Boundary wall 1
Excavation 541 1 121 120 121 121 100.00%
Blinding concrete 121 121 100.00%
Blinding waterproofing 121 119 98.35%
Precast footing erection 121 121 100.00%
Precast column erection 121 121 100.00%
Precast lower beam erection 121 121 100.00%
Footing waterproofing 121 91 75.21%
Beams waterproofing 121 0 0.00%
Precast wall panel erection 121 121 100.00%
Backfilling 121 0 0.00%
Painting works 121 0 0.00%
Boundary wall 2 603 122 255 133
Excavation 133 129 96.99%
Blinding concrete 133 129 96.99%
Blinding waterproofing 133 129 96.99%
Precast footing erection 133 129 96.99%
Precast column erection 133 129 96.99%
Precast lower beam erection 133 123 92.48%
As on
BOUNDARY WALL, DRY VENTILATED WAREHOUSES AND SHOW ROOMS
23-Nov-20
Location/Description of Grid Grid Work Completed in
UOM Length Difference Total Qty.
Works Start End done Qty %
Footing waterproofing 133 77 57.89%
Beams waterproofing 133 0 0.00%
Precast wall panel erection 133 123 92.48%
Backfilling 133 0 0.00%
Painting works 133 0 0.00%
Boundary wall 3 312 256 324 68
Excavation 69 66 95.65%
Blinding concrete 69 66 95.65%
Blinding waterproofing 69 66 95.65%
Precast footing erection 69 65 94.20%
Precast column erection 69 65 94.20%
Precast lower beam erection 68 59 86.76%
Footing waterproofing 69 52 75.36%
Beams waterproofing 68 0 0.00%
Precast wall panel erection 68 61 89.71%
Backfilling 68 45 66.18%
Painting works 68 0 0.00%
Boundary wall 4 60 325 338 13
Excavation 14 14 100.00%
Blinding concrete 14 13 92.86%
Blinding waterproofing 14 13 92.86%
Precast footing erection 14 13 92.86%
Precast column erection 14 0 0.00%
Precast lower beam erection 14 0 0.00%
Footing waterproofing 14 0 0.00%
Beams waterproofing 14 0 0.00%
Precast wall panel erection 14 0 0.00%
Backfilling 14 0 0.00%
Painting works 14 0 0.00%
Boundary wall 5 60 339 352 13
Excavation 14 14 100.00%
Blinding concrete 14 14 100.00%
Blinding waterproofing 14 14 100.00%
Precast footing erection 14 14 100.00%
Precast column erection 14 0 0.00%
Precast lower beam erection 14 0 0.00%
Footing waterproofing 14 0 0.00%
Beams waterproofing 14 0 0.00%
Precast wall panel erection 14 0 0.00%
Backfilling 14 0 0.00%
Painting works 14 0 0.00%
Boundary wall 6 60 353 366 13
Excavation 14 14 100.00%
Blinding concrete 14 14 100.00%
Blinding waterproofing 14 14 100.00%
Precast footing erection 14 14 100.00%
Precast column erection 14 0 0.00%
Precast lower beam erection 14 0 0.00%
Footing waterproofing 14 0 0.00%
Beams waterproofing 14 0 0.00%
Precast wall panel erection 14 0 0.00%
Backfilling 14 0 0.00%
Painting works 14 0 0.00%
Boundary wall 7 1202 367 630 263
Excavation 264 259 98.11%
Blinding concrete 264 255 96.59%
Blinding waterproofing 264 255 96.59%
As on
BOUNDARY WALL, DRY VENTILATED WAREHOUSES AND SHOW ROOMS
23-Nov-20
Location/Description of Grid Grid Work Completed in
UOM Length Difference Total Qty.
