Professional Documents
Culture Documents
You are hereby directed to make herein described changes from the plans and specifications of the following described work not included in the plans and specifications:
902(2) Formworks And Falseworks - - L.S. 1013(2)a2 Embankment From Borrow - 1.00 L.S.
900(1)c2 Structural Concrete (Footing and Slab on Fill), A 28 Days - 76.30 cu.m.
REASON FOR CHANGE : Due to Extra Work - To suit actual field condition leading to revision of plans.
CHANGE REQUESTED BY : Project Engineer, DPWH
ITEMIZED QUANTITIES AND COST OF REVISION IS SHOWN IN THE ATTACHED BILL OF QUANTITIES AND COST ESTIMATE
PIF-12-VO-01A Rev 00
Contract ID : 21ED0125
Contract Name : Construction of Pola ABC Building, Pola, Oriental Mindoro
Location : Pola, Oriental Mindoro
Contractor : Greenfield Construction
B.3 PERMITS AND CLEARANCES L.S. 1.00 9,030.00 9,030.00 0.00 - 0.00 - 1.00 9,030.00
B.5 PROJECT BILLBOARD/ SIGNBOARD EACH 1.00 4,131.87 4,131.87 0.00 - 0.00 - 1.00 4,131.87
B.7 (2) OCCUPATION SAFETY & HEALTH PROGRAM L.S. 1.00 74,699.78 74,699.78 0.00 - 0.00 - 1.00 74,699.78
B.9 MOBILIZATION/DEMOBILIZATION L.S. 1.00 34,672.93 34,672.93 0.00 - 0.00 - 1.00 34,672.93
800 (1) CLEARING AND GRUBBING M^2 232.80 43.02 10,015.06 0.00 - 106.98 4,602.28 125.82 5,412.78
803(1)a STRUCTURE EXCAVATION, COMMON SOIL M^3 396.75 209.02 82,928.69 0.00 - 140.93 29,457.19 255.82 53,471.50
EMBANKMENT FROM
803(1)a M^3 202.08 177.29 35,826.76 0.00 - 96.94 17,186.49 105.14 18,640.27
ROADWAY/STRUCUTRE EXCAVATION
804(4) GRAVEL FILL M^3 24.43 1,214.64 29,673.66 0.00 - 17.68 21,474.84 6.75 8,198.82
902(2) FORMWORKS AND FALSEWORKS M^2 105.93 1,169.86 123,923.27 386.76 452,455.05 0.00 - 492.69 576,378.32
1010(4) WOODEN DOORS AND WINDOWS L.S. 1.00 246,327.19 246,327.19 0.00 - 1.00 174,423.05 0.00 71,904.14
Conformed:
ANNALIZA M. PLATA
Contractor
PIF-12-VO-02A Rev 00
Contract ID : 21ED0125
Contract Name : Construction of Pola ABC Building, Pola, Oriental Mindoro
Location : Pola, Oriental Mindoro
Contractor : Greenfield Construction
1021(1)c CEMENT FLOOR FINISH, PLAIN M^2 150.32 335.95 50,500.00 0.00 - 37.87 12,722.43 112.45 37,777.58
1027(1) CEMENT PLASTER FINISH M^2 1,116.86 168.32 187,989.88 8.70 1,464.38 - - 1,125.56 189,454.26
1051(6) RAILINGS L.S. 1.00 292,523.48 292,523.48 1.00 128,691.37 0.00 - 1.00 421,214.85
1018(5) GLAZED TILES M^2 141.60 1,340.13 189,762.41 76.06 101,930.29 0.00 - 217.66 291,692.70
1018(2) UNGLAZED TILES M^2 433.61 1,486.78 644,682.68 0.00 - 355.15 528,029.92 78.46 116,652.76
1032(1)a PAINTING WORKS, MASONRY/CONCRETE M^2 1,116.86 186.84 208,674.12 0.00 - 554.08 103,524.31 562.78 105,149.82
1047(2)a STRUCTURAL STEEL, TRUSSES KG 5,833.59 81.33 474,445.87 0.00 - 5,833.59 474,445.87 - -
1047(2)b STRUCTURAL STEEL PURLINS KG 807.25 83.61 67,494.17 0.00 - 775.05 64,801.93 32.20 2,692.24
1047(7)a METAL STRUCTURE ACCESSORIES, BOLTS PC 134.00 64.38 8,626.92 0.00 - 134.00 8,626.92 - -
1001(9) STORM DRAINAGE AND DOWNSPOUT L.S. 1.00 21,314.88 21,314.88 0.00 - 1.00 11,905.13 1.00 9,409.75
1002(27) PLUMBING WORKS L.S. 1.00 573,267.05 573,267.05 0.00 - 1.00 573,267.05 - -
1001(11) SEPTIC VAULT (CONCRETE/CHB) L.S. 1.00 150,678.55 150,678.55 0.00 - 1.00 90,716.22 1.00 59,962.33
1001(5)b CATCH BASIN EACH 7.00 999.45 6,996.15 0.00 - 2.00 1,998.90 5.00 4,997.25
Conformed:
ANNALIZA M. PLATA
Contractor
PIF-12-VO-02A Rev 00
Contract ID : 21ED0125
Contract Name : Construction of Pola ABC Building, Pola, Oriental Mindoro
Location : Pola, Oriental Mindoro
Contractor : Greenfield Construction
ITEMIZED COST OF REVISION
Proposed Variation Order No. 1
1101(33) WIRES AND WIRING DEVICES L.S. 1.00 ### 180,002.45 0.00 - 1.00 84,526.37 1.00 95,476.08
1103(1) LIGHTING FIXTURES sq.m. 1.00 ### 112,092.60 1.00 3,283.10 0.00 - 1.00 115,375.70
804(1)b EMBANKMENT FROM BORROW cu.m. 875.20 0.00 - 875.20 - 25.10 21,967.60 25.10 21,967.60
### ALUMINUM FRAMED GLASS DOOR sq.m. 8,598.85 0.00 - 8,598.85 - 37.96 326,412.20 37.96 326,412.20
1039(1) ALUMINUM CLADDING sq.m. 3,106.07 0.00 - 3,106.07 - 456.09 1,416,648.12 456.09 1,416,648.12
1016(1)a WATERPROOFING, CEMENT-BASE m. 195.38 0.00 - 195.38 - 115.34 22,535.10 115.34 22,535.10
1001(8) SEWER LINE WORKS m. 32,420.46 0.00 - 32,420.46 - 1.00 32,420.46 1.00 32,420.46
1002(4) PLUMBING FIXTURES m. ### 0.00 - 120,979.20 - 1.00 120,979.20 1.00 120,979.20
1002(24) COLD WATER LINES kg. 37,736.21 0.00 - 37,736.21 - 1.00 37,736.21 1.0 37,736.21
1201(8) WATER TANK L.S. ### 0.00 - 367,716.11 - 1.00 367,716.11 1.00 367,716.11
1200(13)a AIRCONDITIONING (PACKAGE/SPLIT TYPE) L.S. ### 0.00 - 947,246.43 - 1.00 947,246.43 1.00 947,246.43
ROMAN
Chief, A. ANTE
Construction Section EDWIN
Chief, PlanningA.
& CABRAL
Design Section
Project Engineer
Conformed:
ANNALIZA M. PLATA
Contractor
PIF-12-VO-02A Rev 00
Contract ID : 21ED0125
Contract Name : Construction of Pola ABC Building, Pola, Oriental Mindoro
Location : Pola, Oriental Mindoro
Contractor : Greenfield Construction
ORIGINAL CONTRACT REVISED CONTRACT DUE TO PREVIOUS V.O. PROPOSED VARIATION ORDER No. ___
PROPOSED REVISED CONTRACT COST DUE
Pay Item No. Pay Item Description CHANGE ORDER TO VARIATION ORDER No. ___ REMARKS
EXTRA WORK ORDER
UNIT QTY UNIT PRICE TOTAL AMOUNT UNIT QTY UNIT PRICE TOTAL AMOUNT ADDITIVE DEDUCTIVE
QTY AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
B.3 PERMITS AND CLEARANCES L.S. 1.00 9,030.00 9,030.00 L.S. 1.00 9,030.00 9,030.00 - - - 1.00 9,030.00
B.5 PROJECT BILLBOARD/ SIGNBOARD EACH 1.00 4,131.87 4,131.87 EACH 1.00 4,131.87 4,131.87 - - - 1.00 4,131.87
OCCUPATION SAFETY & HEALTH
B.7 (2) L.S. 1.00 74,699.78 74,699.78 L.S. 1.00 74,699.78 74,699.78 - - - 1.00 74,699.78
PROGRAM
B.9 MOBILIZATION/DEMOBILIZATION L.S. 1.00 34,672.93 34,672.93 L.S. 1.00 34,672.93 34,672.93 - - - 1.00 34,672.93
800 (1) CLEARING AND GRUBBING M^2 232.80 43.02 10,015.06 M^2 125.82 43.02 5,412.78 - - - 125.82 5,412.78
STRUCTURE EXCAVATION, COMMON
803(1)a M^3 396.75 209.02 82,928.69 M^3 255.82 209.02 53,471.50 - - - 255.82 53,471.50
SOIL
EMBANKMENT FROM
803(1)a M^3 202.08 177.29 35,826.76 M^3 105.14 177.29 18,640.27 - - - 105.14 18,640.27
ROADWAY/STRUCUTRE EXCAVATION
804(4) GRAVEL FILL M^3 24.43 1,214.64 29,673.66 M^3 6.75 1,214.64 8,198.82 - - - 6.75 8,198.82
STRUCTURAL CONCRETE (FOOTINGS
900(1)c2 M^3 121.30 6,145.01 745,389.71 M^3 45.00 6,145.01 276,525.45 - - - 45.00 276,525.45
AND SLAB ON FILL),A 28 DAYS
STRUCTURAL CONCRETE (FOOTING
900(1)c3 M^3 17.93 6,815.96 122,210.16 M^3 11.94 6,815.96 81,382.56 - - - 11.94 81,382.56
TIE BEAMS ) 28 DAYS, A
STRUCTURAL CONCRETE (COLUMN), A
900(1)c4 M^3 34.40 6,815.96 234,469.02 M^3 34.27 6,815.96 233,582.95 - - - 34.27 233,582.95
28 DAYS
STRUCTURAL CONCRETE (SUSPENDED
900(1)c5 M^3 60.21 6,145.01 369,991.05 M^3 31.61 6,145.01 194,243.77 - - - 31.61 194,243.77
SLAB), A 28 DAYS
STRUCTURAL CONCRETE
900(1)c6 M^3 44.94 6,815.96 306,309.24 M^3 23.49 6,815.96 160,106.90 - - - 23.49 160,106.90
(BEAM/GIRDERS), A, 28 DAYS
REINFORCING STEEL (DEFORMED),
902(1)a KG 22302.40 70.74 1,577,671.78 KG 21643.19 70.74 1,531,039.26 - - - 21643.19 1,531,039.26
GRADE 40
Err:509 Err:509 ### Err:509 Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Concurred:
ANNALIZA M. PLATA
Contractor
PIF-12-VO-03A Rev 00
Contract ID :
Contract Name :
Location :
Contractor :
Prepared by: Checked by: Submitted by : Verified as to Unit Cost: Verified as to Quantities
NAME & SIGNATURE NAME & SIGNATURE NAME & SIGNATURE NAME & SIGNATURE NAME & SIGNATURE
BOC
Project Engineer Project Manager Project Director BOD Director
Director
DPWH & Consultant, if any DPWH & Consultant, if any (if BOC is not the IO)
Conformed:
PIF-12-VO-02B Rev 00
Republic of the Philippines
Department of Public Works and Highways
(IMPLEMENTING OFFICE)
(Adress)
PROJECT/LOCATION :
TO:
You are hereby directed to make herein described changes from the plans and specifications of the following described work not included in the plans and specifications:
CHANGE REQUESTED BY :
ITEMIZED QUANTITIES AND COST OF REVISION IS SHOWN ON THE ATTACHED BILL OF QUANTITIES
We the undersigned Contractor/s have given careful consirderation to the change proposed and hereby agree, if Original Contract Amount : :
this proposal is approved that we will provide all equipment, furnish all materials except as maybe otherwise be Revised Contract Amount :
noted and perform all service necessary for work above specified and will accept as full payment thereto the (+) Additive :
prices shown on the attached sheet. (-) Deductive :
Difference of Cost to this Change: :
Net Cost of Previous Change :
Total Cost of Change :
Estimated Revised Contract Amount :
ACCEPTED BY: Percentage of Change in Original Contract :
Original Contract Time :
NAME & SIGNATURE Approved additional Contract Time due to V.O. :
Contractor Revised Contract Time :
DATE: Effectivity of Contract :
Original Expiry Date :
