ID Task Task Name Duration Start Finish

Mode
2024
2019 2020 2021 2022 2023 2024 2025 2026 2027
1 SUNSHINE, SHRIRAM GRAND CITY, KONNAGAR 1651 days Wed 01-01-20 Mon 08-07-24
2 Pre Construction Activities 347 days Wed 01-01-20 Sun 13-12-20
3 Issuance of LOI along with MA 0 days Wed 01-01-20 Wed 01-01-20 01-01
4 Issuance of GFC Drawing 0 days Wed 01-01-20 Wed 01-01-20 01-01
5 Site Mobilization 0 days Wed 01-01-20 Wed 01-01-20 01-01
6 Issuance of PO - MIVAN Shuttering Materials for Tower 2B 0 days Mon 17-08-20 Mon 17-08-20 17-08
7 Issuance of PO - MIVAN Shuttering Materials for Tower 3D, 3E, 2A and 01A
days Wed 14-10-20 Wed 14-10-20 14-10
8 Receival of MIVAN Shuttering Materials for Tower 2B 0 days Fri 16-10-20 Fri 16-10-20 16-10
9 Receival of MIVAN Shuttering Materials for Tower 3D, 3E, 2A and 1A 0 days Sun 13-12-20 Sun 13-12-20 13-12
10 Construction Activities 1646 days Mon 06-01-20 Mon 08-07-24
11 SUNSHINE ONE 1210 days Mon 06-01-20 Sat 29-04-23
12 Pile Foundation Activity (SUNSHINE ONE) 267 days Mon 06-01-20 Mon 28-09-20
13 3D Tower 120 days Mon 01-06-20 Mon 28-09-20 Pile Cost - Sunshine One[₹ 24,924,594.00]
14 3E Tower 120 days Mon 01-06-20 Mon 28-09-20 Pile Cost - Sunshine One[₹ 24,924,594.00]
15 2A Tower 120 days Mon 01-06-20 Mon 28-09-20 Pile Cost - Sunshine One[₹ 18,723,193.00]
16 2B Tower 150 days Mon 06-01-20 Fri 17-07-20 Pile Cost - Sunshine One[₹ 18,723,193.00]
17 1A Tower 120 days Mon 01-06-20 Mon 28-09-20 Pile Cost - Sunshine One[₹ 16,523,479.00]
18 Sub-Structure + Ground Floor Activity 208 days Fri 03-07-20 Tue 26-01-21
19 3D Tower 150 days Sun 30-08-20 Tue 26-01-21
20 3E Tower 150 days Sun 30-08-20 Tue 26-01-21
21 2A Tower 150 days Sun 30-08-20 Tue 26-01-21
22 2B Tower 150 days Fri 03-07-20 Sun 29-11-20
23 1A Tower 150 days Sun 30-08-20 Tue 26-01-21
24 Super-Structure Activity 371 days Mon 30-11-20 Sun 05-12-21
25 3D Tower 313 days Wed 27-01-21 Sun 05-12-21
26 Systemic Slab - with Aluform Shuttering 313 days Wed 27-01-21 Sun 05-12-21
27 1st Slab (Ground Floor) 65 days Wed 27-01-21 Thu 01-04-21
28 2nd Slab (1st Floor) 20 days Fri 02-04-21 Wed 21-04-21
29 3rd Slab (2nd Floor) 13 days Thu 22-04-21 Tue 04-05-21
30 4th Slab (3rd Floor) 13 days Wed 05-05-21 Mon 17-05-21
31 5th Slab (4th Floor) 13 days Tue 18-05-21 Sun 30-05-21
32 6th Slab (5th Floor) 13 days Mon 31-05-21 Sat 12-06-21
33 7th Slab (6th Floor) 13 days Sun 13-06-21 Fri 25-06-21
34 8th Slab (7th Floor) 13 days Sat 26-06-21 Thu 08-07-21
35 9th Slab (8th Floor) 13 days Fri 09-07-21 Wed 21-07-21
36 10th Slab (9th Floor) 13 days Thu 22-07-21 Tue 03-08-21
37 11th Slab (10th Floor) 13 days Wed 04-08-21 Mon 16-08-21
38 12th Slab (11th Floor) 13 days Tue 17-08-21 Sun 29-08-21
39 13th Slab (12th Floor) 13 days Mon 30-08-21 Sat 11-09-21