Works Start End done Qty %
Precast footing erection 264 253 95.83%
Precast column erection 264 255 96.59%
Precast lower beam erection 261 254 97.32%
Footing waterproofing 264 143 54.17%
Beams waterproofing 261 0 0.00%
Precast wall panel erection 261 254 97.32%
Backfilling 261 0 0.00%
Painting works 261 0 0.00%
Boundary wall 8 1027 631 859 228
Excavation 229 227 99.13%
Blinding concrete 229 224 97.82%
Blinding waterproofing 229 224 97.82%
Precast footing erection 229 227 99.13%
Precast column erection 229 227 99.13%
Precast lower beam erection 229 219 95.63%
Footing waterproofing 229 155 67.69%
Beams waterproofing 229 0 0.00%
Precast wall panel erection 229 219 95.63%
Backfilling 229 4 1.75%
Painting works 229 0 0.00%
Boundary wall 9 1166 860 1118 258
Excavation 259 259 100.00%
Blinding concrete 259 259 100.00%
Blinding waterproofing 259 259 100.00%
Precast footing erection 259 259 100.00%
Precast column erection 259 259 100.00%
Precast lower beam erection 259 259 100.00%
Footing waterproofing 259 142 54.83%
Beams waterproofing 259 0 0.00%
Precast wall panel erection 259 259 100.00%
Backfilling 259 0 0.00%
Painting works 259 0 0.00%
Dry Ventilated Warehouses and Show Rooms Blinding Concrete Status
Total
26/Sep
27/Sep
28/Sep
29/Sep
30/Sep
10/Oct
11/Oct
12/Oct
13/Oct
14/Oct
15/Oct
16/Oct
17/Oct
18/Oct
19/Oct
20/Oct
21/Oct
22/Oct
23/Oct
24/Oct
25/Oct
26/Oct
27/Oct
28/Oct
29/Oct
30/Oct
31/Oct
1/Nov
2/Nov
3/Nov
4/Nov
2/Sep
1/Oct
2/Oct
3/Oct
4/Oct
5/Oct
6/Oct
7/Oct
8/Oct
9/Oct
Area Total Percent
Completed
B8 A01 48 48 100.0%
B8 A02 48 48 100.0%
B8 A03 27 27 100.0%
Total 123 123
B2 A09 121 121 100.0%
AC
Dry Ventilated Warehouses and Show Rooms footing pedestal installations Status
Total
10/Nov
11/Nov
12/Nov
13/Nov
14/Nov
15/Nov
16/Nov
17/Nov
29/Sep
30/Sep
10/Oct
11/Oct
12/Oct
13/Oct
14/Oct
15/Oct
16/Oct
17/Oct
18/Oct
19/Oct
20/Oct
21/Oct
22/Oct
27/Oct
28/Oct
29/Oct
30/Oct
31/Oct
1/Nov
2/Nov
3/Nov
4/Nov
5/Nov
6/Nov
7/Nov
8/Nov
9/Nov
8/Sep
9/Sep
1/Oct
2/Oct
3/Oct
4/Oct
5/Oct
6/Oct
7/Oct
8/Oct
9/Oct
B8 A01 48 2 2 1 1 48 100.0%
B8 A02 48 2 48 100.0%
B8 A03 27 1 27 100.0%
Total 123 123
B2 A09 121 1 1 2 121 100.0%
4 1 1 2 2 2 2 2 2 4 1 1 1 1
AC
Total
10/Nov
11/Nov
12/Nov
13/Nov
14/Nov
15/Nov
16/Nov
17/Nov
24/Sep
28/Sep
29/Sep
30/Sep
10/Oct
11/Oct
12/Oct
13/Oct
14/Oct
15/Oct
20/Oct
21/Oct
22/Oct
23/Oct
24/Oct
25/Oct
26/Oct
27/Oct
28/Oct
29/Oct
30/Oct
31/Oct
1/Nov
2/Nov
3/Nov
4/Nov
5/Nov
6/Nov
7/Nov
8/Nov
9/Nov
1/Oct
2/Oct
3/Oct
4/Oct
5/Oct
6/Oct
7/Oct
8/Oct
9/Oct
Area Total Percent
Completed
B1A1 71 1 1 71 100.0%
B1A2 67 3 3 3 66 98.5%
B1A3 72 72 100.0%
B1A4 72 72 100.0%
B1A5 72 72 100.0%
Dry Ventilated
B1A6 72 72 100.0%
B1A7 72 72 100.0%
B1A8 72 72 100.0%
B1A9 72 72 100.0%
B1A10 72 72 100.0%
B1A11 72 72 100.0%
B1A12 72 72 100.0%
Total 858 857
2 1 1
Show Rooms
B8 A01 48 48 100.0%
B8 A02 48 1 1 1 1 48 100.0%
B8 A03 27 1 26 96.3%
Total 123 122
B2 A09 121 6 10 12 2 1 1 1 4 5 7 6 4 6 3 2 2 2 3 3 3 2 4 4 4 4 2 117 96.7%
4 3 5 3 2 2 2 2 2 1 5 7 5 7 4 4 4 4 4 4 2 1
AC
AC, Dry Ventilated Warehouses and Show Rooms 1st stage S.o.Grade concrete Status
Total
10/Nov
11/Nov
12/Nov
13/Nov
14/Nov
15/Nov
16/Nov
17/Nov
18/Nov
19/Nov
20/Nov
21/Nov
22/Nov
23/Nov
24/Nov
25/Nov
26/Nov
27/Nov
28/Nov
29/Nov
30/Nov
17/Oct
18/Oct
19/Oct
20/Oct
21/Oct
22/Oct
23/Oct
24/Oct
25/Oct
26/Oct
27/Oct
28/Oct
29/Oct
30/Oct
31/Oct
1/Nov
2/Nov
3/Nov
4/Nov
5/Nov
6/Nov
7/Nov
8/Nov
9/Nov
1/Dec
2/Dec
3/Dec
Area Total Completed Percent
B1A1 37 2 8 10 27.0%
B1A2 34 0 0.0%
B1A3 38 2 3 5 6 8 2 5 7 38 100.0%
B1A4 38 3 6 8 7 7 1 2 2 1 1 38 100.0%
B1A5 38 3 38 100.0%
Dry Ventilated
B1A6 38 1 38 100.0%
B1A7 38 38 100.0%
B1A8 38 38 100.0%
B1A9 38 38 100.0%
B1A10 38 38 100.0%
B1A11 38 38 100.0%
B1A12 38 38 100.0%
Total 451 390
Show Rooms
B8 A01 30 22 2 2 2 2 30 100.0%
B8 A02 30 1 2 4 1 2 2 2 2 16 53.3%
B8 A03 16 0 0.0%
Total 76 46
B2 A09 0
AC
B2 A10 0
Total 0 0
86.47%
60.53%
#DIV/0!
AC, Dry Ventilated Warehouses and Show Rooms Precast wall panels installations Status
Total
10/Nov
11/Nov
12/Nov
13/Nov
14/Nov
15/Nov
16/Nov
17/Nov
18/Nov
19/Nov
20/Nov
21/Nov
22/Nov
23/Nov
24/Nov
25/Nov
26/Nov
27/Nov
28/Nov
29/Nov
30/Nov
10/Dec
11/Dec
12/Dec
26/Oct
27/Oct
28/Oct
29/Oct
30/Oct
31/Oct
1/Nov
2/Nov
3/Nov
4/Nov
5/Nov
6/Nov
7/Nov
8/Nov
9/Nov
1/Dec
2/Dec
3/Dec
4/Dec
5/Dec
6/Dec
7/Dec
8/Dec
9/Dec
Area Total Percent
Completed
B2 A10 86 13
Total 172 38
37.05%
45.68%
22.09%
AC, Dry Ventilated Warehouses and Show Rooms Precast roof beam installation Status
Total
10/Nov
11/Nov
12/Nov
13/Nov
14/Nov
15/Nov
16/Nov
17/Nov
18/Nov
19/Nov
20/Nov
21/Nov
22/Nov
23/Nov
24/Nov
25/Nov
26/Nov
27/Nov
28/Nov
29/Nov
30/Nov
10/Dec
11/Dec
12/Dec
26/Oct
27/Oct
28/Oct
29/Oct
30/Oct
31/Oct
1/Nov
2/Nov
3/Nov
4/Nov
5/Nov
6/Nov
7/Nov
8/Nov
9/Nov
1/Dec
2/Dec
3/Dec
4/Dec
5/Dec
6/Dec
7/Dec
8/Dec
9/Dec
Area Total Percent
Completed
B8 A01 47 1 1 1 1 2 45
B8 A02 47 40
B8 A03 25 23
Total 119 108
B2 A09 162 12 12 16 14 15 16 4 4 5 4 120
2 2 2 4 4 4 4 4 4 12 14 7
AC
B2 A10 162 63
Total 324 183
89.39%
90.76%
56.48%
Dry Ventilated
Area
Total
B1A9
B1A8
B1A7
B1A6
B1A5
B1A4
B1A3
B1A2
B1A1
B1A12
B1A11
B1A10
57
57
57
57
57
57
57
57
57
57
57
53
680
Total
8
4/Nov
6
5/Nov
6/Nov
1
9
1 7/Nov
4
11
8/Nov
4
7
9/Nov
3
5
10/Nov
11/Nov
12/Nov
13/Nov
14/Nov
15/Nov
16/Nov
17/Nov
18/Nov
19/Nov
AC, Dry Ventilated Warehouses and Show Rooms Precast parapet installation Status
20/Nov
21/Nov
22/Nov
23/Nov
24/Nov
25/Nov
26/Nov
27/Nov
28/Nov
29/Nov
30/Nov
1/Dec
2/Dec
3/Dec
4/Dec
5/Dec
6/Dec
7/Dec
8/Dec
9/Dec
10/Dec
11/Dec
12/Dec
13/Dec
14/Dec
15/Dec
16/Dec
17/Dec
18/Dec
19/Dec
20/Dec
21/Dec
9
5
0
0
0
0
56
56
28
57
30
15
256
Total
Completed
8.8%
0.0%
0.0%
0.0%
0.0%
98.2%
98.2%
49.1%
52.6%
26.3%
15.8%
100.0%
Percent
Show Rooms B8 A01 32 1 2 2 25 78.1%
B8 A02 32 3 8 25.0%
B8 A03 20 0 0.0%
Total 84 33
B2 A09 0
AC
B2 A10 0
Total 0 0
37.65%
39.29%
#DIV/0!
Footing Footing Column 1st stage Roof
Area Wall panels HC Slabs Parapet Plinth beams
Blinding Installations Installations S.o.Grade beams
A - 12
A - 11
A - 10
D A-9
R
Y
V
A-8
E
N A-7
T
I
L A-6
A
T
E A-5
D
A-4
A-3
A-2
A-1
A-3
S.Rooms A - 2
A-1
A - 10
AC
A-9
As on 17.09.2020
Roof beam Parapet
Warehouse
Total Installed Total Installed
B1A1 101 52 53 0
B1A2 103 40 57 0
B1A3 105 48 57 0
B1A4 105 47 57 0
B1A5 105 52 57 0
B1A6 105 64 57 0
B1A7 105 42 57 0
B1A8 105 35 57 0
B1A9 105 60 57 0
B1A10 105 60 57 0
B1A11 105 103 57 24
B1A12 105 78 57 5
Total 1254 681 680 29
Plinth beam
Total Installed
98 90
91 25
101 97
101 97
101 101
101 98
101 97
101 98
101 80
101 60
101 101
101 79
1199 1023