRUMENT 34 days Thu 7/19/18Tue 8/21/18
47 6.1. SPECIFICATION 3 days Thu 7/19/18Sat 7/21/18
48 Instrument Specification - 3 days Thu Sat 7/21/18
Mounted Instrument 7/19/18
49 6.2. DATA SHEET 5 days Thu 8/9/18 Mon 8/13/18
50 Instrument Data Sheet - Temperature 3 days
Gauge Thu 8/9/18 Sat 8/11/18
51 Instrument Data Sheet - Pressure Indicator
5 days Thu 8/9/18 Mon 8/13/18
52 Instrument Data Sheet - Flow Meter5 days Thu 8/9/18 Mon 8/13/18
53 6.3. LIST 3 days Tue 8/14/18Thu 8/16/18
54 Instrument List 3 days Tue 8/14/18Thu 8/16/18
55 6.4. MATERIAL TAKE OFF 5 days Fri 8/17/18 Tue 8/21/18
56 Material Take Off 5 days Fri 8/17/18 Tue 8/21/18
57 7. CIVIL 64 days Thu 7/19/18Thu 9/20/18
58 7.1. SPECIFICATION 3 days Thu 7/19/18Sat 7/21/18
59 Civil Specification for Foundation 3 days Thu 7/19/18Sat 7/21/18
60 7.2. CALCULATION 10 days Thu 9/6/18 Sat 9/15/18
61 Civil Calculation Sheet for Pipe 10 days Thu 9/6/18 Sat 9/15/18
Support Foundation
62 7.3. DRAWING 12 days Sun 9/9/18 Thu 9/20/18
63 Typical Pipe Support Foundation 5 days Sun 9/16/18Thu 9/20/18
64 Transfer Pump Foundation 5 days Sun 9/9/18 Thu 9/13/18
65 7.4. MATERIAL TAKE OFF 3 days Fri 9/14/18 Sun 9/16/18
66 Material Take Off 3 days Fri 9/14/18 Sun 9/16/18
67 8. PIPING& PIPELINE 49 days Thu 7/19/18Wed 9/5/18
68 8.1. SPECIFICATION 7 days Thu 7/19/18Wed 7/25/18
69 Specification of Pipe, Valve, Fitting 7 days Thu Wed 7/25/18
and Accessories 7/19/18
70 Specification of Welding 7 days Thu 7/19/18Wed 7/25/18
71 8.2. LIST 5 days Thu 8/9/18 Mon 8/13/18
72 Piping List 5 days Thu 8/9/18 Mon 8/13/18
73 Valve List 5 days Thu 8/9/18 Mon 8/13/18
74 8.3. CALCULATION 49 days Thu 7/19/18Wed 9/5/18
75 Pipe Wall Thickness 7 days Thu 7/19/18Wed 7/25/18
76 Pipe Stress Analysis 14 days Thu 8/23/18Wed 9/5/18
77 8.4. DRAWING 40 days Thu 7/19/18Mon 8/27/18
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 2
ID Task Name Duration Start Finish Qtr 3, 2018 Qtr 4, 2018
Jun Jul Aug Sep Oct
78 Drawing Index 5 days Thu 8/23/18Mon 8/27/18
79 Plot Plan Overall 10 days Sat 7/21/18 Mon 7/30/18
80 Piping Isometric Drawing 21 days Thu 8/2/18 Wed 8/22/18
81 Pipe Support Standard Drawing 7 days Thu 7/19/18Wed 7/25/18
82 Pipeline Alignment Sheet Brine 21 days Thu 8/2/18 Wed 8/22/18
83 8.4. MTO 10 days Thu 8/23/18Sat 9/1/18
84 Material Take Off 10 days Thu 8/23/18Sat 9/1/18
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress