Finish 30 Nov '20 07 Dec '20 14 Dec '20 21 Dec '20 28 Dec '20 04 Jan '21 11 Jan '21 18 Jan '21 25 Jan '21 01 Feb '21 08 Feb '21 15 Feb '21 22 Feb '21 01 Mar '21 08 Mar '21 15 Mar '21 22 Mar '21 29 Mar '21 05 Apr '21 12 Apr '21 19 Apr '21 26 Apr '21 03 May '21 10 May '21
Mode WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SM
1
1 Inch APQP time plan 140 days? Thu 03-12-20 Fri 14-05-21
4 Team Feasibility Team feasibility review and risk analysis 8 days Thu 03-12-20 Fri 11-12-20
7 Release of Product Design Document (Drawing/BOM) 8 days Thu 03-12-20 Fri 11-12-20
8 Project Review & Management Support 1 day Fri 11-12-20 Fri 11-12-20
14 Assembly and Leak testing Cell 10 days Sat 05-12-20 Wed 16-12-20
27 Sample submission for Approval to FTW 11 days Thu 31-12-20 Tue 12-01-21
28 Feedback on submitted sample from FTW 4 days Tue 12-01-21 Fri 15-01-21
32 Receipt of Inhouse tooling & Fixtures 14 days Sat 05-12-20 Sun 20-12-20
37 PPAP & Part Submission Warrant Sign off 8 days Mon 15-02-21 Tue 23-02-21
Project: 1 Inch project. Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Thu 03-12-20 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress