ID Task Mode Task Name Duration Start Finish Predecessors

0 Master Plan 503 days Sun 11/1/20 Thu 6/9/22


1 Prepration phase 27 days Sun 11/1/20 Tue 12/1/20
2 Prepration Work 27 days Sun 11/1/20 Tue 12/1/20
3 Project Work start 0 days Sun 11/1/20 Sun 11/1/20
4 Mobilization 7 days Sun 11/1/20 Sun 11/8/20 3
5 Site clearance 15 days Mon 11/9/20 Wed 11/25/20 4
6 Layout marking 5 days Thu 11/26/20 Tue 12/1/20 5
8 Construction Work Block A 139 days Tue 5/18/21 Wed 10/27/21
1 Project Completion 0 days Tue 5/18/21 Tue 5/18/21
3 Start of Block A 0 days Tue 5/18/21 Tue 5/18/21 C:\Users\Owner\D
4 Excavation‐BL A 12 days Wed 5/19/21 Tue 6/1/21 3
5 Steel Work BL A 8 days Wed 6/2/21 Thu 6/10/21 4
6 Stuttring BL A 10 days Wed 6/2/21 Sun 6/13/21 4
7 FD Concrete BL A 3 days Mon 6/14/21 Wed 6/16/21 5,6
8 Column BL A 10 days Thu 6/17/21 Mon 6/28/21 7
9 Slab Stutt BL A 10 days Tue 6/29/21 Sat 7/10/21 8
10 Slab Steel BL A 7 days Tue 6/29/21 Tue 7/6/21 8
11 MEP BL A 6 days Tue 6/29/21 Mon 7/5/21 8
12 Slab Concrete BL A 3 days Sun 7/11/21 Tue 7/13/21 9,10,11
13 MSN BL A 18 days Wed 7/14/21 Tue 8/3/21 12
14 Plumb BL A 9 days Wed 7/14/21 Sat 7/24/21 12
15 Finshing BL A 50 days Wed 8/4/21 Thu 9/30/21 13,14
16 Inpection BL A 8 days Sat 10/2/21 Sun 10/10/21 15
17 Rectification BL A 15 days Mon 10/11/21 Wed 10/27/21 16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1
ID Task Mode Task Name Duration Start Finish Predecessors

18 Completion Block A 0 days Wed 10/27/21 Wed 10/27/21 17


9 Construction Work Block B 104 days Wed 10/27/21 Sat 2/26/22
2 Start of Block B 0 days Wed 10/27/21 Wed 10/27/21 C:\Users\Owner\D
3 Excavation‐BL B 8 days Thu 10/28/21 Sat 11/6/21 2
4 Steel Work BL B 7 days Sun 11/7/21 Sun 11/14/21 3
5 Stuttring BL B 9 days Sun 11/7/21 Tue 11/16/21 3
6 FD Concrete BL B 1 day Wed 11/17/21 Wed 11/17/21 4,5
7 Column BL B 8 days Thu 11/18/21 Sat 11/27/21 6
8 Slab Stutt BL B 8 days Sun 11/28/21 Mon 12/6/21 7
9 Slab Steel BL B 6 days Sun 11/28/21 Sat 12/4/21 7
10 MEH BL B 5 days Sun 11/28/21 Thu 12/2/21 7
11 Slab Concrete BL B 1 day Tue 12/7/21 Tue 12/7/21 8,9,10
12 MSN BL B 15 days Wed 12/8/21 Sat 12/25/21 11
13 Plumb BL B 7 days Wed 12/8/21 Wed 12/15/21 11
14 Finshing BL B 45 days Sun 12/26/21 Tue 2/15/22 12,13
15 Inpection BL B 3 days Wed 2/16/22 Sat 2/19/22 14
16 Rectification BL B 6 days Sun 2/20/22 Sat 2/26/22 15
17 Completion Block B 0 days Sat 2/26/22 Sat 2/26/22 16
10 Construction Work Block C 89 days Sat 2/26/22 Thu 6/9/22
2 Start of Block C 0 days Sat 2/26/22 Sat 2/26/22 C:\Users\Owner\D
3 Excavation‐BL C 6 days Sun 2/27/22 Sat 3/5/22 2
4 Steel Work BL C 6 days Sun 3/6/22 Sat 3/12/22 3
5 Stuttring BL C 8 days Sun 3/6/22 Mon 3/14/22 3
6 FD Concrete BL C 1 day Tue 3/15/22 Tue 3/15/22 4,5

