Descon Enginering Construction of Lahore Center Sun 11/1/20 To Sat 5/15/21

ID Task Task Name % Duration Baseline Actual Duration Remaining Duration Start Finish Baseline Cost Actual Cost Remaining Cost
Mode Complete Duration Duration Variance
0 Construction of Lahore Center 8% 168 days 170 days 13.46 days 154.54 days ‐2 days Sun 11/1/20 Sat 5/15/21 Rs 10,457,280.00 Rs 2,463,080.00 Rs 7,518,280.00
1 Prepration phase 100% 27 days 27 days 27 days 0 days 0 days Sun 11/1/20 Tue 12/1/20 Rs 1,335,800.00 Rs 1,180,520.00 Rs 0.00
2 Prepration Work 100% 27 days 27 days 27 days 0 days 0 days Sun 11/1/20 Tue 12/1/20 Rs 1,335,800.00 Rs 1,180,520.00 Rs 0.00
3 Project Work start 100% 0 days 0 days 0 days 0 days 0 days Sun 11/1/20 Sun 11/1/20 Rs 0.00 Rs 0.00 Rs 0.00
4 Mobilization 100% 10 days 7 days 10 days 0 days 3 days Sun 11/1/20 Wed 11/11/20 Rs 253,200.00 Rs 306,000.00 Rs 0.00
5 Site clearance 100% 12 days 15 days 12 days 0 days ‐3 days Thu 11/12/20 Wed 11/25/20 Rs 1,040,400.00 Rs 832,320.00 Rs 0.00
6 Layout marking 100% 5 days 5 days 5 days 0 days 0 days Thu 11/26/20 Tue 12/1/20 Rs 42,200.00 Rs 42,200.00 Rs 0.00
7 Construction phase 2% 119 days 121 days 2.45 days 116.55 days ‐2 days Tue 12/1/20 Mon 4/19/21 Rs 8,342,280.00 Rs 1,282,560.00 Rs 6,739,080.00
8 Construction Work Block A 5% 119 days 121 days 6.39 days 112.61 days ‐2 days Tue 12/1/20 Mon 4/19/21 Rs 8,342,280.00 Rs 1,282,560.00 Rs 6,739,080.00
9 Start of Block A 100% 0 days 0 days 0 days 0 days 0 days Tue 12/1/20 Tue 12/1/20 Rs 0.00 Rs 0.00 Rs 0.00
10 Excavation‐BL A 100% 8 days 10 days 8 days 0 days ‐2 days Wed 12/2/20 Thu 12/10/20 Rs 1,603,200.00 Rs 1,282,560.00 Rs 0.00
11 Steel Work BL A 0% 8 days 8 days 0 days 8 days 0 days Sat 12/12/20 Sun 12/20/20 Rs 1,531,200.00 Rs 0.00 Rs 1,531,200.00
12 Stuttring BL A 0% 10 days 10 days 0 days 10 days 0 days Sat 12/12/20 Tue 12/22/20 Rs 182,000.00 Rs 0.00 Rs 182,000.00
13 FD Concrete BL A 0% 1 day 1 day 0 days 1 day 0 days Wed 12/23/20 Wed 12/23/20 Rs 119,960.00 Rs 0.00 Rs 119,960.00
14 Column BL A 0% 10 days 10 days 0 days 10 days 0 days Thu 12/24/20 Mon 1/4/21 Rs 198,180.00 Rs 0.00 Rs 198,180.00
15 Slab Stutt BL A 0% 10 days 10 days 0 days 10 days 0 days Tue 1/5/21 Sat 1/16/21 Rs 193,200.00 Rs 0.00 Rs 193,200.00
16 Slab Steel BL A 0% 7 days 7 days 0 days 7 days 0 days Tue 1/5/21 Tue 1/12/21 Rs 1,428,640.00 Rs 0.00 Rs 1,428,640.00
17 MEP BL A 0% 6 days 6 days 0 days 6 days 0 days Tue 1/5/21 Mon 1/11/21 Rs 1,000,000.00 Rs 0.00 Rs 1,000,000.00
18 Slab Concrete BL A 0% 1 day 1 day 0 days 1 day 0 days Sun 1/17/21 Sun 1/17/21 Rs 198,800.00 Rs 0.00 Rs 198,800.00
19 MSN BL A 0% 18 days 18 days 0 days 18 days 0 days Mon 1/18/21 Sun 2/7/21 Rs 169,900.00 Rs 0.00 Rs 169,900.00
