1 0 days Sat 01-01-22 Sat 01-01-22 ₹12,000,785,400.00 Acquisition of land
2 15 days Sun 02-01-22 Sun 16-01-22 ₹182,106,000.00 Demarcation of Boundary

3 30 days Mon 17-01-22 Tue 15-02-22 ₹101,170,000.00 Site Leveling and Cleaning

4 20 days Mon 17-01-22 Sat 05-02-22 ₹1,750,000.00 Designing of Layout


5 20 days Wed 16-02-22 Mon 07-03-22 ₹75,877,500.00 Demarcation of Roads as per Layout Plan

6 30 days Sun 06-02-22 Mon 07-03-22 ₹6,250,000.00 Advertisement (for inviting people to buy the commercial plots
7 30 days Tue 08-03-22 Wed 06-04-22 ₹2,438,831,507.00 Appllication
8 60 days Thu 07-04-22 Sun 05-06-22 ₹0.00 Draw
9 90 days Mon 06-06-22 Sat 03-09-22 ₹0.00 Return of money
10 20 days Mon 06-06-22 Sat 25-06-22 ₹9,210,242,520.00 1st installment
11 30 days Sun 04-09-22 Mon 03-10-22 ₹3,058,937,655.00 Transfer of land to govt.

12 120 days Sun 26-06-22 Sun 23-10-22 ₹67,012,060.00 Utility Trench


13 90 days Sun 26-06-22 Fri 23-09-22 ₹18,986,000.00 Sewerage Network
14 90 days Sun 26-06-22 Fri 23-09-22 ₹25,560,000.00 Water Supply Network
15 30 days Sat 24-09-22 Sun 23-10-22 ₹38,280,000.00 Storm Water Network
16 30 days Sat 24-09-22 Sun 23-10-22 ₹46,520,000.00 Utility cables
17 320 days Sun 26-06-22 Thu 11-05-23 ₹39,460,000.00 Roads
18 60 days Mon 24-10-22 Thu 22-12-22 ₹1,155,000.00 Street Lights
19 20 days Fri 23-12-22 Wed 11-01-23 ₹9,755,326,027.00 2nd installment (20%)- beginning of construction
20 120 days Thu 12-01-23 Thu 11-05-23 ESS
21 30 days Fri 12-05-23 Sat 10-06-23 ₹1,200,000.00 transformers
22 240 days Thu 12-01-23 Fri 08-09-23 ₹1,612,345.00 OHR
23 180 days Thu 12-01-23 Mon 10-07-23 ₹11,000,000.00 WPS
24 270 days Thu 12-01-23 Sun 08-10-23 ₹833,237,500.00 Construction of buildings

25 40 days Mon 31-07-23 Fri 08-09-23 ₹25,619,000.00 Parking facilities


26 20 days Tue 11-07-23 Sun 30-07-23 ₹14,632,989,041.00 3rd Installment
27 45 days Tue 11-07-23 Thu 24-08-23 ₹152,568,000.00 Construction of cycle tracks

28 30 days Sun 11-06-23 Mon 10-07-23 ₹16,942,000.00 Construction of footpaths

29 15 days Tue 11-07-23 Tue 25-07-23 ₹168,150.00 Planataion along the road

30 140 days Sat 09-09-23 Fri 26-01-24 ₹22,731,365.00 Landscape


31 30 days Sat 09-09-23 Sun 08-10-23 ₹8,207,550.00 Development of green areas in zone 1,7

32 20 days Sat 27-01-24 Thu 15-02-24 ₹14,632,989,041.00 4th installment (30%) on handing over the constructed b
33 10 days Fri 16-02-24 Sun 25-02-24 ₹1,000,000.00 Informal Unit
34 10 days Mon 26-02-24 Wed 06-03-24 ₹1,000,000.00 infrastructure
35 20 days Fri 16-02-24 Wed 06-03-24 ₹0.00 Handover

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Tue 23-11-21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1

You might also like