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 2
ID Task Mode Task Name Duration Start Finish Predecessors

7 Column BL C 7 days Wed 3/16/22 Wed 3/23/22 6


8 Slab Stutt BL C 7 days Thu 3/24/22 Thu 3/31/22 7
9 Slab Steel BL C 6 days Thu 3/24/22 Wed 3/30/22 7
10 MEH BL C 4 days Thu 3/24/22 Mon 3/28/22 7
11 Slab Concrete BL C 1 day Sat 4/2/22 Sat 4/2/22 8,9,10
12 MSN BL C 12 days Sun 4/3/22 Sat 4/16/22 11
13 Plumb BL C 5 days Sun 4/3/22 Thu 4/7/22 11
14 Finshing BL C 40 days Sun 4/17/22 Wed 6/1/22 12,13
15 Inpection BL C 2 days Thu 6/2/22 Sat 6/4/22 14
16 Rectification BL C 5 days Sun 6/5/22 Thu 6/9/22 15
17 Completion Block C 0 days Thu 6/9/22 Thu 6/9/22 16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 3
Cost Start Slack Oct 24, '20 Nov 7, '20 Nov 21, '20 Dec 5, '20 Dec 19, '20 Jan 2, '21 Jan 16, '21 Jan
S W S T M F T S W S T M F T S W S T M F T S W S T
Rs 10,230,640.00 144 days
Rs 1,335,800.00 144 days
Rs 1,335,800.00 144 days
Rs 0.00 144 days 11/1
Rs 253,200.00 144 days Operator[200%],Helper[500%],Mobilization[Rs 200,000.00]
Rs 1,040,400.00 144 days Operator[200%],Helper[300%],Excavator,Dumper[200%]
Rs 42,200.00 144 days Mason[400%],Helper[500%],Limestone powder[Rs 5,000.00]
Rs 8,894,840.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 1,923,840.00 0 days
Rs 1,531,200.00 2 days
Rs 182,000.00 0 days
Rs 205,080.00 0 days
Rs 198,180.00 0 days
Rs 193,200.00 0 days
Rs 1,428,640.00 3 days
Rs 1,000,000.00 4 days
Rs 286,800.00 0 days
Rs 169,900.00 0 days
Rs 300,000.00 9 days
Rs 1,000,000.00 0 days
Rs 50,000.00 0 days
Rs 426,000.00 0 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 4
Cost Start Slack Oct 24, '20 Nov 7, '20 Nov 21, '20 Dec 5, '20 Dec 19, '20 Jan 2, '21 Jan 16, '21 Jan
S W S T M F T S W S T M F T S W S T M F T S W S T
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 2 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 2 days
Rs 0.00 3 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 8 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 2 days
Rs 0.00 0 days
Rs 0.00 0 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 5
Cost Start Slack Oct 24, '20 Nov 7, '20 Nov 21, '20 Dec 5, '20 Dec 19, '20 Jan 2, '21 Jan 16, '21 Jan
S W S T M F T S W S T M F T S W S T M F T S W S T
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 1 day
Rs 0.00 3 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 7 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days
Rs 0.00 0 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 6
n 30, '21 Feb 13, '21 Feb 27, '21 Mar 13, '21 Mar 27, '21 Apr 10, '21 Apr 24, '21 May 8, '21 May 22, '21 Jun 5,
M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S

