ID Task Task Name Duration Start Finish Qtr 4, 2024 Qtr 1, 2025Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025

Qtr 1, 2025Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026Qtr 2, 2026 Qtr 3, 2026 Qtr 4, 2026
Mode Dec Jan FebMarAprMayJun Jul AugSepOctNovDec Jan FebMarAprMayJun Jul AugSepOctNov
1 Deep Water Port Project 627 days Wed 1/1/25 Sat 9/19/26

2 Project Planning 74 days Wed 1/1/25 Sat 3/15/25

3 Business Case 30 days Wed 1/1/25 Thu 1/30/25

4 Develop a Proposal 14 days Fri 1/31/25 Thu 2/13/25

5 Feasibility study 30 days Fri 2/14/25 Sat 3/15/25

6 Project Execution 548 days Sun 3/16/25 Mon 9/14/26

7 Engineering 90 days Sun 3/16/25 Fri 6/13/25

8 Procurement 290 days Thu 5/15/25 Sat 2/28/26

9 Construction 338 days Wed 8/13/25 Thu 7/16/26

10 As built Engineering 60 days Fri 7/17/26 Mon 9/14/26

11 Commissioning & start-up 60 days Fri 7/17/26 Mon 9/14/26

12 Project Closure 5 days Tue 9/15/26 Sat 9/19/26

13 Formal acceptance 5 days Tue 9/15/26 Sat 9/19/26