40 14th Slab (13th Floor) 13 days Sun 12-09-21 Fri 24-09-21
41 15th Slab (14th Floor) 13 days Sat 25-09-21 Thu 07-10-21
42 16th Slab (15th Floor) 13 days Fri 08-10-21 Wed 20-10-21

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: SUNSHINE Split External Tasks Inactive Summary Manual Summary Progress
Date: Fri 17-04-20
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Task Name Duration Start Finish
Mode
2024
2019 2020 2021 2022 2023 2024 2025 2026 2027
43 17th Slab (16th Floor) 13 days Thu 21-10-21 Tue 02-11-21
44 18th Slab (17th Floor) 13 days Wed 03-11-21 Mon 15-11-21
45 19th Slab (18th Floor) 20 days Tue 16-11-21 Sun 05-12-21
46 3E Tower 313 days Wed 27-01-21 Sun 05-12-21
47 2A Tower 313 days Wed 27-01-21 Sun 05-12-21
48 2B Tower 313 days Mon 30-11-20 Fri 08-10-21
49 1A Tower 313 days Wed 27-01-21 Sun 05-12-21
50 Finishing Activity 418 days Thu 09-09-21 Mon 31-10-22
51 3D Tower 360 days Sat 06-11-21 Mon 31-10-22
52 3E Tower 360 days Sat 06-11-21 Mon 31-10-22
53 2A Tower 360 days Sat 06-11-21 Mon 31-10-22
54 2B Tower 360 days Thu 09-09-21 Sat 03-09-22
55 1A Tower 360 days Sat 06-11-21 Mon 31-10-22
56 Infrastructure Activity 480 days Wed 05-01-22 Sat 29-04-23
57 Phase One 480 days Wed 05-01-22 Sat 29-04-23
58 Consultancy & Misc. 1154 days Sat 18-01-20 Sat 29-04-23 Consultancy & Misc.[₹ 38,919,161.00]
59 Escalation and Price Variation 1154 days Sat 18-01-20 Sat 29-04-23 Escalation and Price Variation[₹ 48,580,243.00]
60 Labour cess & Insurance 1154 days Sat 18-01-20 Sat 29-04-23 Labour cess & Insurance[₹ 21,088,464.00]
61 SUNSHINE TWO 1222 days Mon 02-11-20 Thu 07-03-24
62 Pile Foundation Activity (SUNSHINE TWO) 210 days Mon 02-11-20 Sun 30-05-21
63 3A Tower 90 days Mon 02-11-20 Sat 30-01-21
64 3B Tower 90 days Mon 02-11-20 Sat 30-01-21
65 2C Tower 90 days Sun 31-01-21 Fri 30-04-21
66 2D Tower 90 days Sun 31-01-21 Fri 30-04-21
67 1B Tower 120 days Sun 31-01-21 Sun 30-05-21
68 Sub-Structure + Ground Floor Activity 208 days Tue 11-05-21 Sun 05-12-21
69 3A Tower 150 days Thu 08-07-21 Sun 05-12-21
70 3B Tower 150 days Thu 08-07-21 Sun 05-12-21
71 2C Tower 150 days Thu 08-07-21 Sun 05-12-21
72 2D Tower 150 days Tue 11-05-21 Fri 08-10-21
73 1B Tower 150 days Thu 08-07-21 Sun 05-12-21
74 Super-Structure Activity 371 days Sat 09-10-21 Fri 14-10-22
75 3A Tower 313 days Mon 06-12-21 Fri 14-10-22
76 3B Tower 313 days Mon 06-12-21 Fri 14-10-22
77 2C Tower 313 days Mon 06-12-21 Fri 14-10-22
78 2D Tower 313 days Sat 09-10-21 Wed 17-08-22
79 1B Tower 313 days Mon 06-12-21 Fri 14-10-22
80 Finishing Activity 358 days Tue 19-07-22 Tue 11-07-23
81 3A Tower 300 days Thu 15-09-22 Tue 11-07-23
82 3B Tower 300 days Thu 15-09-22 Tue 11-07-23
83 2C Tower 300 days Thu 15-09-22 Tue 11-07-23
84 2D Tower 300 days Tue 19-07-22 Sun 14-05-23

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: SUNSHINE Split External Tasks Inactive Summary Manual Summary Progress
Date: Fri 17-04-20
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Task Name Duration Start Finish
Mode
2024
2019 2020 2021 2022 2023 2024 2025 2026 2027
85 1B Tower 300 days Thu 15-09-22 Tue 11-07-23
86 Infrastructure Activity 450 days Wed 14-12-22 Thu 07-03-24
87 Phase Two 450 days Wed 14-12-22 Thu 07-03-24
88 Consultancy & Misc. 1222 days Mon 02-11-20 Thu 07-03-24 Consultancy & Misc.[₹ 37,717,765.00]
89 Escalation and Price Variation 1222 days Mon 02-11-20 Thu 07-03-24 Escalation and Price Variation[₹ 47,080,619.00]
90 Labour cess & Insurance 1222 days Mon 02-11-20 Thu 07-03-24 Labour cess & Insurance[₹ 18,132,106.00]
91 SUNSHINE THREE 1165 days Sat 01-05-21 Mon 08-07-24
92 Pile Foundation Activity (SUNSHINE THREE) 180 days Sat 01-05-21 Wed 27-10-21
93 3C Tower 90 days Sat 01-05-21 Thu 29-07-21
94 2E Tower 90 days Sat 01-05-21 Thu 29-07-21
95 2F Tower 90 days Mon 31-05-21 Sat 28-08-21
96 2G Tower 90 days Fri 30-07-21 Wed 27-10-21
97 1C Tower 90 days Fri 30-07-21 Wed 27-10-21
98 Sub-Structure + Ground Floor Activity 298 days Sun 20-03-22 Thu 12-01-23
99 3C Tower 150 days Tue 17-05-22 Fri 14-10-22
100 2E Tower 150 days Tue 17-05-22 Fri 14-10-22
101 2F Tower 150 days Sun 20-03-22 Wed 17-08-22
102 2G Tower 150 days Mon 15-08-22 Thu 12-01-23
103 1C Tower 150 days Tue 17-05-22 Fri 14-10-22
104 Super-Structure Activity 461 days Thu 18-08-22 Tue 21-11-23
105 3C Tower 313 days Sat 15-10-22 Wed 23-08-23
106 2E Tower 313 days Sat 15-10-22 Wed 23-08-23
107 2F Tower 313 days Thu 18-08-22 Mon 26-06-23
108 2G Tower 313 days Fri 13-01-23 Tue 21-11-23
109 1C Tower 313 days Sat 15-10-22 Wed 23-08-23
110 Finishing Activity 358 days Sun 28-05-23 Sun 19-05-24
111 3C Tower 300 days Tue 25-07-23 Sun 19-05-24
112 2E Tower 300 days Tue 25-07-23 Sun 19-05-24
113 2F Tower 300 days Sun 28-05-23 Fri 22-03-24
114 2G Tower 210 days Mon 23-10-23 Sun 19-05-24
115 1C Tower 300 days Tue 25-07-23 Sun 19-05-24
116 Infrastructure Activity 223 days Wed 29-11-23 Mon 08-07-24
117 Phase Three 223 days Wed 29-11-23 Mon 08-07-24
118 Consultancy & Misc. 1165 days Sat 01-05-21 Mon 08-07-24 Consultancy & Misc.[₹ 35,462,319.00]
119 Escalation and Price Variation 1165 days Sat 01-05-21 Mon 08-07-24 Escalation and Price Variation[₹ 44,265,293.00]
120 Labour cess & Insurance 1165 days Sat 01-05-21 Mon 08-07-24 Labour cess & Insurance[₹ 16,852,968.00]

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Project: SUNSHINE Split External Tasks Inactive Summary Manual Summary Progress
Date: Fri 17-04-20
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 3