20 Plumb BL A 0% 9 days 9 days 0 days 9 days 0 days Mon 1/18/21 Wed 1/27/21 Rs 300,000.00 Rs 0.00 Rs 300,000.00
21 Finshing BL A 0% 50 days 50 days 0 days 50 days 0 days Mon 2/8/21 Tue 4/6/21 Rs 1,000,000.00 Rs 0.00 Rs 1,000,000.00
22 Inpection BL A 0% 3 days 3 days 0 days 3 days 0 days Wed 4/7/21 Sat 4/10/21 Rs 50,000.00 Rs 0.00 Rs 50,000.00
23 Rectification BL A 0% 8 days 8 days 0 days 8 days 0 days Sun 4/11/21 Mon 4/19/21 Rs 367,200.00 Rs 0.00 Rs 367,200.00
24 Completion Block A 0% 0 days 0 days 0 days 0 days 0 days Mon 4/19/21 Mon 4/19/21 Rs 0.00 Rs 0.00 Rs 0.00
25 Construction Work Block B 0% 104 days 104 days 0 days 104 days 0 days Tue 12/1/20 Thu 4/1/21 Rs 0.00 Rs 0.00 Rs 0.00
26 Start of Block B 0% 0 days 0 days 0 days 0 days 0 days Tue 12/1/20 Tue 12/1/20 Rs 0.00 Rs 0.00 Rs 0.00
27 Excavation‐BL B 0% 8 days 8 days 0 days 8 days 0 days Wed 12/2/20 Thu 12/10/20 Rs 0.00 Rs 0.00 Rs 0.00
28 Steel Work BL B 0% 7 days 7 days 0 days 7 days 0 days Sat 12/12/20 Sat 12/19/20 Rs 0.00 Rs 0.00 Rs 0.00
29 Stuttring BL B 0% 9 days 9 days 0 days 9 days 0 days Sat 12/12/20 Mon 12/21/20 Rs 0.00 Rs 0.00 Rs 0.00
30 FD Concrete BL B 0% 1 day 1 day 0 days 1 day 0 days Tue 12/22/20 Tue 12/22/20 Rs 0.00 Rs 0.00 Rs 0.00
31 Column BL B 0% 8 days 8 days 0 days 8 days 0 days Wed 12/23/20 Thu 12/31/20 Rs 0.00 Rs 0.00 Rs 0.00
32 Slab Stutt BL B 0% 8 days 8 days 0 days 8 days 0 days Sat 1/2/21 Sun 1/10/21 Rs 0.00 Rs 0.00 Rs 0.00
33 Slab Steel BL B 0% 6 days 6 days 0 days 6 days 0 days Sat 1/2/21 Thu 1/7/21 Rs 0.00 Rs 0.00 Rs 0.00
34 MEH BL B 0% 5 days 5 days 0 days 5 days 0 days Sat 1/2/21 Wed 1/6/21 Rs 0.00 Rs 0.00 Rs 0.00
35 Slab Concrete BL B 0% 1 day 1 day 0 days 1 day 0 days Mon 1/11/21 Mon 1/11/21 Rs 0.00 Rs 0.00 Rs 0.00
36 MSN BL B 0% 15 days 15 days 0 days 15 days 0 days Tue 1/12/21 Thu 1/28/21 Rs 0.00 Rs 0.00 Rs 0.00
37 Plumb BL B 0% 7 days 7 days 0 days 7 days 0 days Tue 1/12/21 Tue 1/19/21 Rs 0.00 Rs 0.00 Rs 0.00
38 Finshing BL B 0% 45 days 45 days 0 days 45 days 0 days Sat 1/30/21 Mon 3/22/21 Rs 0.00 Rs 0.00 Rs 0.00
39 Inpection BL B 0% 3 days 3 days 0 days 3 days 0 days Tue 3/23/21 Thu 3/25/21 Rs 0.00 Rs 0.00 Rs 0.00
40 Rectification BL B 0% 6 days 6 days 0 days 6 days 0 days Sat 3/27/21 Thu 4/1/21 Rs 0.00 Rs 0.00 Rs 0.00
41 Completion Block B 0% 0 days 0 days 0 days 0 days 0 days Thu 4/1/21 Thu 4/1/21 Rs 0.00 Rs 0.00 Rs 0.00
42 Construction Work Block C 0% 89 days 89 days 0 days 89 days 0 days Tue 12/1/20 Mon 3/15/21 Rs 0.00 Rs 0.00 Rs 0.00
43 Start of Block C 0% 0 days 0 days 0 days 0 days 0 days Tue 12/1/20 Tue 12/1/20 Rs 0.00 Rs 0.00 Rs 0.00
44 Excavation‐BL C 0% 6 days 6 days 0 days 6 days 0 days Wed 12/2/20 Tue 12/8/20 Rs 0.00 Rs 0.00 Rs 0.00

Page 1
Descon Enginering Construction of Lahore Center Sun 11/1/20 To Sat 5/15/21
ID Task Task Name % Duration Baseline Actual Duration Remaining Duration Start Finish Baseline Cost Actual Cost Remaining Cost
Mode Complete Duration Duration Variance
45 Steel Work BL C 0% 6 days 6 days 0 days 6 days 0 days Wed 12/9/20 Tue 12/15/20 Rs 0.00 Rs 0.00 Rs 0.00
46 Stuttring BL C 0% 8 days 8 days 0 days 8 days 0 days Wed 12/9/20 Thu 12/17/20 Rs 0.00 Rs 0.00 Rs 0.00
47 FD Concrete BL C 0% 1 day 1 day 0 days 1 day 0 days Sat 12/19/20 Sat 12/19/20 Rs 0.00 Rs 0.00 Rs 0.00
48 Column BL C 0% 7 days 7 days 0 days 7 days 0 days Sun 12/20/20 Sun 12/27/20 Rs 0.00 Rs 0.00 Rs 0.00
49 Slab Stutt BL C 0% 7 days 7 days 0 days 7 days 0 days Mon 12/28/20 Mon 1/4/21 Rs 0.00 Rs 0.00 Rs 0.00
50 Slab Steel BL C 0% 6 days 6 days 0 days 6 days 0 days Mon 12/28/20 Sun 1/3/21 Rs 0.00 Rs 0.00 Rs 0.00
51 MEH BL C 0% 4 days 4 days 0 days 4 days 0 days Mon 12/28/20 Thu 12/31/20 Rs 0.00 Rs 0.00 Rs 0.00
52 Slab Concrete BL C 0% 1 day 1 day 0 days 1 day 0 days Tue 1/5/21 Tue 1/5/21 Rs 0.00 Rs 0.00 Rs 0.00
53 MSN BL C 0% 12 days 12 days 0 days 12 days 0 days Wed 1/6/21 Tue 1/19/21 Rs 0.00 Rs 0.00 Rs 0.00
54 Plumb BL C 0% 5 days 5 days 0 days 5 days 0 days Wed 1/6/21 Mon 1/11/21 Rs 0.00 Rs 0.00 Rs 0.00
55 Finshing BL C 0% 40 days 40 days 0 days 40 days 0 days Wed 1/20/21 Sun 3/7/21 Rs 0.00 Rs 0.00 Rs 0.00
56 Inpection BL C 0% 2 days 2 days 0 days 2 days 0 days Mon 3/8/21 Tue 3/9/21 Rs 0.00 Rs 0.00 Rs 0.00
57 Rectification BL C 0% 5 days 5 days 0 days 5 days 0 days Wed 3/10/21 Mon 3/15/21 Rs 0.00 Rs 0.00 Rs 0.00
58 Completion Block C 0% 0 days 0 days 0 days 0 days 0 days Mon 3/15/21 Mon 3/15/21 Rs 0.00 Rs 0.00 Rs 0.00
59 Final phase 0% 22 days 22 days 0 days 22 days 0 days Tue 4/20/21 Sat 5/15/21 Rs 779,200.00 Rs 0.00 Rs 779,200.00
60 Final Work 0% 22 days 22 days 0 days 22 days 0 days Tue 4/20/21 Sat 5/15/21 Rs 779,200.00 Rs 0.00 Rs 779,200.00
61 Project Inspection 0% 5 days 5 days 0 days 5 days 0 days Tue 4/20/21 Sun 4/25/21 Rs 184,000.00 Rs 0.00 Rs 184,000.00
62 Project H/O 0% 10 days 10 days 0 days 10 days 0 days Mon 4/26/21 Thu 5/6/21 Rs 595,200.00 Rs 0.00 Rs 595,200.00
63 Demobilization 0% 7 days 7 days 0 days 7 days 0 days Sat 5/8/21 Sat 5/15/21 Rs 0.00 Rs 0.00 Rs 0.00
64 Project Completion 0% 0 days 0 days 0 days 0 days 0 days Sat 5/15/21 Sat 5/15/21 Rs 0.00 Rs 0.00 Rs 0.00

Page 2
Descon Enginering Construction of Lahore Center Sun 11/1/20 To Sat 5/15/21
Cost Variance

(Rs 475,920.00)
(Rs 155,280.00)
(Rs 155,280.00)
Rs 0.00
Rs 52,800.00
(Rs 208,080.00)
Rs 0.00
(Rs 320,640.00)
(Rs 320,640.00)
Rs 0.00
(Rs 320,640.00)
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00

Page 3
Descon Enginering Construction of Lahore Center Sun 11/1/20 To Sat 5/15/21
Cost Variance

Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00
Rs 0.00

Page 4

You might also like