sh '20 Feb '20 Mar '20 Apr '20 May '20 Jun '20 Jul '20 Aug '20 Sep '20 Oct '20 Nov '20 Dec '21 Jan '21 Feb
0 M2J2%20Project_draft%201 207 daysWed 20-03-18
Thu 20-12-31
5 1.1.3. Finalise speicifcations for online platform 3 days Thu 20-03-26Mon 20-03-30
8 1.2.2. Analyse data and develop project charter 3 days Tue 20-03-31 Thu 20-04-02
13 1.4. Technical Side Prep - Online Platform Building7 days Fri 20-05-01 Mon 20-05-11
14 1.4.1. Development and Publication of RFP/ SOW2 days Mon 20-05-11Tue 20-05-12
15 1.4.2. Bids/proposal evaluation 3 days Mon 20-06-01Wed 20-06-03
19 2. Phase - Online Education Platform Development 21 days Mon 20-06-08Mon 20-07-06 07-06
35 4. Phase - Training and launch of the Platform 16 days Mon 20-07-27Mon 20-08-17 08-17
36 4.1. Training of faculty staff, program staff 10 days Mon 20-07-27Fri 20-08-07
37 4.1.1. Development of the training module, FAQ3 days Wed 20-08-05Fri 20-08-07
43 4.3. Development of FAQ and support resources 5 days Thu 20-08-13Wed 20-08-19
52 6.2. Preparation of narrative and financial report 6 days Tue 20-12-15 Tue 20-12-22
54 6.4. Report to sponsors and University CEO 7 days Wed 20-12-23Thu 20-12-31
Project: M2J2%20Project_draft% Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Progress Slack
Date: Thu 20-06-25 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Late Manual Progress