5/18
5/18
Excavat

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 7
n 30, '21 Feb 13, '21 Feb 27, '21 Mar 13, '21 Mar 27, '21 Apr 10, '21 Apr 24, '21 May 8, '21 May 22, '21 Jun 5,
M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 8
n 30, '21 Feb 13, '21 Feb 27, '21 Mar 13, '21 Mar 27, '21 Apr 10, '21 Apr 24, '21 May 8, '21 May 22, '21 Jun 5,
M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 9
'21 Jun 19, '21 Jul 3, '21 Jul 17, '21 Jul 31, '21 Aug 14, '21 Aug 28, '21 Sep 11, '21 Sep 25, '21 Oct 9, '21
W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M

ator[200%],Dumper[500%],Operator[600%],Helper[600%]
Steel fixer[1,500%],Steel[12 Tons],Helper[1,500%]
Carpenter[500%],Helper[1,000%],Shuterring[1,200 SFT]
Mason[500%],Helper[800%],Cement[100 bags],Sand [200 CFT],Crush[400 CFT],Mixer machine[200%],Water bowzer
Mason[200%],Carpenter,Steel fixer[200%],Steel[1 Tons],Shuterring[500 SFT],Cement[20 bags],Sand [40 CFT],Crush[60 CFT]
Carpenter[600%],Helper[1,000%],Shuterring[1,200 SFT]
Steel[12 Tons],Steel fixer[800%],Helper[1,000%]
Limestone powder[Rs 1,000,000.00]
Mason[500%],Helper[1,000%],Cement[200 bags],Sand [400 CFT],Crush[800 CFT],Mixer machine[200%],Water
Cement[10 bags],Sand [20 CFT],Helper[600%],Mason[500%]
LUMPSUM Cost[Rs 300,000.00]
LUMPSUM Cost
LUM

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 10
'21 Jun 19, '21 Jul 3, '21 Jul 17, '21 Jul 31, '21 Aug 14, '21 Aug 28, '21 Sep 11, '21 Sep 25, '21 Oct 9, '21
W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 11
'21 Jun 19, '21 Jul 3, '21 Jul 17, '21 Jul 31, '21 Aug 14, '21 Aug 28, '21 Sep 11, '21 Sep 25, '21 Oct 9, '21
W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 12
1 Oct 23, '21 Nov 6, '21 Nov 20, '21 Dec 4, '21 Dec 18, '21 Jan 1, '22 Jan 15, '22 Jan 29, '22 Feb 12, '22
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W

r bowzer

st[Rs 1,000,000.00]
UMPSUM Cost[Rs 50,000.00]
LUMPSUM Cost[Rs 300,000.00],Mason[500%],Helper[500%]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 13
1 Oct 23, '21 Nov 6, '21 Nov 20, '21 Dec 4, '21 Dec 18, '21 Jan 1, '22 Jan 15, '22 Jan 29, '22 Feb 12, '22
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
10/27

10/27

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 14
1 Oct 23, '21 Nov 6, '21 Nov 20, '21 Dec 4, '21 Dec 18, '21 Jan 1, '22 Jan 15, '22 Jan 29, '22 Feb 12, '22
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 15
Feb 26, '22 Mar 12, '22 Mar 26, '22 Apr 9, '22 Apr 23, '22 May 7, '22 May 21, '22 Jun 4, '22 Jun 18, '22
S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 16
Feb 26, '22 Mar 12, '22 Mar 26, '22 Apr 9, '22 Apr 23, '22 May 7, '22 May 21, '22 Jun 4, '22 Jun 18, '22
S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F

2/26

2/26

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 17
Feb 26, '22 Mar 12, '22 Mar 26, '22 Apr 9, '22 Apr 23, '22 May 7, '22 May 21, '22 Jun 4, '22 Jun 18, '22
S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F

6/9

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Master Plan
Summary Manual Summary Rollup Critical
Date: Fri 3/19/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 18