Revised Expiry Date :
PROJECT/LOCATION :
TO:
You are hereby directed to make herein described changes from the plans and specifications of the following described work not included in the plans and specifications:
CHANGE REQUESTED BY :
ITEMIZED QUANTITIES AND COST OF REVISION IS SHOWN ON THE ATTACHED BILL OF QUANTITIES
We the undersigned Contractor/s have given careful consirderation to the change proposed and hereby agree, if this proposal is approved Original Contract Amount : :
that we will provide all equipment, furnish all materials except as maybe otherwise be noted and perform all service necessary for work Revised Contract Amount :
above specified and will accept as full payment thereto the prices shown on the attached sheet. (+) Additive :
(-) Deductive :
Difference of Cost to this Change: :
Net Cost of Previous Change :
Total Cost of Change :
Estimated Revised Contract Amount :
ACCEPTED BY: Percentage of Change in Original Contract :
Original Contract Time :
NAME & SIGNATURE Approved additional Contract Time due to V.O. :
Contractor Revised Contract Time :
Effectivity of Contract :
Original Expiry Date :
Revised Expiry Date :
RECOMMENDING APPROVAL:
PREPARED BY:
SUBMITTED BY APPROVED:
Prepared by: Checked and Submitted by : Submitted by : Verified as to Unit Cost: Verified as to Quantities
NAME & SIGNATURE NAME & SIGNATURE NAME & SIGNATURE NAME & SIGNATURE NAME & SIGNATURE
Project Engineer Project Manager Project Director BOC Director BOD Director
DPWH & Consultant, if any DPWH & Consultant, if any (if BOC is not the IO)
Concurred:
PIF-12-VO-03B Rev 00
Contract ID :
Name of Projec
:
Location :
Contractor :
Concurred:
Volume Computation
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis)
3.87 Months
A.1.1 (11) Provision of Furnitures, Fixtures, Equipment and Appliances for the Field Office for the Engineer
1.00 L.S.
A.1.1 (16) Occupational and Safety and Health Program
3.87 Months
A.1.4 (1) Provision of Progress Photographs
3.87 Months
B.5 Project Billboard/Signboard
2.00 Each
B.7 (1) Occupational Safety & Health Program
3.87 Months
B.8 (1) Traffic Management
3.87 Months
B.9 Mobilization/Demobilization
1.00 L.S.
102 (2) Surplus Common Excavation
243.28 Cu.m
103 (1) a Structure Excavation, Common Soil
177.66 Cu.m
Area Volume
Station Distance
Cut Fill 200 (1) 506 (1) Cut Fill 200 (1) 506 (1)
0+000.00 0.00 5.04 0.00 1.89 0.00 0.00
0+020.00 20.00 0.00 6.01 1.89 50.40 60.10 37.80
0+040.00 20.00 0.00 3.60 1.89 0.00 96.10 37.80
0+060.00 20.00 0.00 1.84 1.74 0.00 54.40 36.30
0+080.00 20.00 0.35 0.35 1.89 3.50 21.90 36.30
0+100.00 20.00 1.31 0.00 1.89 16.60 3.50 37.80
0+120.00 20.00 1.28 0.00 1.89 25.90 0.00 37.80
0+140.00 20.00 3.62 3.14 0.00 49.00 31.40 18.90
0+160.00 20.00 0.98 0.04 1.70 46.00 31.80 17.00
0+180.00 20.00 0.00 1.47 1.70 9.80 15.10 34.00
0+200.00 20.00 0.30 0.66 1.70 3.00 21.30 34.00
0+220.00 20.00 0.00 2.85 1.55 3.00 35.10 32.50
0+240.00 20.00 1.96 3.14 1.69 19.60 59.90 32.40
0+260.00 20.00 0.00 2.90 1.70 19.60 60.40 33.90
0+280.00 20.00 0.00 2.08 1.70 0.00 49.80 34.00
0+300.00 20.00 0.00 2.23 1.70 0.00 43.10 34.00
0+320.00 20.00 0.00 3.74 1.70 0.00 59.70 34.00
0+340.00 20.00 0.00 2.34 1.70 0.00 60.80 34.00
0+360.00 20.00 0.00 1.43 1.70 0.00 37.70 34.00
0+380.00 20.00 0.00 2.75 1.70 0.00 41.80 34.00
0+400.00 20.00 3.12 3.14 1.70 31.20 58.90 34.00
0+420.00 20.00 0.00 3.62 1.89 31.20 67.60 35.90
0+440.00 20.00 0.00 1.32 1.89 0.00 49.40 37.80
0+460.00 20.00 0.42 0.00 1.89 4.20 13.20 37.80
0+480.00 20.00 1.20 0.00 2.09 16.20 0.00 39.80
0+500.00 20.00 2.54 0.00 2.09 37.40 0.00 41.80
0+520.00 20.00 2.66 0.00 2.09 52.00 0.00 41.80
0+540.00 20.00 2.47 0.00 2.09 51.30 0.00 41.80
0+560.00 20.00 3.43 0.00 2.09 59.00 0.00 41.80
0+580.00 20.00 1.10 0.24 2.09 45.30 2.40 41.80
0+600.00 20.00 1.61 0.00 2.09 27.10 2.40 41.80
0+620.00 20.00 0.70 0.45 2.09 23.10 4.50 41.80
0+640.00 20.00 0.96 0.25 2.09 16.60 7.00 41.80
0+660.00 20.00 1.78 0.00 2.09 27.40 2.50 41.80
0+680.00 20.00 1.34 0.44 2.09 31.20 4.40 41.80
0+700.00 20.00 0.00 4.78 2.09 13.40 52.20 41.80
0+720.00 20.00 0.00 6.21 2.09 0.00 109.90 41.80
0+740.00 20.00 1.26 1.01 2.09 12.60 72.20 41.80
0+760.00 20.00 12.69 0.00 2.09 139.50 10.10 41.80
0+780.00 20.00 13.08 0.00 2.09 257.70 0.00 41.80
0+800.00 20.00 5.30 0.00 1.00 183.80 0.00 30.90
0+820.00 20.00 4.96 0.00 1.00 102.60 0.00 20.00
0+840.00 20.00 0.00 2.30 1.00 49.60 23.00 20.00
0+860.00 20.00 1.10 3.66 1.80 11.00 59.60 28.00
0+880.00 20.00 6.54 0.00 1.00 76.40 36.60 28.00
0+900.00 20.00 8.73 0.00 1.00 152.70 0.00 20.00
0+920.00 20.00 4.82 0.00 1.00 135.50 0.00 20.00
0+940.00 20.00 2.24 0.00 1.00 70.60 0.00 20.00
0+960.00 20.00 1.28 0.00 1.00 35.20 0.00 20.00
0+980.00 20.00 0.30 0.31 1.00 15.80 3.10 20.00
1+000.00 20.00 0.00 0.45 1.00 3.00 7.60 20.00
1+008.00 8.00 0.30 0.31 1.00 1.20 3.04 8.00
TOTAL 1008.00 1960.20 1373.54 1697.70 0.00
Area
Station Distance Volume
L/S R/S
Slope Protection
00+142.00 0.00 0.95 0.00
00+160.00 18.00 0.95 17.10
00+180.00 20.00 1.11 20.60
00+200.00 20.00 0.94 20.50
00+220.00 20.00 1.20 21.40
00+238.00 18.00 1.20 21.60
00+240.00 RCPC
00+242.00 2.00 1.18 0.00
00+260.00 18.00 1.18 21.24
00+280.00 20.00 1.44 26.20
00+300.00 20.00 1.14 25.80
00+320.00 20.00 1.34 24.80
00+340.00 20.00 0.85 21.90
00+360.00 20.00 0.74 15.90
00+380.00 20.00 1.38 21.20
Line Canal
00+800.00 - 0.89 0.89 0.00
00+820.00 20.00 0.89 0.89 35.60
00+840.00 20.00 0.89 1.88 45.50
00+858.00 18.00 0.89 2.00 50.94
00+860.00 RCPC
00+862.00 2.00 0.89 0.89 0.00
00+880.00 18.00 0.89 0.89 32.04
00+900.00 20.00 0.89 0.89 35.60
00+920.00 20.00 0.89 0.89 35.60
00+940.00 20.00 0.89 0.89 35.60
00+960.00 20.00 0.89 0.89 35.60
00+980.00 20.00 0.89 0.89 35.60
01+000.00 20.00 0.89 0.89 35.60
01+008.00 8.00 0.89 0.89 14.24
Subtotal 650.16
Headwall and Apron for RCPC
Area
Station Length Volume
Left Right
00+860.00 4.00 2.14 2.42 18.24
Total 668.40
ROMAN A. ANTE
Engineer III
Construction of Pola ABC Building, Pola, Oriental Mindoro
Pola, Oriental Mindoro
#REF!
Item No. / Description : #REF!
Equipment
B.1 a. One Bagger Mixer 1 1 172.00 172.00
b. Concrete Vibrator 1 1 91.25 91.25
c. Water Truck/Pump (16000 L) 1 0.1 2,450.00 245.00
Minor Tools (5% of Labor Cost) 69.10
Sub - Total for B.1 - As Submitted 577.35
Equipment
B.2
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 1,959.35
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted 1.40
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,399.54
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
a. Lumber, Good - 4 uses bd-ft 17.5 45.00 787.50
b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc 0.4 690.00 276.00
F.1
c. Assorted CWN (1kg/100 bd-ft of Lumber) kg 0.7 75.00 52.50
d. Cement bag 9.50 260.00 2,470.00
e. Sand cu.m. 0.50 730.00 365.00
f. Gravel cu.m. 1.00 860.00 860.00
Sub - Total for F.1 - As Submitted 4,811.00
Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,210.54
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% 745.26
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated
I.1 Contractor's Profit (CP) - As Submitted 8% 496.84
I.2 Contractor's Profit (CP) - As Evaluated
J.1 Value Added Tax (VAT) - As Submitted 5% 372.63
J.2 Value Added Tax (VAT) - As Evaluated
K.1 Total Unit Cost - As Submitted 7,825.28
K.2 Total Unit Cost - As Evaluated
VOLUME COMPUTATION
B.3 Permits and Clearances 1.00 L.s.
Backfill Volume From Footing - (Length x Width x Height from Top of Footing to NGL X Qty)
Height from
Backfill Volume BACKFILL
Length Width top of Footing Qty
From Footing VOLUME
to NGL
Backfill Volume From WF - (Perimeter x Thickness x Height from Top of WF to NGL x Qty)
Height from
Backfill Volume BACKFILL
Perimeter Thickness top of Footing Qty
From Footing VOLUME
to NGL
FLOOR SLAB
SLAB AREA THICKNESS QTY VOLUME
119.430 0.1 1 11.943
RAMP
2.890 0.10 1 0.289
PATHWALK
55.000 0.10 1 5.5
Total 17.73
FOOTING
Length Width Thickness Qty.
1 x 1.22 x 0.2 x 2 = 0.488
900(1)c3 Structural Concrete (Footing Tie Beams ) 28 Days, A 11.94 cu.m.
FLOOR SLAB
AREA THICKNESS QTY VOLUME
Suspended Slab 232.90 x 0.125 x 1.00 = 29.1125
Canopy 7.58 x 0.100 x 1.00 = 0.758
Counter top 3.74 x 0.100 x 1.00 = 0.374
Stair Landing 3.4425 x 0.125 x 2.00 = 0.8606
Total 31.11
PLATFORM
LENGTH WIDTH THICKNESS QTY VOLUME
2.743 1.22 0.152 0.98 0.5
Total 0.5
Total Volume 31.61
900(1)c6 Structural Concrete (Beam/Girders), A, 28 Days 23.49 cu.m.
GIRDER
Length Width Height Qty Volume
4.00 x 0.25 x 0.40 x 4.00 = 1.60000
4.00 x 0.25 x 0.40 x 3.00 = 1.20000
2.05 x 0.25 x 0.40 x 1.00 = 0.20500
1.95 x 0.25 x 0.30 x 1.00 = 0.14625
2.55 x 0.25 x 0.40 x 3.00 = 0.76500
2.55 x 0.25 x 0.30 x 1.00 = 0.19125
4.20 x 0.25 x 0.40 x 2.00 = 0.84000
4.20 x 0.25 x 0.30 x 1.00 = 0.31500
1.95 x 0.25 x 0.40 x 2.00 = 0.39000
3.15 x 0.25 x 0.40 x 2.00 = 0.63000
1.65 x 0.25 x 0.40 x 2.00 = 0.33000
4.00 x 0.25 x 0.40 x 2.00 = 0.80000
1.27 x 0.25 x 0.40 x 1.00 = 0.12650
2.74 x 0.25 x 0.40 x 2.00 = 0.54700
4.00 x 0.25 x 0.40 x 5.00 = 2.00000
2.64 x 0.25 x 0.40 x 1.00 = 0.26350
1.00 x 0.25 x 0.40 x 2.00 = 0.20000
4.00 x 0.25 x 0.40 x 4.00 = 1.60000
4.00 x 0.25 x 0.40 x 3.00 = 1.20000
2.05 x 0.25 x 0.40 x 1.00 = 0.20500
1.95 x 0.25 x 0.30 x 1.00 = 0.14625
2.55 x 0.25 x 0.40 x 3.00 = 0.76500
4.20 x 0.25 x 0.40 x 2.00 = 0.84000
1.95 x 0.25 x 0.40 x 2.00 = 0.39000
3.15 x 0.25 x 0.40 x 2.00 = 0.63000
1.65 x 0.25 x 0.40 x 2.00 = 0.33000
4.00 x 0.25 x 0.40 x 2.00 = 0.80000
1.27 x 0.25 x 0.40 x 1.00 = 0.12650
2.74 x 0.25 x 0.40 x 2.00 = 0.54700
4.00 x 0.25 x 0.40 x 4.00 = 1.60000
1.37 x 0.25 x 0.40 x 1.00 = 0.13650
2.64 x 0.25 x 0.40 x 2.00 = 0.52700
2.55 x 0.25 x 0.30 x 2.00 = 0.38250
2.74 x 0.25 x 0.30 x 2.00 = 0.41025
Total 21.1855
BEAM
Area Thickness Qty Volume
0.05 x 0.90 x 32 x 1.440
0.84 x 0.90 x 1 x 0.756
Total 2.20
W D L No. Volume
0.20 x 0.20 x 2.743 x 1 = 0.1097
Total 0.1097
Total Volume 23.49
F1
LENGTH WIDTH PCS
6.00 x 1.58 x 63 = 597.24
6.00 x 1.58 x 17 = 161.16
6.00 x 1.58 x 20 = 189.6
6.00 x 1.58 x 16 = 151.68
6.00 x 1.58 x 10 = 94.8
6.00 x 1.58 x 11 = 104.28
6.00 x 1.58 x 17 = 161.16
6.00 x 0.89 x 3 = 16.02
Total 1475.94
FTB
LENGTH WIDTH PCS
6.00 x 0.62 x 40.00 = 148.8
6.00 x 0.62 x 30.00 = 111.6
6.00 x 0.62 x 7.00 = 26.04
6.00 x 0.62 x 24.00 = 89.28
6.00 x 0.62 x 22.00 = 81.84
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 6.00 = 22.32
6.00 x 0.62 x 18.00 = 66.96
6.00 x 0.62 x 6.00 = 22.32
6.00 x 0.62 x 16.00 = 59.52
6.00 x 0.62 x 20.00 = 74.4
6.00 x 0.62 x 6.00 = 22.32
6.00 x 0.62 x 16.00 = 59.52
6.00 x 0.62 x 40.00 = 148.8
Total 985.8
WF
LENGTH WIDTH PCS
6.00 x 0.62 x 2 = 7.44
6.00 x 0.62 x 1 = 3.72
Total 11.16
C3
LENGTH WIDTH PCS
6.00 x 2.47 x 181.00 = 2682.42
6.00 x 2.47 x 27.00 = 400.14
6.00 x 2.47 x 40.00 = 592.8
6.00 x 2.47 x 13.00 = 192.66
6.00 x 2.47 x 40.00 = 592.8
6.00 x 1.58 x 10.00 = 94.8
6.00 x 1.58 x 10.00 = 94.8
6.00 x 2.47 x 40.00 = 592.8
6.00 x 2.47 x 20.00 = 296.4
6.00 x 2.47 x 20.00 = 296.4
6.00 x 2.47 x 40.00 = 592.8
6.00 x 2.47 x 13.00 = 192.66
6.00 x 2.47 x 9.00 = 133.38
6.00 x 0.62 x 180.00 = 669.6
6.00 x 0.62 x 34.00 = 126.48
6.00 x 0.62 x 40.00 = 148.8
6.00 x 0.62 x 17.00 = 63.24
6.00 x 0.62 x 40.00 = 148.8
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 40.00 = 148.8
6.00 x 0.62 x 20.00 = 74.4
6.00 x 0.62 x 17.00 = 63.24
6.00 x 0.62 x 40.00 = 148.8
6.00 x 0.62 x 17.00 = 63.24
6.00 x 0.62 x 20.00 = 74.4
6.00 x 0.62 x 144.00 = 535.68
6.00 x 0.62 x 28.00 = 104.16
6.00 x 0.62 x 32.00 = 119.04
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 32.00 = 119.04
6.00 x 0.62 x 9.00 = 33.48
6.00 x 0.62 x 9.00 = 33.48
6.00 x 0.62 x 32.00 = 119.04
6.00 x 0.62 x 16.00 = 59.52
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 32.00 = 119.04
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 16.00 = 59.52
Total 10047.06
B3
LENGTH WIDTH PCS
6.00 x 1.58 x 20.00 = 189.6
6.00 x 1.58 x 15.00 = 142.2
6.00 x 1.58 x 3.00 = 28.44
6.00 x 1.58 x 2.00 = 18.96
6.00 x 1.58 x 9.00 = 85.32
6.00 x 1.58 x 3.00 = 28.44
6.00 x 1.58 x 10.00 = 94.8
6.00 x 1.58 x 4.00 = 37.92
6.00 x 1.58 x 6.00 = 56.88
6.00 x 1.58 x 8.00 = 75.84
6.00 x 1.58 x 4.00 = 37.92
6.00 x 1.58 x 10.00 = 94.8
6.00 x 1.58 x 2.00 = 18.96
6.00 x 1.58 x 6.00 = 56.88
6.00 x 1.58 x 25.00 = 237
6.00 x 1.58 x 3.00 = 28.44
6.00 x 1.58 x 4.00 = 37.92
6.00 x 1.58 x 16.00 = 151.68
6.00 x 1.58 x 12.00 = 113.76
6.00 x 1.58 x 2.00 = 18.96
6.00 x 1.58 x 2.00 = 18.96
6.00 x 1.58 x 9.00 = 85.32
6.00 x 1.58 x 8.00 = 75.84
6.00 x 1.58 x 4.00 = 37.92
6.00 x 1.58 x 6.00 = 56.88
6.00 x 1.58 x 4.00 = 37.92
6.00 x 1.58 x 8.00 = 75.84
6.00 x 1.58 x 2.00 = 18.96
6.00 x 1.58 x 6.00 = 56.88
6.00 x 1.58 x 16.00 = 151.68
6.00 x 1.58 x 2.00 = 18.96
6.00 x 1.58 x 6.00 = 56.88
6.00 x 1.58 x 6.00 = 56.88
6.00 x 1.58 x 6.00 = 56.88
6.00 x 0.62 x 36.00 = 133.92
6.00 x 0.62 x 27.00 = 100.44
6.00 x 0.62 x 7.00 = 26.04
6.00 x 0.62 x 6.00 = 22.32
6.00 x 0.62 x 21.00 = 78.12
6.00 x 0.62 x 7.00 = 26.04
6.00 x 0.62 x 20.00 = 74.4
6.00 x 0.62 x 9.00 = 33.48
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 16.00 = 59.52
6.00 x 0.62 x 12.00 = 44.64
6.00 x 0.62 x 18.00 = 66.96
6.00 x 0.62 x 6.00 = 22.32
6.00 x 0.62 x 16.00 = 59.52
6.00 x 0.62 x 45.00 = 167.4
6.00 x 0.62 x 7.00 = 26.04
6.00 x 0.62 x 10.00 = 37.2
6.00 x 0.62 x 36.00 = 133.92
6.00 x 0.62 x 27.00 = 100.44
6.00 x 0.62 x 7.00 = 26.04
6.00 x 0.62 x 6.00 = 22.32
6.00 x 0.62 x 21.00 = 78.12
6.00 x 0.62 x 20.00 = 74.4
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 16.00 = 59.52
6.00 x 0.62 x 12.00 = 44.64
6.00 x 0.62 x 18.00 = 66.96
6.00 x 0.62 x 6.00 = 22.32
6.00 x 0.62 x 16.00 = 59.52
6.00 x 0.62 x 36.00 = 133.92
6.00 x 0.62 x 6.00 = 22.32
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 14.00 = 52.08
6.00 x 0.62 x 14.00 = 52.08
Total 4443.72
FS
LENGTH WIDTH PCS
6.00 x 0.62 x 143 = 531.96
6.00 x 0.89 x 284 = 1516.56
6.00 x 0.62 x 14 = 52.08
6.00 x 0.62 x 12 = 44.64
6.00 x 0.62 x 4 = 14.88
6.00 x 0.62 x 22 = 81.84
6.00 x 0.62 x 18 = 66.96
6.00 x 0.62 x 7 = 26.04
6.00 x 0.62 x 47 = 174.84
Total 2509.8
CS
LENGTH WIDTH PCS
6.00 x 0.62 x 5.00 = 18.6
6.00 x 0.62 x 6.00 = 22.32
Total 40.92
L-H L-V
F2 20.00 + 24.4 = 44.40
W H No.
C1 4.00 x 5.982 x 2 = 47.86
C2 18.00 + 24 x 1.2 = 50.4
Total 98.26
L H No.
B1 2.74 x 4 x 1 = 10.972
B2 8.93 + 0.07 x 1.2 = 10.80
Total 21.772
L-H L-V
W1 28.57 + 26.14704 = 54.71
W2 14.61 + 16.12884 = 30.73468
Total 85.45
GRAND TOTAL ((F2+C1+B1+W1+W2)*1.58) + ((C2+B2)*0.62) + F1+FTB+WF+C3+B3+FS+CS
GRAND TOTAL 21625.19
902(2) Formworks And Falseworks
492.69
FTB (WIDTH+DEPTH) xTOTAL SPAN x QUANTITY
Width Depth Total Span Qty. Surface Area
0.25 + 1.00 x 4.00 x 4.00 = 20.00
0.25 + 1.00 x 4.00 x 3.00 = 15.00
0.25 + 1.00 x 2.25 x 1.00 = 2.8125
0.25 + 1.00 x 2.55 x 3.00 = 9.5625
0.25 + 1.00 x 4.20 x 2.00 = 10.50
0.25 + 1.00 x 1.95 x 2.00 = 4.875
0.25 + 1.00 x 1.65 x 1.00 = 2.0625
0.25 + 1.00 x 3.15 x 2.00 = 7.875
0.25 + 1.00 x 1.27 x 1.00 = 1.58125
0.25 + 1.00 x 2.74 x 2.00 = 6.8375
0.25 + 1.00 x 4.00 x 2.00 = 10.00
0.25 + 1.00 x 1.37 x 1.00 = 1.70625
0.25 + 1.00 x 2.64 x 2.00 = 6.5875
0.25 + 1.00 x 4.00 x 4.00 = 20.00
Total 119.4
COLUMN (WIDTH+DEPTH) xTOTAL SPAN x QUANTITY
Width Depth Total Span Qty. Surface Area
0.40 + 0.80 x 9.20 x 9.00 = 99.36
0.25 + 0.80 x 9.20 x 2.00 = 19.32
0.40 + 0.80 x 9.20 x 2.00 = 22.08
0.25 + 0.80 x 9.20 x 1.00 = 9.66
0.40 + 0.80 x 9.20 x 2.00 = 22.08
0.25 + 0.50 x 9.20 x 1.00 = 6.90
0.25 + 0.50 x 9.20 x 1.00 = 6.90
0.40 + 0.80 x 9.20 x 2.00 = 22.08
0.40 + 0.80 x 9.20 x 1.00 = 11.04
0.25 + 0.80 x 9.20 x 1.00 = 9.66
0.40 + 0.80 x 9.20 x 2.00 = 22.08
0.25 + 0.80 x 9.20 x 1.00 = 9.66
0.40 + 0.80 x 1.00 x 4.00 = 4.80
Total 265.62
Total / 2 132.81
SUSPENDED SLAB
Area 1 Area 2
117.90 + 115 = 232.90
Total 232.90
CANOPY AREA 1
3.79 x 2 = 7.58
Total 7.58
Grand Total 492.69
1046(2)a1 Chb Non-Load Bearing (Including Reinforcing Steel),100Mm 97.92
Wall Total
Height
Length Wall Area
1st Floor 12.80 x 3.4 = 43.52
2nd Floor 17.00 x 3.2 = 54.4
Total 97.92
1046(2)a2 Chb Non-Load Bearing (Including Reinforcing Steel),150Mm 464.86
Wall Total
Span
Length Wall Area
1st floor 55.70 3.40 189.38
2nd floor 55.70 3.20 178.24
Roof Deck 55.70 1.00 55.7
Roof Deck 2 13.40 3.10 41.54
Total 464.86
1021(1)c Cement Floor Finish, With Floor Hardener 112.45
Length Width
56.23 2 112.45
1014(1)b2 Prepainted Metal Sheets Long Span, Corrugated Type, above 0.427 mm, Long Span 6.21
Length Width
2.3 2.7 6.21
1013(2)b1 Fabricated Metal Roofing Accessory, Gauge 24, Gutter 2.50
Length 1
2.5 2.5
Prepared by:
FRANKLIN S. MAURICIO
General Manager ROBERT M. GONDA
Project Engineer
Noted By:
ROMAN A. ANTE
Engineer III
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Mindoro Oriental District Engineering Office
Masipit, Calapan City, Oriental Mindoro
DEDUCTIVE QUANTITIES
Items Reason
800 (1) Clearing And Grubbing
803(1)a Structure Excavation, Common Soil
803(1)a Embankment From Roadway/Strucutre Excavation
804(4) Gravel Fill
900(1)c2 Structural Concrete (Footings And Slab On Fill),A 28 Days
900(1)c3 Structural Concrete (Footing Tie Beams ) 28 Days, A
900(1)c4 Structural Concrete (Column), A 28 Days
900(1)c5 Structural Concrete (Suspended Slab), A 28 Days
900(1)c6 Structural Concrete (Beam/Girders), A, 28 Days
902(1)a Reinforcing Steel (Deformed), Grade 40
1046(2)a1 Chb Non-Load Bearing (Including Reinforcing Steel),100Mm
1046(2)a2 Chb Non-Load Bearing (Including Reinforcing Steel),150Mm
1010(4) Wooden Doors And Windows
1021(1)c Cement Floor Finish, Plain
1003(1)a1 Ceiling, Fiber Cement Board, 4.5Mm, Metal Frame Due To revision of Plans
1018(2) Unglazed Tiles
1032(1)a Painting Works, Masonry/Concrete
1014(1)b2
Prepainted Metal Sheets Long Span, Rib Type, Above 0.427Mm, Long Span
1013(2)b1 Fabricated Metal Roofing Accessory, Gauge 24, Gutter
1013(2)a2 Fabricated Metal Roofing Accessory, Gauge 26, Flashing
1047(2)b Structural Steel Purlins
1001(9) Storm Drainage And Downspout
1001(11) Septic Vault (Concrete/Chb)
1001(5)b Catch Basin
1100(10) Conduit, Boxes, And Fittings (Conduit Works/Conduit Rough-In)
1101(33) Wires And Wiring Devices
1102(1) Panelboard With Main And Branch Breakers
PIF-12-VO-04 Rev 00
NEW ITEMS
804(1)b Embankment From Borrow
1,007.00 Aluminum Framed Glass Door
1,008.00 Aluminum Glass Window (Sliding/Casement/Awning/Fixed Type)
1039(1) Aluminum Cladding
1016(1)a Waterproofing, Cement-Base
1001(8) Sewer Line Works Due To revision of Plans
DELETED ITEMS
Items Reason
PIF-12-VO-04 Rev 00
Republic of the Philippines
DEPARTMENT OF PUBLIC WORK AND HIGHWAYS
MINDORO ORIENTAL
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE IV-B
Masipit, Calapan City, Oriental Mindoro
Calapan City, Oriental Mindoro
March 8, 2022
MEMORANDUM
a) Item
804(1)b Embankment From Borrow
1007 Aluminum Framed Glass Door
1008 Aluminum Glass Window (Sliding/Casement/Awning/Fixed Type)
1039(1) Aluminum Cladding
1016(1)a Waterproofing, Cement-Base
1001(8) Sewer Line Works
1002(4) Plumbing Fixtures
1002(24) Cold Water Lines
1102(10) Pole Mounted Distribution Transformer With Complete Accessories
1201(8) Water Tank
1200(13)a Airconditioning (Package/Split Type)
For Deletion:
a) Item
1008 (1)a Aluminum Glass Window (Sliding Type)
1008(1)b Aluminum Glass Windows (Casement Type)
1003(11)a1Fascia Board
1047(2)a Structural Steel, Trusses
1047(6) Metal Structure Accesorries (Steel Plates)
1047(7)a Metal Structure Accessories, Bolts
1002(27) Plumbing Works
ROBERT M. GONDA
Project Engineer
R4B11.2CCM/RAA/EDU
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Mindoro Oriental District Engineering Office
Calapan City, Oriental Mindoro
March 4, 2022
EXECUTIVE SUMMARY
( Variation Order No. 01 )
5 Reason for Request : Design revision to align actual site condition. Structural design requirement
partake on major addition.
7 Contractual Data :
ORIGINAL REVISED
7.1 Original Contract Amount Php 9,486,378.61
7.2 Original Contract Duration 238 Calendar Days
7.3 Effectivity of Contract March 08, 2022
7.4 Original Expiry Date
7.5 Revised Contract Amount if CO is approved Php 9,486,360.23
7.6 Additional Contract Time due To CO N/A
Revised Contract Duration if CO is
7.7 N/A
approved
7.8 Revised Expiry Date if CO Is Approved N/A
10 Remarks :
The Variation Order No.1 was introduced to suit actual field conditions due to site problem leading to
revision of plans.
The Variation Order No. 1 is in accordance with Section IV – General Conditions of Contract, Clause 42.1,
which states that: “ Variation Order may be issued by the Procuring Entity to cover any increase/decrease in
quantities, including the introduction of new work items that are not included in the original contract or
reclassification of work items that are either due to change of plans, design or alignment to suit actual field
conditions resulting in disparity between the preconstruction plans used for purposes of bidding and the “As-Staked
Plans” or construction drawings prepared after a joint survey by the Contractor and Procuring Entity after award of
the contract, provided that the cumulative amount of the Variation Order does not exceed ten percent ( 10.00% )
of the original project cost. The addition/deletion of Works should be within the general scope of the project as bid
and awarded.”
