ID Task Name Duration Start Finish Qtr 3, 2018 Qtr 4, 2018

Jun Jul Aug Sep Oct


1 0. Hasil Topografi 11 days Tue 7/10/18Fri 7/20/18
2 0. SURVEY 6 days Tue 7/10/18Sun 7/15/18
3 1. GENERAL 67 days Mon 7/16/18Thu 9/20/18
4 Project Planning and Progress 67 days Mon Thu 9/20/18
Measurement Procedure 7/16/18
5 Specification for Construction Inspection
5 days Thu 8/23/18Mon 8/27/18
6 Master Document Register 3 days Mon 7/16/18Wed 7/18/18
7 Project Master Schedule 3 days Mon 7/16/18Wed 7/18/18
8 2. BIDDING 67 days Mon 7/16/18Thu 9/20/18
9 Overall Material Take Off 3 days Mon 9/17/18Wed 9/19/18
10 Project Execution Schedule 67 days Mon 7/16/18Thu 9/20/18
11 3. PROCESS 48 days Mon 7/16/18Sat 9/1/18
12 3.1. GENERAL ASPECT 5 days Mon 7/16/18Fri 7/20/18
13 Basic Engineering Design Data 3 days Mon 7/16/18Wed 7/18/18
14 Process Design Methodology 5 days Mon 7/16/18Fri 7/20/18
15 3.2. CALCULATION 24 days Thu 8/9/18 Sat 9/1/18
16 Heat and Material Balance 7 days Thu 8/9/18 Wed 8/15/18
17 Pipe Sizing 5 days Thu 8/16/18Mon 8/20/18
18 Presure Drop Calculation 10 days Thu 8/23/18Sat 9/1/18
19 Pump Sizing 5 days Thu 8/23/18Mon 8/27/18
20 3.3. DRAWING 24 days Mon 7/16/18Wed 8/8/18
21 Block Flow Diagram 7 days Mon 7/16/18Sun 7/22/18
22 P&ID Symbol and Legend 14 days Thu 7/26/18Wed 8/8/18
23 P&ID Injection System (note: the 14 days Thu Wed 8/8/18
scope is limited for this project) 7/26/18
24 4. MECHANICAL 59 days Thu 7/19/18Sat 9/15/18
25 4.1. SPECIFICATION 7 days Thu 7/19/18Wed 7/25/18
26 Specification of Transfer Pumps 7 days Thu 7/19/18Wed 7/25/18
27 4.2. LIST 3 days Thu 8/9/18 Sat 8/11/18
28 Equipment List 3 days Thu 8/9/18 Sat 8/11/18
29 4.3 DATA SHEET 6 days Mon 9/3/18Sat 9/8/18
30 Data Sheet of Transfer Pumps 6 days Mon 9/3/18 Sat 9/8/18
31 4.4. CALCULATION 6 days Tue 8/28/18Sun 9/2/18
32 Mechanical Calculation of Pumps 6 days Tue 8/28/18Sun 9/2/18
33 4.5. MATERIAL TAKE OFF 7 days Sun 9/9/18 Sat 9/15/18
34 MTO of Mechanical 7 days Sun 9/9/18 Sat 9/15/18
35 5. ELECTRICAL 68 days Thu 7/19/18Mon 9/24/18
36 5.1. SPECIFICATION 3 days Thu 7/19/18Sat 7/21/18
37 Electrical Specification of Electric Motors
3 days Thu 7/19/18Sat 7/21/18
38 5.2. DATA SHEET 5 days Sun 9/9/18 Thu 9/13/18
39 Datasheet of Electric Motors 5 days Sun 9/9/18 Thu 9/13/18
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project Master Schedul
Milestone Inactive Summary Start-only Critical
Date: Tue 7/17/18
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
ID Task Name Duration Start Finish Qtr 3, 2018 Qtr 4, 2018
Jun Jul Aug Sep Oct
40 5.3. CALCULATION 11 days Fri 9/14/18 Mon 9/24/18
41 Cable Sizing 11 days Fri 9/14/18 Mon 9/24/18
42 5.4. DRAWING 10 days Mon 9/3/18Wed 9/12/18
43 Electrical Equipment Layout 10 days Mon 9/3/18 Wed 9/12/18
44 5.5. MATERIAL TAKE OFF 3 days Thu 9/13/18Sat 9/15/18
45 Material Take Off 3 days Thu 9/13/18Sat 9/15/18
46 6. INSTRUMENT 34 days Thu 7/19/18Tue 8/21/18
47 6.1. SPECIFICATION 3 days Thu 7/19/18Sat 7/21/18
48 Instrument Specification - 3 days Thu Sat 7/21/18
Mounted Instrument 7/19/18
49 6.2. DATA SHEET 5 days Thu 8/9/18 Mon 8/13/18
50 Instrument Data Sheet - Temperature 3 days
Gauge Thu 8/9/18 Sat 8/11/18
51 Instrument Data Sheet - Pressure Indicator
5 days Thu 8/9/18 Mon 8/13/18
52 Instrument Data Sheet - Flow Meter5 days Thu 8/9/18 Mon 8/13/18
53 6.3. LIST 3 days Tue 8/14/18Thu 8/16/18
54 Instrument List 3 days Tue 8/14/18Thu 8/16/18
55 6.4. MATERIAL TAKE OFF 5 days Fri 8/17/18 Tue 8/21/18
56 Material Take Off 5 days Fri 8/17/18 Tue 8/21/18
57 7. CIVIL 64 days Thu 7/19/18Thu 9/20/18
58 7.1. SPECIFICATION 3 days Thu 7/19/18Sat 7/21/18
59 Civil Specification for Foundation 3 days Thu 7/19/18Sat 7/21/18
60 7.2. CALCULATION 10 days Thu 9/6/18 Sat 9/15/18
61 Civil Calculation Sheet for Pipe 10 days Thu 9/6/18 Sat 9/15/18
Support Foundation
62 7.3. DRAWING 12 days Sun 9/9/18 Thu 9/20/18
63 Typical Pipe Support Foundation 5 days Sun 9/16/18Thu 9/20/18
64 Transfer Pump Foundation 5 days Sun 9/9/18 Thu 9/13/18
65 7.4. MATERIAL TAKE OFF 3 days Fri 9/14/18 Sun 9/16/18
66 Material Take Off 3 days Fri 9/14/18 Sun 9/16/18
67 8. PIPING& PIPELINE 49 days Thu 7/19/18Wed 9/5/18
68 8.1. SPECIFICATION 7 days Thu 7/19/18Wed 7/25/18
69 Specification of Pipe, Valve, Fitting 7 days Thu Wed 7/25/18
and Accessories 7/19/18
70 Specification of Welding 7 days Thu 7/19/18Wed 7/25/18
71 8.2. LIST 5 days Thu 8/9/18 Mon 8/13/18
72 Piping List 5 days Thu 8/9/18 Mon 8/13/18
73 Valve List 5 days Thu 8/9/18 Mon 8/13/18
74 8.3. CALCULATION 49 days Thu 7/19/18Wed 9/5/18
75 Pipe Wall Thickness 7 days Thu 7/19/18Wed 7/25/18
76 Pipe Stress Analysis 14 days Thu 8/23/18Wed 9/5/18
77 8.4. DRAWING 40 days Thu 7/19/18Mon 8/27/18

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project Master Schedul
Milestone Inactive Summary Start-only Critical
Date: Tue 7/17/18
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 2
ID Task Name Duration Start Finish Qtr 3, 2018 Qtr 4, 2018
Jun Jul Aug Sep Oct
78 Drawing Index 5 days Thu 8/23/18Mon 8/27/18
79 Plot Plan Overall 10 days Sat 7/21/18 Mon 7/30/18
80 Piping Isometric Drawing 21 days Thu 8/2/18 Wed 8/22/18
81 Pipe Support Standard Drawing 7 days Thu 7/19/18Wed 7/25/18
82 Pipeline Alignment Sheet Brine 21 days Thu 8/2/18 Wed 8/22/18
83 8.4. MTO 10 days Thu 8/23/18Sat 9/1/18
84 Material Take Off 10 days Thu 8/23/18Sat 9/1/18

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project Master Schedul
Milestone Inactive Summary Start-only Critical
Date: Tue 7/17/18
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress