ID WBS Task Task Name Duration Start Finish Predecessors Successors

Mode
1 1 Electronic Content Management Software 480 days Tue 09-04-19 Fri 05-02-21

2 1.1 Initiation 23 days Tue 09-04-19 Thu 09-05-19


3 1.1.1 Assign key person 10 days Tue 09-04-19 Mon 22-04-19 4,6
4 1.1.2 Developing Project charter 3 days Tue 23-04-19 Thu 25-04-193 5
5 1.1.3 Developing Project teams 10 days Fri 26-04-19 Thu 09-05-194 8
6 1.1.4 Gathering Requirements 7 days Tue 23-04-19 Wed 01-05-193 8
7 1.2 Planning 68 days Fri 10-05-19 Tue 13-08-19
8 1.2.1 Planning timeline schedule 10 days Fri 10-05-19 Thu 23-05-196,5 9
9 1.2.2 Budget Plan 25 days Fri 24-05-19 Thu 27-06-198 10
10 1.2.3 Creating Scope 33 days Fri 28-06-19 Tue 13-08-19 9 13,14,15,16
11 1.3 Analysis and Design 178 days Wed 14-08-19 Fri 17-04-20
12 1.3.1 Analysis 36 days Wed 14-08-19 Wed 02-10-19
13 1.3.1.1 Manual data entry 6 days Wed 14-08-19 Wed 21-08-1910 17
14 1.3.1.2 Access to the documents 4 days Wed 14-08-19 Mon 19-08-1910 17
15 1.3.1.3 Collaboration methods 7 days Wed 14-08-19 Thu 22-08-1910 17
16 1.3.1.4 Fixing Requirements from stakeholders 12 days Wed 14-08-19 Thu 29-08-1910 18

17 1.3.1.5 Fixing software requirements 16 days Fri 23-08-19 Fri 13-09-1913,14,15 19


18 1.3.1.6 Fixing Hardware requirements 20 days Fri 30-08-19 Thu 26-09-1916 19
19 1.3.1.7 Approval of requirements/purchase 4 days Fri 27-09-19 Wed 02-10-1917,18 21

20 1.3.2 Design 142 days Thu 03-10-19 Fri 17-04-20


21 1.3.2.1 Design a framework 14 days Thu 03-10-19 Tue 22-10-19 19 22
22 1.3.2.2 Software Specification 11 days Wed 23-10-19 Wed 06-11-1921 23
23 1.3.2.3 Software Prototype 22 days Thu 07-11-19 Fri 06-12-1922 24
24 1.3.2.4 Software Detailed Design 31 days Mon 09-12-19 Mon 20-01-2023 25
25 1.3.2.5 Software Coding 41 days Tue 21-01-20 Tue 17-03-20 24 26
26 1.3.2.6 software debugging 23 days Wed 18-03-20 Fri 17-04-2025 28,29
27 1.4 Development 79 days Mon 20-04-20 Wed 05-08-20
28 1.4.1 Work environment 20 days Mon 20-04-20 Fri 15-05-2026 36
29 1.4.2 Management Methods 20 days Mon 20-04-20 Fri 15-05-2026 30,31,32,33
30 1.4.3 Document Storage in server 22 days Mon 18-05-20 Mon 15-06-2029 34
31 1.4.4 Document Conversion 19 days Mon 18-05-20 Wed 10-06-2029 34
32 1.4.5 Automated Data Entry 25 days Mon 18-05-20 Thu 18-06-2029 34
33 1.4.6 Mobile Applications 30 days Mon 18-05-20 Thu 25-06-2029 34
34 1.4.7 Searching & retrieving data 14 days Fri 26-06-20 Wed 15-07-2030,31,32,33 35
35 1.4.8 Interfaces to sever 5 days Thu 16-07-20 Wed 22-07-2034 36
connection/collaboration platform
36 1.4.9 Validation Plan 10 days Thu 23-07-20 Wed 05-08-2035,28 38,39
37 1.5 Testing 62 days Thu 06-08-20 Fri 30-10-20
38 1.5.1 Alpha Test 40 days Thu 06-08-20 Wed 30-09-2036 40
39 1.5.2 Beta Test 30 days Thu 06-08-20 Wed 16-09-2036 40
40 1.5.3 Integration test 20 days Thu 01-10-20 Wed 28-10-2038,39 41
41 1.5.4 Release of interface 2 days Thu 29-10-20 Fri 30-10-2040 43
42 1.6 Deployment 70 days Mon 02-11-20 Fri 05-02-21
43 1.6.1 Preparing a Roll Out Plan 4 days Mon 02-11-20 Thu 05-11-2041 44,45
44 1.6.2 Deploying solution components 10 days Fri 06-11-20 Thu 19-11-2043 46
45 1.6.3 Preparing Migration Plan to the new 16 days Fri 06-11-20 Fri 27-11-2043 46
system
46 1.6.4 Validating system and data 30 days Mon 30-11-20 Fri 08-01-2144,45 47
47 1.6.5 Launch Product 4 days Mon 11-01-21 Thu 14-01-2146 48
48 1.6.6 Conducting User survey 16 days Fri 15-01-21 Fri 05-02-2147