In view of the foregoing, the herein Variation Order No. 01 is respectfully forwarded for consideration and
approval.
ROMAN A. ANTE
Chief, Construction Section
Approved by:
March 8, 2022
Sir:
May I respectfully request the services of the District Inspectorate Team for Civil Works to conduct on-the-
spot inspection/assessment/evaluation to verify the need for the work to be prosecuted.
Under Variation Order No. 01 for the hereunder project under my supervision.
Contract ID : 21ED0125
CONSTRUCTION OF POLA ABC BUILDING, POLA,
Name of Project :
ORIENTAL MINDORO
ROBERT M. GONDA
Project Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Mindoro Oriental District Engineering Office
Calapan City, Oriental Mindoro
March 4, 2022
MEMORANDUM
You are hereby directed to undertake within two (2) days from receipt hereof a validation/
assessment/evaluation of the proposed works for the above-subject project to be covered under the proposed
Variation Order.
You shall submit within two (2) days after the conduct of your inspection a report of your findings and
recommendations.
For Compliance.
March 8, 2022
MEMORANDUM
In compliance with your memorandum dated March 04, 2022, we the members of the District Inspectorate
Team for Civil Works, conducted a joint inspection/assessment/evaluation on March 07, 2022 to verify the need for
and reasonableness of the work to be prosecuted under Variation Order No. 01 of the following project/s:
Contract ID : 21ED0125
CONSTRUCTION OF POLA ABC BUILDING, POLA,
Name of Project :
ORIENTAL MINDORO
Location : Calapan City, Oriental Mindoro
Original Contract Amount : Php 9,486,378.61
Contractor : Greenfield Construction
Hereunder are our findings and recommendation.
FINDINGS:
1. The Variation Order entails the increase in the original quantity of Item 902(1)a - Formworks and
Falseworks, 1027(1) - Cement Plaster Finish, 1051(6) - Railings, 1018(5) - Glazed Tiles, 1103(1) -
Lighting Fixtures, decrease of Item 800(1) - Clearing and Grubbing, 803(1)a - Structure Excavation,
Common Soil, 804(1)a - Embankment from Roadway/Structure Excavation, 804(4) - Gravel Fill, 900(1)c2
- Structural Concrete (Footings and Slab on Fill),A 28 Days, 900(1)c3 - Structural Concrete (Footing Tie
Beams),A 28 Days, 900(1)c4 - Structural Concrete (Column),A 28 Days, 900(1)c5 - Structural Concrete
(Suspended Slab),A 28 Days, 900(1)c6 - Structural Concrete (Beam/Girders),A 28 Days, 902(1)a -
Reinforcing Steel (Deformed),Grade 40, 1046(2)a1 - CHB Non-Load Bearing (Including Reinforcing
Steel),100mm, 1046(2)a2 - CHB Non-Load Bearing (Including Reinforcing Steel),150mm, 1010(4) -
Wooden Doors and Windows, 1021(1)c - Cement Floor Finish, Plain, 1003(1)a1 - Ceiling, Fiber Cement
Board, 4.5mm, Metal Frame, 1018(2) - Unglazed Tiles, 1032(1)a - Painting Works, Masonry/Concrete,
1014(1)b2 - Prepainted Metal Sheets Long Span, Rib Type, Above 0.427mm, Long Span, 1013(2)b1 -
Fabricated Metal Roofing Accessory, Gauge 24, Gutter, 1013(2)a2 - Fabricated Metal Roofing Accessory,
Gauge 26, Flashing, 1047(2)b - Structural Steel Purlins, 1001(9) - Storm Drainage and Downspout,
1001(11) - Septic Vault (Concrete/CHB), 1001(5)b - Catch Basin, 1100(10) - Conduit, Boxes, and Fittings
(Conduit Works/Conduit Rough-In), 1101(33) - Wires and Wiring Devices, 1102(1) - Panelboard with
Main and Branch Breakers, introduction of new Item, 804(1)b - Embankment from Borrow, 1007 -
Aluminum Framed Glass Door, 1008 - Aluminum Glass Window (Sliding/Casement/Awning/Fixed Type),
1039(1) - Aluminum Cladding, 1016(1)a - Waterproofing, Cement Base, 1001(8) - Sewer Line Works,
1002(4) - Plumbing Fixtures, 1002(24) - Cold Water Lines, 1102(10) - Pole Mounted Distribution
Transformer with Complete Accessories, 1201(8) - Water Tank, 1200(13)a - Airconditioning
(Package/Split Type), deletion of Item 1008(1)a, Aluminum Glass Window (Sliding Type), 1008(1)b,
Aluminum Glass Windows (Casement Type), 1047(2)a, Structural Steel, Trusses, 1003(11)a1, Fascia
Board, 1047(6), Metal Structure Accessories (Steel Plates), 1047(7)a, Metal Structure Accessories, Bolts,
1002(27), Plumbing Works
2. The Items of Work involved are the following:
900(1)c2 Structural Concrete (Footings And Slab On Fill),A 28 Days Decrease in quantity
1003(1)a1 Ceiling, Fiber Cement Board, 4.5Mm, Metal Frame Decrease in quantity
1013(2)a2 Fabricated Metal Roofing Accessory, Gauge 26, Flashing Decrease in quantity
RECOMMENDATION:
Since the proposed works are necessary to suit actual field conditions and for the utilization of savings
due to increase in quantities of some items of work which were found reasonable, we hereby recommend favorable
consideration and/or approval of the Variation Order.
Robert M. GONDA
Project Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Mindoro Oriental District Engineering Office
Calapan City, Oriental Mindoro
Gentlemen;
In connection with the CONSTRUCTION OF POLA ABC BUILDING, POLA, ORIENTAL MINDORO, under your
contract and in accordance with the provisions and guidelines for the preparation, issuance and approval of and
commencement of the work under Variation Order, Extra Work Order and negotiated contract under MPW
Memorandum Circular No. 45 dated March 21, 1997 and pursuant to the implementing rules and regulations of R.A.
9184, You are hereby directed to perform the following additional works:
Approved By: