You are on page 1of 147

ANNEX A

BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING Appropriation :


Source of Fund :
Project ID : Target Start Date :
Location : Total Project Duration :
Project Description :

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF!
Part II Other General Requirements #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF!
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF!
PART C FINISHING WORKS #REF!
PART D PLUMBING/SANITARY WORKS #REF!
PART E ELECTRICAL WORKS #REF!

Total

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor #REF! A. Total Direct Cost #REF!
2. Materials #REF! B. OCM and Profit #REF!
3. Rental of Equipment #REF! C. Value Added Tax #REF!
4. Provisional Sum / Daywork D. Total Construction Cost #REF!
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit #REF! E. Eng'g & Administrative Overhead, % #REF!
6. Value Added Tax #REF! F. RROW Acquisition
7. EAO, % G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST H. TOTAL ESTIMATED COST #REF!

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning/Const. Section/Division/Consultant Planning/Const. Section/Division/UPMO Planning/Construction Division/BOC
Republic of the Philippines
Department of Public Works and Highways ANNEX A
Region IV-B, MIMAROPA
OFFICE OF THE DISTRICT ENGINEER
Masipit, Calapan City, Oriental Mindoro FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : Construction/Improvement/Rehabilitation/Completion of Various Multi-Purpose Buildings Appropriation : 10,000,000


(Covered Court, Brgy. Hall, Evacuation Center), Baco, Oriental Mindoro Source of Fund : GAA 2022
Project ID : Target Start Date :
Location : Baco, Oriental Mindoro Total Project Duration : 270 C.D.
Project Description : Total No. of Working Days : 225 C.D.
Total No. of Pre-Determined : 45 C.D.
Non-Working Days
Geotag Coordinates: :

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part II Other General Requirements 1.43% 114,653.66
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 0.67% 54,116.26
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.36% 2,763,954.17
PART C FINISHING WORKS 44.39% 3,570,810.22
PART D PLUMBING/SANITARY WORKS 6.41% 515,928.09
PART E ELECTRICAL WORKS 2.84% 228,431.72

Total 100% 8,043,929.40

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 1,125,617.51 A. Total Direct Cost 8,043,929.40
2. Materials 5,775,185.60 B. OCM and Profit 1,607,865.43
3. Rental of Equipment 347,091.01 C. Value Added Tax (5%) 482,589.79
4. Provisional Sum / Daywork D. Total Construction Cost 10,134,384.62
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 1,607,865.43 E. Eng'g & Administrative Overhead, 2% 200,000.00
6. Value Added Tax (5%) 482,589.79 F. RROW Acquisition
7. EAO, 0.2 % 200,000.00 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 10,334,384.62 H. TOTAL ESTIMATED COST 10,334,384.62
Note: 1.Prices of Materials were based on CMPD 2020 4th Quarter and Labor based on June 2020 rates in Region IV-B

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Recommending Approval: Approved:

RAMIR G. BASA EDWIN A. CABRAL ALBIEN M. MAHIA ERWIN DG. UMALI


Engineer II CHIEF, PLANNING AND DESIGN OIC-ASSISTANT DISTRICT ENGINEER OIC - OFFICE OF THE DISTRICT ENGINEER
Construction/Improvement/Rehabilitation/Completion of Various Multi-Purpose Buildings

FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Plate Compactor (400-500 Gasoline Engine) 5 hp 1 31
2 One Bagger Mixer 4 - 6 ft3/min 1 32
3 Bar Cutter (25 mm Maximum Rebar ø) Three phase 1 33 `
4 Bar Bender (25 mm Maximum Rebar ø (Grade 40)) Single Phase 1 34
5 Welding Machine (Electric Driven/DC Output) 500 amp 1 35
6 Cutting Outfit 1 36
7 37
8 38
9 39
10 40
11 41
12 42
13 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL 6 SUB-TOTAL
TOTAL 6
Construction/Improvement/Rehabilitation/Completion of Various Multi-Purpose Buildings

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED

PART I FACILITIES FOR THE ENGINEER

I.1.1 Offices and Laboratory for the Engineer


A.1.2 (4) Provision of 4x2 Pick-up Type Service Vehicle fir the Engineer On Bare Rental Basis - mo - #DIV/0! #DIV/0! -

A.1.2 (6) Operation and Maintenance of 4x2 Pick-up Type Service Vehicle for the Engineer - mo - #DIV/0! #DIV/0! -

TOTAL OF PART I -

PART II OTHER GENERAL REQUIREMENTS

B.3 Permits and Clearances 1.00 l.s. 13,700.00 13,700.00 14,385.00 0.17

B.5 Project Billboard/ Sign Board 1.00 ea 3,444.42 3,444.42 4,339.97 0.04

B.7 (2) Occupational Safety and Health Program 1.00 l.s. 67,509.24 67,509.24 76,555.48 0.84

B.9 Mobilization/Demobilization 1.00 l.s. 30,000.00 30,000.00 31,500.00 0.37

B.13 Additional Geotechnical Investigation (2 holes) - l.s. - #DIV/0! #DIV/0! -

TOTAL OF PART II 114,653.66

Project ID

(Project Component ID - Description)

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS

PART A EARTHWORKS

101(1) Removal of Structures and Obstruction - l.s. - #DIV/0! #DIV/0! -

800 (1) Clearing and Grubbing 125.82 m2 4,587.82 36.46 45.94 0.06

802(2) Surplus Common Excavation - m3 - #DIV/0! #DIV/0! -

803 (1) a Structure Excavation, Common Soil 255.82 m3 21,496.77 84.03 105.88 0.27

804 (1) a Embankment from Roadway/Structure Excavation 105.14 m3 3,770.73 35.86 45.19 0.05

804 (1) b Embankment from Borrow 25.10 m3 16,074.32 640.51 807.05 0.20

804 (4) Gravel Fill 6.75 m3 8,186.62 1,213.46 1,528.96 0.10

1706(1) Overhaul, Cubic Meter-Kilometer - km - #DIV/0! #DIV/0! -

TOTAL OF PART A 54,116.26

PART B PLAIN AND REINFORCED CONCRETE WORKS

900(1)c2 Structural Concrete (Footings and Slab on Fill), A, 28 days 45.00 m3 232,995.87 5,177.82 6,524.05 2.90
Structural Concrete (Footing Tie Beams), 28 days, A
900(1)c3 11.94 m3 67,832.02 5,681.07 7,158.15 0.84
Structural Concrete (Column), A, 28 days
900(1)c4 34.27 m3 194,672.61 5,681.07 7,158.15 2.42

900(1)c5 Structural Concrete (Suspended Slab), A, 28 days 31.61 m3 179,600.26 5,681.07 7,158.15 2.23
Structural Concrete (Beams/Girders), A, 28 days
900(1)c6 23.49 m3 133,455.36 5,681.07 7,158.15 1.66

400 (37) a Micro piles, 0.20 m - l.m - #DIV/0! #DIV/0! -

902 (1) a Reinforcing Steel (Deformed), Grade 40 21,625.19 kg 1,754,388.26 81.13 102.22 21.81

903 (2) Formworks and Falseworks 492.69 m2 201,009.79 407.98 514.06 2.50

1052(29) Micro Piles - m - #DIV/0! #DIV/0! -

TOTAL OF PART B 2,763,954.17

PART C FINISHING

C.1 Termite Control Works


1000 (1) Soil Poisoning - L - #DIV/0! #DIV/0! -

Sub-Total C.1 -

C.2. Masonry Works


1046 (2) a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm 97.92 m2 65,905.47 673.05 848.05 0.82

1046 (2) a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm 464.86 m2 475,075.60 1,021.98 1,287.69 5.91

Sub-Total C.2 540,981.07

C.3 Fabricated Materials


1010 (4) Wooden Doors and Windows 1.00 l.s. 57,694.82 57,694.82 72,695.47 0.72

1006 (6) Steel Doors and Frames - l.s. - #DIV/0! #DIV/0! -

1007 Aluminum Framed Glass Door 37.96 m2 286,605.30 7,550.19 9,513.24 3.56

1008 Aluminum Glass Window (Sliding/Casement/Awning/Fixed Type) 41.94 m2 263,493.88 6,282.64 7,916.13 3.28

1008(1) Aluminum Glass Window (Sliding Type) - m2 - #DIV/0! #DIV/0! -

1008(1)b Aluminum Glass Window (Casement Type) - m2 - #DIV/0! #DIV/0! -

1004 (2) Finishing Hardware 1.00 l.s. 15,705.00 15,705.00 19,788.30 0.20

1003 (17) Carpentry and Joinery Works - l.s. - #DIV/0! #DIV/0! -

1722(1)c Fence, Cyclone/Welded Wire, Square Meter - l.s. - #DIV/0! #DIV/0! -

1038(1) Reflective Insulation - m2 - #DIV/0! #DIV/0! -

1003 (4) Cabinets, Each - ea - #DIV/0! #DIV/0! -

Sub-Total C.3 623,499.00


Construction/Improvement/Rehabilitation/Completion of Various Multi-Purpose Buildings

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED

C.4 Finishing Works


1021 (1) c Cement Floor Finish, with Floor Hardener 112.45 m2 32,395.88 288.09 363.00 0.40

1027 (1) Cement Plaster Finish 1,125.56 m2 190,999.23 169.69 213.81 2.37

1051 (6) Railing 1.00 l.s. 26,984.74 26,984.74 34,000.77 0.34

1003 (1) a1 Ceiling, Fiber Cement Board, 4.5mm, Metal Frame 295.64 m2 250,491.29 847.28 1,067.58 3.11

1039(1) Aluminum Cladding 456.09 m2 1,173,135.25 2,572.17 3,240.94 14.58

1016 (1)a Waterproofing ,Cement-Base 115.34 m2 19,127.60 165.84 208.95 0.24

1018 (1) Glazed Tiles and Trims 217.66 m2 338,890.45 1,556.97 1,961.78 4.21

1018 (2) Unglazed Tiles 102.64 m2 146,658.93 1,428.87 1,800.37 1.82

1003 (1) a1 Ceiling, Fiber Cement Board, 4.5mm, Metal Frame - m2 - #DIV/0! #DIV/0! -

Sub-Total C.4 2,178,683.37

C.5 Painting Works


1032 (1) a Painting Works, Masonry/Concrete 562.78 m2 132,915.50 236.18 297.58 1.65

1032 (1) b Painting Works, Wood - m2 - #DIV/0! #DIV/0! -

1032 (1) c Painting Works, Steel - m2 - #DIV/0! #DIV/0! -

411(2) Paint - m2 - #DIV/0! #DIV/0! -

Sub-Total C.5 132,915.50

C.6 Roof Framing and Roofing Works


1014 (1) b2 Prepainted Metal Sheets Long Span, Rib Type, above 0.427 mm, Long Span - m2 - #DIV/0! #DIV/0! -

1014(1)b1 Prepainted Metal Sheets Long Span, Corrugated Type, above 0.427 mm, Long Span 6.21 m2 3,840.54 618.44 779.24 0.05

1013(2)b1 Fabricated Metal Roofing Accessory, gauge 24, Gutters 2.50 m 907.16 362.86 457.21 0.01

1013(2)a1 Fabricated Metal Roofing Accessory, gauge 26, Ridge/Rolls - m - #DIV/0! #DIV/0! -

1013 (2) a2 Fabricated Metal Roofing Accessory, gauge 26, Flashings 8.10 m 2,082.30 257.07 323.91 0.03

1047 (2) a Structural Steel, Trusses - kg - #DIV/0! #DIV/0! -

1047 (2) b Structural Steel Purlins 32.20 kg 2,385.32 74.08 93.34 0.03

1003 (11) a1 Fascia Board - m - #DIV/0! #DIV/0! -

1047 (6) Metal Structure Accessories (Steel Plates) - kg - #DIV/0! #DIV/0! -

1047 (3) a Metal Structure Accessories, Bolts - pc - #DIV/0! #DIV/0! -

1047 (3)d Metal Structure Accessories (Cross bracing) - pc - #DIV/0! #DIV/0! -

1047 (3) c Metal Structure Accessories, Turnbuckle - pc - #DIV/0! #DIV/0! -

1047 (3) b Metal Structure Accessories, Sagrods - pc - #DIV/0! #DIV/0! -

1047 (10) Structural Steel 1.00 l.s. 85,515.96 85,515.96 107,750.11 1.06

Sub-Total C.6 94,731.28

TOTAL OF PART C 3,570,810.22

PART D PLUMBING/SANITARY WORKS

1001 (8) Sewer Line Works 1.00 l.s. 26,921.26 26,921.26 33,920.79 0.33

1002 (24) Cold Water Lines 1.00 l.s. 30,056.80 30,056.80 37,871.57 0.37

1001 (9) Storm Drainage and Downspout 1.00 l.s. 7,034.69 7,034.69 8,863.71 0.09

1002 (27) Plumbing Works - l.s. - #DIV/0! #DIV/0! -

1001 (11) Septic Vault (Concrete/CHB) 1.00 l.s. 63,833.68 63,833.68 80,430.44 0.79

1001 (5) b Catch Basin, CHB 5.00 ea 5,698.90 1,139.78 1,436.12 0.07

1002(4) Plumbing Fixtures 1.00 l.s. 83,121.12 83,121.12 104,732.61 1.03

1201 (8) Water Tank 1.00 l.s. 299,261.64 299,261.64 377,069.67 3.72

1002 (26) Cistern - l.s. - #DIV/0! #DIV/0! -

1201 (8) Water Tank - l.s. - #DIV/0! #DIV/0! -

TOTAL OF PART D 515,928.09

PART E ELECTRICAL

1100(10) Conduit, Boxes, and Fittings (Conduit Works/Conduit Rough-in) 1.00 l.s. 37,336.66 37,336.66 47,044.19 0.46

1101(33) Wires and Wiring Devices 1.00 l.s. 76,814.82 76,814.82 96,786.67 0.95

1102(1) Panelboard with Main and Branch Breakers 1.00 l.s. 20,964.08 20,964.08 26,414.75 0.26

1103(1) Lighting Fixtures 1.00 l.s. 93,316.16 93,316.16 117,578.36 1.16

1208(1) Fire Alarm System - l.s. - #DIV/0! #DIV/0! -

1726(1) Generator Set, Lump Sum - l.s. - #DIV/0! #DIV/0! -

1102(10) Pole Mounted Distribution Transformer with Complete Accessories - l.s. - #DIV/0! #DIV/0! -

TOTAL OF PART E 228,431.72

PART F MECHANICAL

1200(5) Exhaust Fan, Ceiling Cassette - set - #DIV/0! #DIV/0! -

1101(33) Wires and Wiring Devices - l.s. - #DIV/0! #DIV/0! -

1102(1) Panelboard with Main and Branch Breakers - l.s. - #DIV/0! #DIV/0! -

1200 (13) a Airconditioning (Package/Split type) 1.00 l.s. 796,035.20 796,035.20 1,019,721.09 9.90

1208(1) Fire Alarm System - l.s. - #DIV/0! #DIV/0! -

TOTAL OF PART F 796,035.20

TOTAL OF PART III 7,929,275.66

TOTAL OF (Project ID) 8,043,929.32

GRAND TOTAL 8,043,929.40 100.00


CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM

DIRECT COS DIRECT COST TOTAL MARK-UP


ITEM
DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
NO.
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE

PART
FACILITIES
I FOR THE ENGINEER

I.1.1 Offices and Laboratory for the Engineer

As Submitted - - mo 0.000 - 0.000 - 45,000.000 - #DIV/0! - 0% - - -


Provision of 4x2 Pick-up
Type Service Vehicle fir
A.1.2 (4)
the Engineer On Bare
Rental Basis
As Evaluated

As Submitted - - mo 23240.000 - 0.000 - 0.000 - #DIV/0! - 0% - - -


Operation and
Maintenance of 4x2 Pick-
A.1.2 (6)
up Type Service Vehicle
for the Engineer
As Evaluated

TOTAL OF PART I As Submitted - - - - - - - -

PART II OTHER GENERAL REQUIREMENTS

B.3 Permits and Clearances As Submitted 0.17 1.00 l.s. 2200.000 2,200.00 11,500.000 11,500.00 0.000 - 13,700.00 13,700.00 0% - 685.00 14,385.00

Project Billboard/ Sign


B.5 As Submitted 0.04 1.00 ea 2555.000 2,555.00 808.560 808.56 80.860 80.86 3,444.42 3,444.42 20% 688.88 206.67 4,339.97
Board

Occupational Safety and


B.7 (2) As Submitted 0.84 1.00 l.s. 50,503.08 50,503.08 17,006.160 17,006.16 0.000 - 67,509.24 67,509.24 8% 5,400.74 3,645.50 76,555.48
Health Program

Mobilization/
B.9 As Submitted 0.37 1.00 l.s. 0.000 - 0.000 - 30,000.000 30,000.00 30,000.00 30,000.00 0% - 1,500.00 31,500.00
Demobilization

Additional Geotechnical
B.13 As Submitted 0.00 - l.s. 6000.000 - 52,894.700 - 139,100.000 - #DIV/0! - 20% - - -
Investigation (2 holes)

TOTAL OF PART II As Submitted 1.43 55,258.08 29,314.72 30,080.86 114,653.66 6,089.62 6,037.17 126,780.45
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM

DIRECT COS DIRECT COST TOTAL MARK-UP


ITEM
DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
NO.
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE

CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING


PART III
WORKS

PART A EARTHWORKS

Removal of Structures
101(1) As Submitted 0.00 - l.s. 0.000 - 9,085.600 - 8,628.560 - #DIV/0! - 20% - - -
and Obstruction

800 (1) Clearing and Grubbing As Submitted 0.06 125.82 m2 13.400 1,685.99 20.967 2,638.03 2.097 263.80 36.46 4,587.82 20% 917.56 275.27 5,780.65

Surplus Common
802(2) As Evaluated 0.00 - m3 0.000 - 165.852 - 16.585 - #DIV/0! - 20% - - -
Excavation

Structure Excavation,
803 (1) a As Submitted 0.27 255.82 m3 - - 11.848 3,030.78 72.185 18,465.99 84.03 21,496.77 20% 4,299.35 1,289.81 27,085.93
Common Soil

Embankment from
804 (1) a Roadway/Structure As Submitted 0.05 105.14 m3 - - 24.080 2,531.81 11.784 1,238.92 35.86 3,770.73 20% 754.15 226.24 4,751.12
Excavation

Embankment from
804 (1) b As Submitted 0.20 25.10 m3 487.500 12,234.30 24.080 604.32 128.933 3,235.70 640.51 16,074.32 20% 3,214.86 964.46 20,253.64
Borrow

804 (4) Gravel Fill As Submitted 0.10 6.75 m3 945.000 6,375.46 197.458 1,332.16 71.000 479.00 1,213.46 8,186.62 20% 1,637.32 491.20 10,315.14

Overhaul, Cubic Meter-


1706(1) As Evaluated 0.00 - km 8984.736 - 0.000 - 0.000 - #DIV/0! - 20% - - -
Kilometer

TOTAL OF PART A As Submitted 0.67 20,295.75 10,137.10 23,683.41 54,116.26 10,823.24 3,246.98 68,186.48
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM

DIRECT COS DIRECT COST TOTAL MARK-UP


ITEM
DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
NO.
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE

PART B PLAIN AND REINFORCED CONCRETE WORKS

Structural Concrete
900(1)c2 (Footings and Slab on As Submitted 2.90 45.00 m3 3616.000 162,715.77 981.849 44,182.04 579.972 26,098.06 5,177.82 232,995.87 20% 46,599.17 13,979.75 293,574.79
Fill), A, 28 days
Structural Concrete
(Footing Tie Beams), 28
900(1)c3 As Submitted 0.84 11.94 m3 3616.000 43,175.04 1,298.222 15,500.77 766.852 9,156.21 5,681.07 67,832.02 20% 13,566.40 4,069.92 85,468.34
days, A

Structural Concrete
900(1)c4 (Column), A, 28 days As Submitted 2.42 34.27 m3 3616.000 123,908.99 1,298.222 44,486.01 766.852 26,277.61 5,681.07 194,672.61 20% 38,934.52 11,680.36 245,287.49

Structural Concrete
900(1)c5 (Suspended Slab), A, 28 As Submitted 2.23 31.61 m3 3616.000 114,315.45 1,298.222 41,041.72 766.852 24,243.09 5,681.07 179,600.26 20% 35,920.05 10,776.02 226,296.33
days
Structural Concrete
(Beams/Girders), A, 28
900(1)c6 As Submitted 1.66 23.49 m3 3616.000 84,944.25 1,298.222 30,496.82 766.852 18,014.29 5,681.07 133,455.36 20% 26,691.07 8,007.32 168,153.75
days

400 (37) a Micro piles, 0.20 m As Submitted - - l.m 1401.690 - 258.947 - 2,320.010 - #DIV/0! - 22% - - -

Reinforcing Steel
902 (1) a As Submitted 21.81 21,625.19 kg 72.430 1,566,312.52 6.096 131,830.47 2.601 56,245.27 81.13 1,754,388.26 20% 350,877.65 105,263.30 2,210,529.21
(Deformed), Grade 40

Formworks and
903 (2) As Submitted 2.50 492.69 m2 213.580 105,228.73 176.731 87,073.83 17.673 8,707.23 407.98 201,009.79 20% 40,201.96 12,060.59 253,272.34
Falseworks

400(37)a Micro Piles As Submitted - - m 1609.760 - 260.023 - 2,345.979 - #DIV/0! - 22% - - -

TOTAL OF PART B As Submitted 34.36 2,200,600.75 394,611.66 168,741.76 2,763,954.17 552,790.83 165,837.26 3,482,582.25

PART C FINISHING

C.1 Termite Control Works

1000 (1) Soil Poisoning As Submitted - - L 320.000 - 46.593 - 4.659 - #DIV/0! - 20% - - -

Sub - Total C.1 As Submitted - - - - - - - -


CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM

DIRECT COS DIRECT COST TOTAL MARK-UP


ITEM
DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
NO.
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE

C.2. Masonry Works

CHB Non-Load Bearing


1046 (2)
(including Reinforcing As Submitted 0.82 97.92 m2 523.070 51,219.01 95.469 9,348.35 54.515 5,338.11 673.05 65,905.47 20% 13,181.09 3,954.33 83,040.89
a1
Steel), 100mm

CHB Non-Load Bearing


1046 (2)
(including Reinforcing As Submitted 5.91 464.86 m2 841.570 391,212.23 114.833 53,381.42 65.572 30,481.95 1,021.98 475,075.60 20% 95,015.12 28,504.54 598,595.26
a2
Steel), 150mm

Sub - Total C.2 As Submitted 6.73 442,431.24 62,729.77 35,820.06 540,981.07 108,196.21 32,458.87 681,636.15

C.3 Fabricated Materials

Wooden Doors and


1010 (4) As Submitted 0.72 1.00 l.s. 54137.160 54,137.16 3,234.240 3,234.24 323.420 323.42 57,694.82 57,694.82 20% 11,538.96 3,461.69 72,695.47
Windows

1006 (6) Steel Doors and Frames As Submitted - l.s. 138641.250 - 23,127.650 - 2,312.770 - #DIV/0! - 20% - - -

Aluminum Framed Glass


1007 As Submitted 3.56 37.96 m2 6695.000 254,142.20 777.462 29,512.44 77.731 2,950.66 7,550.19 286,605.30 20% 57,321.06 17,196.32 361,122.68
Door

Aluminum Glass Window


1008 (Sliding/Casement/Awnin As Submitted 3.28 41.94 m2 5665.000 237,590.10 561.500 23,549.31 56.139 2,354.47 6,282.64 263,493.88 20% 52,698.78 15,809.63 332,002.29
g/Fixed Type)

Aluminum Glass Window


1008(1) As Submitted - - m2 6695.000 - 777.462 - 77.731 - #DIV/0! - 20% - - -
(Sliding Type)

Aluminum Glass Window


1008(1)b As Submitted - - m2 7350.000 - 472.519 - 47.259 - #DIV/0! - 20% - - -
(Casement Type)

1004 (2) Finishing Hardware As Submitted 0.20 1.00 l.s. 15705.000 15,705.00 0.000 - 0.000 - 15,705.00 15,705.00 20% 3,141.00 942.30 19,788.30

Carpentry and Joinery


1003 (17) As Submitted - - l.s. 22060.500 - 9,702.720 - 970.270 - #DIV/0! - 20% - - -
Works

Fence, Cyclone/Welded
1722(1)c As Submitted - - l.s. 95550.000 - 8,051.200 - 805.120 - #DIV/0! - 22% - - -
Wire, Square Meter

1003 (4) Cabinets, Each As Submitted - - ea 9250.000 - 0.000 - 0.000 - #DIV/0! - 8% - - -

1038(1) Reflective Insulation As Submitted - - m2 141.750 - 45.252 - 4.525 - #DIV/0! - 20% - - -

Sub-Total C.3 As Submitted 7.75 561,574.46 56,295.99 5,628.55 623,499.00 124,699.80 37,409.94 785,608.74
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM

DIRECT COS DIRECT COST TOTAL MARK-UP


ITEM
DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
NO.
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE

C.4 Finishing Works

As Submitted 0.40 112.45 m2 232.720 26,169.36 50.338 5,660.49 5.034 566.03 288.09 32,395.88 20% 6,479.18 1,943.75 40,818.81
Cement Floor Finish, with
1021 (1) c
Floor Hardener
As Evaluated

As Submitted 2.37 1,125.56 m2 105.680 118,949.18 58.194 65,500.48 5.819 6,549.57 169.69 190,999.23 20% 38,199.85 11,459.95 240,659.03
1027 (1) Cement Plaster Finish
As Evaluated

As Submitted 0.34 1.00 l.s. 0.000 - 12,628.400 12,628.40 14,356.340 14,356.34 26,984.74 26,984.74 20% 5,396.95 1,619.08 34,000.77
1051 (6) Railing
As Evaluated

Ceiling, Fiber Cement As Submitted 3.11 295.64 m2 624.630 184,665.61 202.414 59,841.53 20.241 5,984.15 847.28 250,491.29 20% 50,098.26 15,029.48 315,619.03
1003 (1)
Board, 4.5mm, Metal
a1
Frame As Evaluated

As Submitted 14.58 456.09 m2 2257.500 1,029,616.40 286.069 130,472.16 28.606 13,046.69 2,572.17 1,173,135.25 20% 234,627.05 70,388.12 1,478,150.42
1039(1) Aluminum Cladding
As Evaluated

As Submitted 0.24 115.34 m2 47.250 5,449.82 107.808 12,434.57 10.779 1,243.21 165.84 19,127.60 20% 3,825.52 1,147.66 24,100.78
Waterproofing ,Cement-
1016 (1)a
Base
As Evaluated

As Submitted 4.21 217.66 m2 1027.990 223,752.30 480.894 104,671.34 48.088 10,466.81 1,556.97 338,890.45 20% 67,778.09 20,333.43 427,001.97
1018 (1) Glazed Tiles and Trims
As Evaluated

As Submitted 1.82 102.64 m2 1058.580 108,652.65 336.626 34,551.26 33.662 3,455.02 1,428.87 146,658.93 20% 29,331.79 8,799.54 184,790.26
1018 (2) Unglazed Tiles
As Evaluated

Ceiling, Fiber Cement As Submitted - - m2 624.630 - 202.414 - 20.241 - #DIV/0! - 20% - - -


1003 (1)
Board, 4.5mm, Metal
a1
Frame As Evaluated

Sub-Total C.4 As Submitted 27.08 1,697,255.32 425,760.23 55,667.82 2,178,683.37 435,736.69 130,721.01 2,745,141.07
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM

DIRECT COS DIRECT COST TOTAL MARK-UP


ITEM
DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
NO.
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE

C.5 Painting Works


Painting Works,
1032 (1) a As Submitted 1.65 562.78 m2 96.710 54,426.45 126.786 71,352.46 12.681 7,136.59 236.18 132,915.50 20% 26,583.10 7,974.93 167,473.53
Masonry/Concrete

1032 (1) b Painting Works, Wood As Submitted - - m2 79.726 - 140.873 - 14.087 - #DIV/0! - 20% - - -

1032 (1) c Painting Works, Steel As Submitted - - m 2


137.025 - 133.125 - 13.313 - #DIV/0! - 20% - - -

411(2) Paint As Evaluated - - m2 230.270 - 26.083 - 2.608 - #DIV/0! - 20% - - -

Sub-Total C.5 As Submitted 1.65 54,426.45 71,352.46 7,136.59 132,915.50 26,583.10 7,974.93 167,473.53

C.6 Roof Framing and Roofing Works


Prepainted Metal Sheets
1014 (1) Long Span, Rib Type,
As Submitted - - m2 463.500 - 90.863 - 9.086 - #DIV/0! - 20% - - -
b2 above 0.427 mm, Long
Span
Prepainted Metal Sheets
Long Span, Corrugated
1014(1)b1 As Submitted 0.05 6.21 m2 485.130 3,012.66 121.195 752.62 12.119 75.26 618.44 3,840.54 20% 768.11 230.43 4,839.08
Type, above 0.427 mm,
Long Span
Fabricated Metal Roofing
1013(2)b1 Accessory, gauge 24, As Submitted 0.01 2.50 m 344.020 860.05 17.131 42.83 1.713 4.28 362.86 907.16 20% 181.43 54.43 1,143.02
Gutters

Fabricated Metal Roofing


1013(2)a1 Accessory, gauge 26, As Submitted - - m 234.840 - 11.357 - 1.136 - #DIV/0! - 20% - - -
Ridge/Rolls

Fabricated Metal Roofing


1013 (2)
Accessory, gauge 26, As Submitted 0.03 8.10 m 234.840 1,902.20 20.214 163.73 2.021 16.37 257.07 2,082.30 20% 416.46 124.94 2,623.70
a2
Flashings

1047 (2) a Structural Steel, Trusses As Submitted - - kg 84.120 - 5.678 - 4.152 - #DIV/0! - 20% - - -

1047 (2) b Structural Steel Purlins As Submitted 0.03 32.20 kg 60.390 1,944.56 4.584 147.61 9.104 293.15 74.08 2,385.32 20% 477.06 143.12 3,005.50

1003 (11)
Fascia Board As Submitted - - m 190.050 - 21.208 - 2.122 - #DIV/0! - 20% - - -
a1

Metal Structure
1047 (6) As Submitted - - kg 83.280 - 15.555 - 1.555 - #DIV/0! - 20% - - -
Accessories (Steel Plates)

Metal Structure
1047 (3) a As Submitted - - pc 250.000 - 20.220 - 2.020 - #DIV/0! - 20% - - -
Accessories, Bolts

Metal Structure
1047 (3)d Accessories (Cross As Submitted - - pc 741.600 - 4.869 - 0.486 - #DIV/0! - 20% - - -
bracing)

Metal Structure
1047 (3) c As Submitted - - pc 185.000 - 30.330 - 3.033 - #DIV/0! - 20% - - -
Accessories, Turnbuckle

Metal Structure
1047 (3) b As Submitted - - pc 208.348 - 20.220 - 2.022 - #DIV/0! - 20% - - -
Accessories, Sagrods

1047 (10) Structural Steel As Submitted 1.06 1.00 l.s. 65888.629 65,888.63 6,468.480 6,468.48 13,158.850 13,158.85 85,515.96 85,515.96 20% 17,103.19 5,130.96 107,750.11

Sub-Total C.6 As Submitted 1.18 73,608.10 7,575.27 13,547.91 94,731.28 18,946.25 5,683.88 119,361.41

TOTAL OF PART C As Submitted 44.39 2,829,295.57 623,713.72 117,800.93 3,570,810.22 714,162.05 214,248.63 4,499,220.90
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM

DIRECT COS DIRECT COST TOTAL MARK-UP


ITEM
DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
NO.
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE

PART D PLUMBING/SANITARY WORKS

1001 (8) Sewer Line Works As Submitted 0.33 1.00 l.s. 22493.100 22,493.10 4,025.600 4,025.60 402.560 402.56 26,921.26 26,921.26 20% 5,384.25 1,615.28 33,920.79

1002 (24) Cold Water Lines As Submitted 0.37 1.00 l.s. 25628.640 25,628.64 4,025.600 4,025.60 402.560 402.56 30,056.80 30,056.80 20% 6,011.36 1,803.41 37,871.57

Storm Drainage and


1001 (9) As Submitted 0.09 1.00 l.s. 5927.650 5,927.65 1,006.400 1,006.40 100.640 100.64 7,034.69 7,034.69 20% 1,406.94 422.08 8,863.71
Downspout

1002 (27) Plumbing Works As Submitted - - l.s. 11616.000 - 2,130.000 - 213.000 - #DIV/0! - 20% - - -

Septic Vault
1001 (11) As Submitted 0.79 1.00 l.s. 52887.450 52,887.45 9,951.120 9,951.12 995.110 995.11 63,833.68 63,833.68 20% 12,766.74 3,830.02 80,430.44
(Concrete/CHB)

1001 (5) b Catch Basin, CHB As Submitted 0.07 5.00 ea 879.130 4,395.65 236.950 1,184.75 23.700 118.50 1,139.78 5,698.90 20% 1,139.78 341.93 7,180.61

1002(4) Plumbing Fixtures As Submitted 1.03 1.00 l.s. 81732.000 81,732.00 1,262.840 1,262.84 126.280 126.28 83,121.12 83,121.12 20% 16,624.22 4,987.27 104,732.61

1201 (8) Water Tank As Submitted 3.72 1.00 l.s. 281563.960 281,563.96 16,088.800 16,088.80 1,608.880 1,608.88 299,261.64 299,261.64 20% 59,852.33 17,955.70 377,069.67

1002 (26) Cistern As Submitted - - l.s. 0.000 - 25,128.000 - 32,290.800 - #DIV/0! - 20% - - -

Water Pumping System,


1201 (1) As Submitted - - l.s. 83716.000 - 10,064.000 - 1,006.400 - #DIV/0! - 20% - - -
Lumpsum

TOTAL OF PART D As Submitted 6.41 474,628.45 37,545.11 3,754.53 515,928.09 103,185.62 30,955.69 650,069.40

PART E ELECTRICAL

Conduit, Boxes, and


1100(10) Fittings (Conduit As Submitted 0.46 1.00 l.s. 23106.000 23,106.00 12,936.960 12,936.96 1,293.700 1,293.70 37,336.66 37,336.66 20% 7,467.33 2,240.20 47,044.19
Works/Conduit Rough-in)

1101(33) Wires and Wiring Devices As Submitted 0.95 1.00 l.s. 64363.000 64,363.00 11,319.840 11,319.84 1,131.980 1,131.98 76,814.82 76,814.82 20% 15,362.96 4,608.89 96,786.67

Panelboard with Main


1102(1) As Submitted 0.26 1.00 l.s. 18750.000 18,750.00 2,012.800 2,012.80 201.280 201.28 20,964.08 20,964.08 20% 4,192.82 1,257.85 26,414.75
and Branch Breakers

1103(1) Lighting Fixtures As Submitted 1.16 1.00 l.s. 88888.000 88,888.00 4,025.600 4,025.60 402.560 402.56 93,316.16 93,316.16 20% 18,663.23 5,598.97 117,578.36

1208(1) Fire Alarm System As Submitted - - l.s. 19180.000 - 1,817.120 - 181.712 - #DIV/0! - 22% - - -

Generator Set, Lump


1726(1) As Submitted - - l.s. 1395000.000 - 6,038.400 - 603.840 - #DIV/0! - 22% - - -
Sum

Pole Mounted
Distribution Transformer
1102(10) As Evaluated - - l.s. 262880.000 - 6,038.400 - 603.840 - #DIV/0! - 20% - - -
with Complete
Accesorries

TOTAL OF PART E As Submitted 2.84 195,107.00 30,295.20 3,029.52 228,431.72 45,686.34 13,705.91 287,823.97
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM

DIRECT COS DIRECT COST TOTAL MARK-UP


ITEM
DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
NO.
UNIT MATERIAL UNIT LABOR UNIT EQUIPMENT UNIT COST TOTAL % VALUE

PART F MECHANICAL

Exhaust Fan, Ceiling


1200(5) As Submitted - - set 2874.730 - 315.710 - 31.571 - #DIV/0! - 22% - - -
Cassette

1101(33) Wires and Wiring Devices As Submitted - - l.s. 64363.000 - 11,319.840 - 1,131.980 - #DIV/0! - 22% - - -

Panelboard with Main


1102(1) As Submitted - - l.s. 7250.000 - 2,012.800 - 201.280 - #DIV/0! - 22% - - -
and Branch Breakers

1200 (13) Airconditioning


As Submitted 9.90 1.00 l.s. 796035.200 796,035.20 0.000 - 0.000 - 796,035.20 796,035.20 22% 175,127.74 48,558.15 1,019,721.09
a (Package/Split type)

1208(1) Fire Alarm System As Submitted - - l.s. 39660.000 - 5,423.520 - 542.350 - #DIV/0! - 20% - - -

TOTAL OF PART F As Submitted 9.90 796,035.20 - - 796,035.20 175,127.74 48,558.15 1,019,721.09

TOTAL OF PART III As Submitted 98.57 5,719,927.52 1,096,302.79 317,010.15 7,929,275.66 1,601,775.81 476,552.62 10,007,604.090

TOTAL OF (Project
As Submitted 5,775,185.60 1,125,617.51 347,091.01 8,043,929.32 1,607,865.43 482,589.79 10,134,384.54
ID)

GRAND TOTAL As Submitted 100 5,775,185.60 1,125,617.51 347,091.01 8,043,929.400 1,607,865.431 482,589.790 10,134,384.54
Republic of the Philippines
Department of Public Works and Highways
Region IV-B, MIMAROPA
OFFICE OF THE DISTRICT ENGINEER
Masipit, Calapan City, Oriental Mindoro

CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

FORM ABC-2015-02-00

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 270 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
AS SUBMITTED - 8.00% - - - -
PART I FACILITIES FOR THE ENGINEER
AS EVALUATED

AS SUBMITTED 114,653.66 5.31% 6,089.62 6,037.17 12,126.79 126,780.45


PART II OTHER GENERAL REQUIREMENTS
AS EVALUATED

(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
AS SUBMITTED 54,116.26 20.00% 10,823.24 3,246.98 14,070.22 68,186.48
PART A EARTHWORKS
AS EVALUATED

AS SUBMITTED 2,763,954.17 20.00% 552,790.83 165,837.26 718,628.09 3,482,582.26


PART B PLAIN AND REINFORCED CONCRETE WORKS
AS EVALUATED

AS SUBMITTED 2,397,674.97 20.00% 479,535.00 143,860.51 623,395.51 3,021,070.48


PART C FINISHING
AS EVALUATED

AS SUBMITTED 515,928.09 20.00% 103,185.62 30,955.69 134,141.31 650,069.40


PART D PLUMBING/SANITARY WORKS
AS EVALUATED

AS SUBMITTED 228,431.72 20.00% 45,686.34 13,705.91 59,392.25 287,823.97


PART E ELECTRICAL
AS EVALUATED

AS SUBMITTED 796,035.20 22.00% 175,127.74 48,558.15 223,685.89 1,019,721.09


PART F MECHANICAL
AS EVALUATED

AS SUBMITTED 6,756,140.41 1,192,021.03 406,164.50 1,598,185.53 8,354,325.94


TOTAL OF PART III
AS EVALUATED

AS SUBMITTED 8,043,929.32 20.00% 1,607,865.43 482,589.79 2,090,455.22 10,134,384.54


TOTAL OF (Project ID)
AS EVALUATED

AS SUBMITTED 6,870,794.07 1,198,110.65 412,201.67 1,610,312.32 7,636,513.04


TOTAL
AS EVALUATED

Prepared and Submitted by : Checked and Reviewed by the Estimating Committee : Approved By:

RAMIR G. BASA RAMIR G. BASA ROMEO A. VILLANUEVA DUANE ANDREW ORIEL C. ANORICO ERWIN DG. UMALI
Engineer II Engineer II( Member) Architect II ( Member) Engineer II ( Chairman ) OIC - OFFICE OF THE DISTRICT ENGINEER
Republic of the Philippines
Department of Public Works and Highways
Region IV-B, MIMAROPA
OFFICE OF THE DISTRICT ENGINEER
Masipit, Calapan City, Oriental Mindoro FORM ABC-2015-02A-00
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 270 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION QUANTITY UNIT ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST UNIT COST
% VALUE
PART I FACILITIES FOR THE ENGINEER
Provision of 4x2 Pick-up Type Service Vehicle fir the Engineer AS SUBMITTED - mo - 0% - - - - #DIV/0!
A.1.2 (4)
On Bare Rental Basis AS EVALUATED
AS SUBMITTED - - - - -
TOTAL OF PART I
AS EVALUATED

PART II OTHER GENERAL REQUIREMENTS


AS SUBMITTED 1.00 l.s. 13,700.00 0% - 685.00 685.00 14,385.00 14,385.00
B.3 Permits and Clearances
AS EVALUATED

AS SUBMITTED 1.00 ea 3,444.42 20% 688.88 206.67 895.55 4,339.97 4,339.97


B.5 Project Billboard/ Sign Board
AS EVALUATED

AS SUBMITTED 1.00 l.s. 67,509.24 8% 5,400.74 3,645.50 9,046.24 76,555.48 76,555.48


B.7 (2) Occupational Safety and Health Program
AS EVALUATED

AS SUBMITTED 1.00 l.s. 30,000.00 0% - 1,500.00 1,500.00 31,500.00 31,500.00


B.9 Mobilization/Demobilization
AS EVALUATED

AS SUBMITTED - l.s. - 20% - - - - #DIV/0!


B.13 Additional Geotechnical Investigation (2 holes)
AS EVALUATED

AS SUBMITTED 114,653.66 6,089.62 6,037.17 12,126.79 126,780.45


TOTAL OF PART II
AS EVALUATED

(Project ID)
(Project Component ID - Description)

CIVIL, MECHANICAL, ELECTRICAL AND


PART III
SANITARY/PLUMBING WORKS

PART A EARTHWORKS
AS SUBMITTED - l.s. - 20% - - - - #DIV/0!
101(1) Removal of Structures and Obstruction
AS EVALUATED

AS SUBMITTED 125.82 m2 4,587.82 20% 917.56 275.27 1,192.83 5,780.65 45.94


800 (1) Clearing and Grubbing
AS EVALUATED

AS EVALUATED - m3 - 20% - - - - #DIV/0!


802(2) Surplus Common Excavation
AS EVALUATED

AS SUBMITTED 255.82 m3 21,496.77 20% 4,299.35 1,289.81 5,589.16 27,085.93 105.88


803 (1) a Structure Excavation, Common Soil
AS EVALUATED

AS SUBMITTED 105.14 m3 3,770.73 20% 754.15 226.24 980.39 4,751.12 45.19


804 (1) a Embankment from Roadway/Structure Excavation
AS EVALUATED

AS SUBMITTED 25.10 m3 16,074.32 20% 3,214.86 964.46 4,179.32 20,253.64 807.05


804 (1) b Embankment from Borrow
AS EVALUATED

AS SUBMITTED 6.75 m3 8,186.62 20% 1,637.32 491.20 2,128.52 10,315.14 1,528.96


804 (4) Gravel Fill
AS EVALUATED

AS EVALUATED - km - 20% - - - -
1706(1) Overhaul, Cubic Meter-Kilometer
AS EVALUATED

AS SUBMITTED 54,116.26 10,823.24 3,246.98 14,070.22 68,186.48


TOTAL OF PART A
AS EVALUATED

Prepared and Submitted by : Checked and Reviewed by the Estimating Committee : Approved By:

RAMIR G. BASA RAMIR G. BASA DUANE ANDREW ORIEL C. ANORICO ERROL R. VILLAN ERWIN DG. UMALI
Engineer II Engineer II( Member) Engineer II ( Member) Engineer II ( Chairman ) OIC - OFFICE OF THE DISTRICT ENGINEER
Republic of the Philippines
Department of Public Works and Highways
Region IV-B, MIMAROPA
OFFICE OF THE DISTRICT ENGINEER
Masipit, Calapan City, Oriental Mindoro FORM ABC-2015-02A-00
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 270 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION QUANTITY UNIT ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST UNIT COST
% VALUE
PART B PLAIN AND REINFORCED CONCRETE WORKS
AS SUBMITTED 45.00 m3 232,995.87 20% 46,599.17 13,979.75 60,578.92 293,574.79 6,524.05
900(1)c2 Structural Concrete (Footings and Slab on Fill), A, 28 days
AS EVALUATED

Structural Concrete (Footing Tie Beams), 28 days, A AS SUBMITTED 11.94 m3 67,832.02 20% 13,566.40 4,069.92 17,636.32 85,468.34 7,158.15
900(1)c3
AS EVALUATED

Structural Concrete (Column), A, 28 days AS SUBMITTED 34.27 m3 194,672.61 20% 38,934.52 11,680.36 50,614.88 245,287.49 7,158.15
900(1)c4
AS EVALUATED

AS SUBMITTED 31.61 m3 179,600.26 20% 35,920.05 10,776.02 46,696.07 226,296.33 7,158.15


900(1)c5 Structural Concrete (Suspended Slab), A, 28 days
AS EVALUATED

Structural Concrete (Beams/Girders), A, 28 days AS SUBMITTED 23.49 m3 133,455.36 20% 26,691.07 8,007.32 34,698.39 168,153.75 7,158.15
900(1)c6
AS EVALUATED

AS SUBMITTED - l.m - 22% - - - - #DIV/0!


400 (37) a Micro piles, 0.20 m
AS EVALUATED

AS SUBMITTED 21,625.19 kg 1,754,388.26 20% 350,877.65 105,263.30 456,140.95 2,210,529.21 102.22


902 (1) a Reinforcing Steel (Deformed), Grade 40
AS EVALUATED

AS SUBMITTED 492.69 m2 201,009.79 20% 40,201.96 12,060.59 52,262.55 253,272.34 514.06


903 (2) Formworks and Falseworks
AS EVALUATED

AS SUBMITTED - m - 22% - - - - #DIV/0!


400(37)a Micro Piles
AS EVALUATED
AS SUBMITTED 2,763,954.17 552,790.83 165,837.26 718,628.09 3,482,582.26
TOTAL OF PART B
AS EVALUATED

PART C FINISHING WORKS

AS SUBMITTED - L - 20% - - - - #DIV/0!


1000 (1) Soil Poisoning
AS EVALUATED

AS SUBMITTED 97.92 m2 65,905.47 20% 13,181.09 3,954.33 17,135.42 83,040.89 848.05


1046 (2) a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
AS EVALUATED

AS SUBMITTED 464.86 m2 475,075.60 20% 95,015.12 28,504.54 123,519.66 598,595.26 1,287.69


1046 (2) a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
AS EVALUATED
AS SUBMITTED 1.00 l.s. 57,694.82 20% 11,538.96 3,461.69 15,000.65 72,695.47 72,695.47
1010 (4) Wooden Doors and Windows
AS EVALUATED

AS SUBMITTED - l.s. - 20% - - - - #DIV/0!


1006 (6) Steel Doors and Frames
AS EVALUATED

Prepared and Submitted by : Checked and Reviewed by the Estimating Committee : Approved By:

RAMIR G. BASA RAMIR G. BASA DUANE ANDREW ORIEL C. ANORICO ERROL R. VILLAN ERWIN DG. UMALI
Engineer II Engineer II( Member) Engineer II ( Member) Engineer II ( Chairman ) OIC - OFFICE OF THE DISTRICT ENGINEER
Republic of the Philippines
Department of Public Works and Highways
Region IV-B, MIMAROPA
OFFICE OF THE DISTRICT ENGINEER
Masipit, Calapan City, Oriental Mindoro FORM ABC-2015-02A-00
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 270 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION QUANTITY UNIT ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST UNIT COST
% VALUE
AS SUBMITTED 37.96 m2 286,605.30 20% 57,321.06 17,196.32 74,517.38 361,122.68 9,513.24
1007 Aluminum Framed Glass Door
AS EVALUATED

Aluminum Glass Window (Sliding/Casement/Awning/Fixed AS SUBMITTED 41.94 m2 263,493.88 20% 52,698.78 15,809.63 68,508.41 332,002.29 7,916.13
1008
Type) AS EVALUATED

AS SUBMITTED - m2 - 20% - - - - #DIV/0!


1008(1) Aluminum Glass Window (Sliding Type)
AS EVALUATED

AS SUBMITTED - m2 - 20% - - - - #DIV/0!


1008(1)b Aluminum Glass Window (Casement Type)
AS EVALUATED

AS SUBMITTED 1.00 l.s. 15,705.00 20% 3,141.00 942.30 4,083.30 19,788.30 19,788.30
1004 (2) Finishing Hardware
AS EVALUATED

AS SUBMITTED - l.s. - 20% - - - - #DIV/0!


1003 (17) Carpentry and Joinery Works
AS EVALUATED

AS SUBMITTED - l.s. - 22% - - - - #DIV/0!


1722(1)c Fence, Cyclone/Welded Wire, Square Meter
AS EVALUATED

AS SUBMITTED - ea - 8% - - - - #DIV/0!
1003 (4) Cabinets, Each
AS EVALUATED

AS SUBMITTED 112.45 m2 32,395.88 20% 6,479.18 1,943.75 8,422.93 40,818.81 363.00


1021(1)c Cement Floor Finish, with Floor Hardener
AS EVALUATED

AS SUBMITTED 1,125.56 m2 190,999.23 20% 38,199.85 11,459.95 49,659.80 240,659.03 213.81


1027 (1) Cement Plaster Finish
AS EVALUATED

AS SUBMITTED 1.00 l.s. 26,984.74 20% 5,396.95 1,619.08 7,016.03 34,000.77 34,000.77
1051 (6) Railing
AS EVALUATED

AS SUBMITTED 295.64 m2 250,491.29 20% 50,098.26 15,029.48 65,127.74 315,619.03 1,067.58


1003 (1) a1 Ceiling, Fiber Cement Board, 4.5mm, Metal Frame
AS EVALUATED

AS SUBMITTED 217.66 m2 338,890.45 20% 67,778.09 20,333.43 88,111.52 427,001.97 1,961.78


1018 (1) Glazed Tiles and Trims
AS EVALUATED

AS SUBMITTED 102.64 m2 146,658.93 20% 29,331.79 8,799.54 38,131.33 184,790.26 1,800.37


1018 (2) Unglazed Tiles
AS EVALUATED

AS SUBMITTED 456.09 m2 1,173,135.25 20% 234,627.05 70,388.12 305,015.17 1,478,150.42 3,240.94


1039(1) Aluminum Cladding
AS EVALUATED

AS SUBMITTED 115.34 m2 19,127.60 20% 3,825.52 1,147.66 4,973.18 24,100.78 208.95


1016 (1)a Waterproofing ,Cement-Base
AS EVALUATED

AS SUBMITTED 562.78 m2 132,915.50 20% 26,583.10 7,974.93 34,558.03 167,473.53 297.58


1032 (1) a Painting Works, Masonry/Concrete
AS EVALUATED

AS SUBMITTED - m2 - 20% - - - - #DIV/0!


1032 (1) b Painting Works, Wood
AS EVALUATED

AS SUBMITTED - m2 - 20% - - - - #DIV/0!


1032 (1) c Painting Works, Steel
AS EVALUATED

AS EVALUATED - m2 - 20% - - - - #DIV/0!


411(2) Paint
AS EVALUATED

Prepainted Metal Sheets Long Span, Rib Type, above 0.427 AS SUBMITTED - m2 - 20% - - - - #DIV/0!
1014 (1) b2
mm, Long Span AS EVALUATED

Prepared and Submitted by : Checked and Reviewed by the Estimating Committee : Approved By:

RAMIR G. BASA RAMIR G. BASA ROMEO A. VILLANUEVA DUANE ANDREW ORIEL C. ANORICO ERWIN DG. UMALI
Engineer II Engineer II( Member) Architect II ( Member) Engineer II ( Chairman ) OIC-OFFICE OF THE DISTRICT ENGINEER
Republic of the Philippines
Department of Public Works and Highways
Region IV-B, MIMAROPA
OFFICE OF THE DISTRICT ENGINEER
Masipit, Calapan City, Oriental Mindoro FORM ABC-2015-02A-00
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 270 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION QUANTITY UNIT ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST UNIT COST
% VALUE

Prepainted Metal Sheets Long Span, Corrugated Type, above AS SUBMITTED 6.21 m2 3,840.54 20% 768.11 230.43 998.54 4,839.08 779.24
1014(1)b1
0.427 mm, Long Span AS EVALUATED

AS SUBMITTED 2.50 m 907.16 20% 181.43 54.43 235.86 1,143.02 457.21


1013(2)b1 Fabricated Metal Roofing Accessory, gauge 24, Gutters
AS EVALUATED

AS SUBMITTED - m - 20% - - - - #DIV/0!


1013(2)a1 Fabricated Metal Roofing Accessory, gauge 26, Ridge/Rolls
AS EVALUATED

Prepared and Submitted by : Checked and Reviewed by the Estimating Committee : Approved By:

RAMIR G. BASA RAMIR G. BASA DUANE ANDREW ORIEL C. ANORICO ERROL R. VILLAN ERWIN DG. UMALI
Engineer II Engineer II( Member) Engineer II ( Member) Engineer II ( Chairman ) OIC - OFFICE OF THE DISTRICT ENGINEER
AS SUBMITTED 8.10 m 2,082.30 20% 416.46 124.94 541.40 2,623.70 323.91
1013 (2) a2 Fabricated Metal Roofing Accessory, gauge 26, Flashings
AS EVALUATED

AS SUBMITTED - kg - 20% - - - - #DIV/0!


1047 (2) a Structural Steel, Trusses
AS EVALUATED

AS SUBMITTED 32.20 kg 2,385.32 20% 477.06 143.12 620.18 3,005.50 93.34


1047 (2) b Structural Steel Purlins
AS EVALUATED

AS SUBMITTED - m - 20% - - - - #DIV/0!


1003 (11) a1 Fascia Board
AS EVALUATED

AS SUBMITTED - kg - 20% - - - - #DIV/0!


1047 (6) Metal Structure Accessories (Steel Plates)
AS EVALUATED

AS SUBMITTED - pc - 20% - - - - #DIV/0!


1047 (3) a Metal Structure Accessories, Bolts
AS EVALUATED

AS SUBMITTED - pc - 20% - - - - #DIV/0!


1047 (3)d Metal Structure Accessories (Cross bracing)
AS EVALUATED

AS SUBMITTED - pc - 20% - - - - #DIV/0!


1047 (3) c Metal Structure Accessories, Turnbuckle
AS EVALUATED

AS SUBMITTED - pc - 20% - - - - #DIV/0!


1047 (3) b Metal Structure Accessories, Sagrods
AS EVALUATED

AS SUBMITTED 1.00 l.s. 85,515.96 20% 17,103.19 5,130.96 22,234.15 107,750.11 107,750.11
1047 (10) Structural Steel
AS EVALUATED

AS SUBMITTED 2,397,674.97 479,535.00 143,860.51 623,395.51 3,021,070.48


TOTAL OF PART C
AS EVALUATED

PART D PLUMBING/SANITARY WORKS


AS SUBMITTED 1.00 l.s. 26,921.26 20% 5,384.25 1,615.28 6,999.53 33,920.79 33,920.79
1001 (8) Sewer Line Works
AS EVALUATED
AS SUBMITTED 1.00 l.s. 30,056.80 20% 6,011.36 1,803.41 7,814.77 37,871.57 37,871.57
1002 (24) Cold Water Lines
AS EVALUATED
AS SUBMITTED 1.00 l.s. 7,034.69 20% 1,406.94 422.08 1,829.02 8,863.71 8,863.71
1001 (9) Storm Drainage and Downspout
AS EVALUATED

AS SUBMITTED - l.s. - 20% - - - - #DIV/0!


1002 (27) Plumbing Works
AS EVALUATED

AS SUBMITTED 1.00 l.s. 63,833.68 20% 12,766.74 3,830.02 16,596.76 80,430.44 80,430.44
1001 (11) Septic Vault (Concrete/CHB)
AS EVALUATED

Prepared and Submitted by : Checked and Reviewed by the Estimating Committee : Approved By:

RAMIR G. BASA RAMIR G. BASA DUANE ANDREW ORIEL C. ANORICO ERROL R. VILLAN NESTOR L. DEL ROSARIO
Engineer II Engineer II / Member Engineer II / Member Engineer II / Chairman District Engineer
Republic of the Philippines
Department of Public Works and Highways
Region IV-B, MIMAROPA
OFFICE OF THE DISTRICT ENGINEER
Masipit, Calapan City, Oriental Mindoro FORM ABC-2015-02A-00
CONSTRUCTION OF POLA BC BUILDING, POLA, ORIENTAL MINDORO

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 270 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION QUANTITY UNIT ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST UNIT COST
% VALUE
AS SUBMITTED 5.00 ea 5,698.90 20% 1,139.78 341.93 1,481.71 7,180.61 1,436.12
1001 (5) b Catch Basin, CHB
AS EVALUATED

AS SUBMITTED 1.00 l.s. 83,121.12 20% 16,624.22 4,987.27 21,611.49 104,732.61 104,732.61
1002(4) Plumbing Fixtures
AS EVALUATED

AS SUBMITTED 1.00 l.s. 299,261.64 20% 59,852.33 17,955.70 77,808.03 377,069.67 377,069.67
1201 (8) Water Tank
AS EVALUATED

AS SUBMITTED - l.s. - 20% - - - - #DIV/0!


1002 (26) Cistern
AS EVALUATED

AS SUBMITTED - l.s. - 20% - - - - #DIV/0!


1201 (1) Water Pumping System, Lumpsum
AS EVALUATED

AS SUBMITTED 515,928.09 103,185.62 30,955.69 134,141.31 650,069.40


TOTAL OF PART D
AS EVALUATED

Prepared and Submitted by : Checked and Reviewed by the Estimating Committee : Approved By:

RAMIR G. BASA RAMIR G. BASA DUANE ANDREW ORIEL C. ANORICO ERROL R. VILLAN ERWIN DG. UMALI
Engineer II Engineer II( Member) Engineer II ( Member) Engineer II ( Chairman ) OIC-OFFICE OF THE DISTRICT ENGINEER
PART E ELECTRICAL WORKS
AS SUBMITTED 1.00 l.s. 37,336.66 20% 7,467.33 2,240.20 9,707.53 47,044.19 47,044.19
1100(10) Conduit, Boxes, and Fittings (Conduit Works/Conduit Rough-in)
AS EVALUATED
AS SUBMITTED 1.00 l.s. 76,814.82 20% 15,362.96 4,608.89 19,971.85 96,786.67 96,786.67
1101(33) Wires and Wiring Devices
AS EVALUATED
AS SUBMITTED 1.00 l.s. 20,964.08 20% 4,192.82 1,257.85 5,450.67 26,414.75 26,414.75
1102(1) Panelboard with Main and Branch Breakers
AS EVALUATED
AS SUBMITTED 1.00 l.s. 93,316.16 20% 18,663.23 5,598.97 24,262.20 117,578.36 117,578.36
1103(1) Lighting Fixtures
AS EVALUATED
AS SUBMITTED - l.s. - 22% - - - #DIV/0!
1208(1) Fire Alarm System
AS EVALUATED
AS SUBMITTED - l.s. - 22% - - - - #DIV/0!
1726(1) Generator Set, Lump Sum
AS EVALUATED
Pole Mounted Distribution Transformer with Complete AS SUBMITTED - l.s. - 20% - - - - #DIV/0!
1102(10)
Accesorries AS EVALUATED
AS SUBMITTED 228,431.72 45,686.34 13,705.91 59,392.25 287,823.97
TOTAL OF PART E
AS EVALUATED
PART F MECHANICAL WORKS
AS SUBMITTED - set - 22% - - - - #DIV/0!
1200(5) Exhaust Fan, Ceiling Cassette
AS EVALUATED
AS SUBMITTED - l.s. - 22% - - - - #DIV/0!
1101(33) Wires and Wiring Devices
AS EVALUATED
AS SUBMITTED - l.s. - 22% - - - - #DIV/0!
1102(1) Panelboard with Main and Branch Breakers
AS EVALUATED
AS SUBMITTED 1.00 l.s. 796,035.20 22% 175,127.74 48,558.15 223,685.89 1,019,721.09 1,019,721.09
1200 (13) a Airconditioning (Package/Split type)
AS EVALUATED
AS SUBMITTED - l.s. - 20% - - - - #DIV/0!
1208(1) Fire Alarm System
AS EVALUATED
AS SUBMITTED 796,035.20 175,127.74 48,558.15 223,685.89 1,019,721.09
TOTAL OF PART F
AS EVALUATED
AS SUBMITTED 5,960,105.21 1,192,021.02 476,552.62 1,668,573.64 7,628,678.85
TOTAL OF PART III
AS EVALUATED
AS SUBMITTED 8,043,929.32 1,607,865.43 482,589.79 2,090,455.22 10,134,384.54
TOTAL OF (Project ID)
AS EVALUATED
AS SUBMITTED 6,074,758.87 1,198,110.64 482,589.79 1,680,700.43 7,755,459.30
GRAND TOTAL
AS EVALUATED

Prepared and Submitted by : Checked and Reviewed by the Estimating Committee : Approved By:

RAMIR G. BASA RAMIR G. BASA ROMEO A. VILLANUEVA DUANE ANDREW ORIEL C. ANORICO ERWIN DG. UMALI
Engineer II Engineer II( Member) Architect II ( Member) Engineer II ( Chairman ) OIC-OFFICE OF THE DISTRICT ENGINEER
DIMENSIONS
Footing Name /
Description Depth from
Length Width Thickness Qty.
Base to NGL

F1 1.70 1.70 0.40 2.00 9.00


CF-1 3.64 2.00 0.40 2.00 1.00
CF-2 5.00 1.80 0.40 2.00 1.00
CF-3 4.01 1.80 0.40 2.00 1.00
CF-4 2.41 1.80 0.40 2.00 1.00
CF-5 2.65 1.80 0.40 2.00 1.00
FOOTING

CF-6 4.15 1.80 0.40 2.00 1.00


Stair Footing 1.20 0.60 0.25 0.50 1.00

TOTAL

DIMENSIONS
Column Name / Height from
Description Length Width Top of Footing Qty.
to NGL

C1-F1 0.40 0.40 1.60 9.00


C2-CF-1 0.25 0.40 1.60 2.00
C1-CF-2 0.40 0.40 1.60 2.00
C2-CF-2 0.25 0.40 1.60 1.00
C1-CF-3 0.40 0.40 1.60 2.00
COLUMN

SC-CF-3 0.25 0.25 0.70 1.00


SC 0.25 0.25 0.70 1.00
C1-CF-4 0.40 0.40 1.60 2.00
C1-CF-5 0.40 0.40 1.60 1.00
C2-CF-5 0.25 0.40 1.60 1.00
C1-CF-6 0.40 0.40 1.60 2.00
C2-CF-6 0.25 0.40 1.60 1.00
TOTAL

DIMENSIONS
FTB Name /
Description Depth from
Width Depth Total Span Qty.
Base to NGL

FTB-1 0.25 0.50 4.00 0.30 4.00


FTB-1 0.25 0.50 4.00 0.30 3.00
FTB-1 0.25 0.50 2.25 0.30 1.00
FTB-1 0.25 0.50 2.55 0.30 3.00
FTB-1 0.25 0.50 4.20 0.30 2.00
FOOTING TIE BEAM

FTB-1 0.25 0.50 1.95 0.30 2.00


FTB-1 0.25 0.50 1.65 0.30 1.00
FTB-1 0.25 0.50 3.15 0.30 2.00
FTB-1 0.25 0.50 1.27 0.30 1.00
FTB-1 0.25 0.50 2.74 0.30 2.00
FTB-1 0.25 0.50 4.00 0.30 2.00
FTB-1 0.25 0.50 1.37 0.30 1.00
FTB-1 0.25 0.50 2.64 0.30 2.00
FTB-1 0.25 0.50 4.00 0.30 4.00

TOTAL

DIMENSIONS
WF Name /
Description Width Thickness Total Span Depth from Qty.
Base to NGL

WF-1 0.40 0.25 1.65 0.85 1.00


WALL FOOTING
WA

TOTAL

DIMENSIONS
CHB Name / Height from
Description Total Length / CHB Thickness Top of WF to Qty.
Perimeter
NGL

WF1 1.65 0.15 0.60 1.00


-
-
-
-
CHB WALL

-
-
-
-
-
-
-
-
-
-
-
-

TOTAL

Excavated Backfill Excess Soil


REF DESCRIPTION
Volume Volume Volume
I FOOTING 132.53 N/A N/A
II COLUMN 115.16 109.67 5.50
III FOOTING TIE BEAM 7.16 (4.78) 11.94
IV WALL FOOTING 0.56 N/A N/A
V CHB WALL 0.40 0.25 0.15
TOTAL 255.82 105.14 17.58
EXCAVATION / BACKFILL
Excavated Volume Backfill Volume

52.02 50.86
14.54 11.64
18.00 14.40
14.44 11.55
8.69 6.95
9.54 7.63
14.94 11.95
0.36 0.18
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
132.53 115.16 -

EXCAVATION / BACKFILL

Backfill Volume
From Footing Backfill Volume Excess Soil Volume

50.86 48.56 2.30


11.64 11.32 0.32
14.40 13.89 0.51
11.55 11.39 0.16
6.95 6.44 0.51
7.63 7.59 0.04
11.95 11.91 0.04
0.18 (0.33) 0.51
- (0.26) 0.26
- (0.16) 0.16
- (0.51) 0.51
- (0.16) 0.16
- - -
- - -
- - -
- - -
- - -
- - -
115.16 109.67 5.50

EXCAVATION / BACKFILL
Excavated Volume Backfill Volume Excess Soil Volume

1.20 (0.80) 2.00


0.90 (0.60) 1.50
0.17 (0.11) 0.28
0.57 (0.38) 0.96
0.63 (0.42) 1.05
0.29 (0.20) 0.49
0.12 (0.08) 0.21
0.47 (0.32) 0.79
0.09 (0.06) 0.16
0.41 (0.27) 0.68
0.60 (0.40) 1.00
0.10 (0.07) 0.17
0.40 (0.26) 0.66
1.20 (0.80) 2.00
- - -
- - -
- - -
- - -
- - -
- - -
7.16 - 4.78 11.94

EXCAVATION / BACKFILL
Excavated Volume Backfill Volume

0.56 0.40
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
0.56 0.40

EXCAVATION / BACKFILL

Backfill Volume Backfill Volume Excess Soil Volume


From WF

0.40 0.25 0.15


- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
0.40 0.25 0.15
1 Storey 5 Classroom

DIMENSIONS
Footing Name /
Description Length Width Thickness Qty. Volume

-
F1 1.70 1.70 0.40 9.00 10.40
CF-1 3.64 2.00 0.40 1.00 2.91
CF-2 5.00 1.80 0.40 1.00 3.60
CF-3 4.01 1.80 0.40 1.00 2.89
CF-4 2.41 1.80 0.40 1.00 1.74
CF-5 2.65 1.80 0.40 1.00 1.91
FOOTING

CF-6 4.15 1.80 0.40 1.00 2.99


Stair Footing 1.20 0.60 0.25 1.00 0.18
-
-
-
-
-
-
-
-
-
-
TOTAL 26.61

DIMENSIONS
FTB Name /
Description Width Depth Total Span Qty. Volume

-
FTB-1 0.25 0.50 4.00 4.00 2.00
FTB-1 0.25 0.50 4.00 3.00 1.50
FTB-1 0.25 0.50 2.25 1.00 0.28
FTB-1 0.25 0.50 2.55 3.00 0.96
FOOTING TIE BEAM

FTB-1 0.25 0.50 4.20 2.00 1.05


FTB-1 0.25 0.50 1.95 2.00 0.49
FTB-1 0.25 0.50 1.65 1.00 0.21
FTB-1 0.25 0.50 3.15 2.00 0.79
FTB-1 0.25 0.50 1.27 1.00 0.16
FTB-1 0.25 0.50 2.74 2.00 0.68
FTB-1 0.25 0.50 4.00 2.00 1.00
FTB-1 0.25 0.50 1.37 1.00 0.17
FTB-1 0.25 0.50 2.64 2.00 0.66
FTB-1 0.25 0.50 4.00 4.00 2.00
-
-
-
-
TOTAL 11.94

DIMENSIONS
WF Name /
Description Width Depth Total Span Qty. Volume

-
WF-1 0.40 0.25 1.65 1.00 0.17
-
-
-
WALL FOOTING

-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL 0.17

DIMENSIONS
Column Name /
Description Length Width Height Qty. Volume

-
C1-F1 0.40 0.40 9.20 9.00 13.25
C2-CF-1 0.25 0.40 9.20 2.00 1.84
C1-CF-2 0.40 0.40 9.20 2.00 2.94
C2-CF-2 0.25 0.40 9.20 1.00 0.92
C1-CF-3 0.40 0.40 9.20 2.00 2.94
SC-CF-3 0.25 0.25 9.20 1.00 0.58
COLUMN

SC 0.25 0.25 9.20 1.00 0.58


C1-CF-4 0.40 0.40 9.20 2.00 2.94
C1-CF-5 0.40 0.40 9.20 1.00 1.47
C2-CF-5 0.25 0.40 9.20 1.00 0.92
C1-CF-6 0.40 0.40 9.20 2.00 2.94
C2-CF-6 0.25 0.40 9.20 1.00 0.92
C1-F1 0.40 0.40 1.00 4.00 0.64
-
-
-
-
-
TOTAL 32.89

DIMENSIONS
Beam Name /
Description Length Width Height Qty. Volume

-
2B-1 4.00 0.25 0.40 4.00 1.60
2B-1 4.00 0.25 0.40 3.00 1.20
2B-1 2.05 0.25 0.40 1.00 0.21
2B-2 1.95 0.25 0.30 1.00 0.15
2B-1 2.55 0.25 0.40 3.00 0.77
2B-2 2.55 0.25 0.30 1.00 0.19
2B-1 4.20 0.25 0.40 2.00 0.84
2B-2 4.20 0.25 0.30 1.00 0.32
2B-1 1.95 0.25 0.40 2.00 0.39
2B-1 3.15 0.25 0.40 2.00 0.63
2B-1 1.65 0.25 0.40 2.00 0.33
2B-1 4.00 0.25 0.40 2.00 0.80
2B-1 1.27 0.25 0.40 1.00 0.13
2B-1 2.74 0.25 0.40 2.00 0.55
GIRDER / BEAM

2B-1 4.00 0.25 0.40 5.00 2.00


2B-1 2.64 0.25 0.40 1.00 0.26
2B-1 1.00 0.25 0.40 2.00 0.20
-
3B-1 4.00 0.25 0.40 4.00 1.60
3B-1 4.00 0.25 0.40 3.00 1.20
3B-1 2.05 0.25 0.40 1.00 0.21
3B-2 1.95 0.25 0.30 1.00 0.15
3B-1 2.55 0.25 0.40 3.00 0.77
3B-1 4.20 0.25 0.40 2.00 0.84
3B-1 1.95 0.25 0.40 2.00 0.39
3B-1 3.15 0.25 0.40 2.00 0.63
3B-1 1.65 0.25 0.40 2.00 0.33
3B-1 4.00 0.25 0.40 2.00 0.80
3B-1 1.27 0.25 0.40 1.00 0.13
3B-1 2.74 0.25 0.40 2.00 0.55
3B-1 4.00 0.25 0.40 4.00 1.60
3B-1 1.37 0.25 0.40 1.00 0.14
3B-1 2.64 0.25 0.40 2.00 0.53
RB-1 2.55 0.25 0.30 2.00 0.38
RB-1 2.74 0.25 0.30 2.00 0.41
-
-
TOTAL 21.19

DIMENSIONS
Area Description /
Floor No. Area Thicknes Qty. Volume

-
Slab 119.43 0.10 1.00 11.94
Suspended Slab 232.90 0.125 1.00 29.11
FLOOR SLAB / COUNTER TOP

Canopy 7.58 0.10 1.00 0.76


Counter top 3.74 0.10 1.00 0.37
Ramp 2.89 0.10 1.00 0.29
Stair Steps 0.05 0.90 32.00 1.44
Stair bot 0.84 0.90 1.00 0.76
Stair Landing 3.44 0.13 2.00 0.86
Pathwalk 55.00 0.10 1.00 5.50
-
-
-
-
-
-
-
-
-
TOTAL 51.03

DIMENSIONS
Description
Height Total Span Thickness Qty. Volume
COUNTER SIDE / RETAINING / SHEAR WALL

-
Counter Side 0.80 0.60 0.10 4.00 0.19
Stair column 0.50 1.20 0.16 1.00 0.10
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
COU
-
TOTAL 0.29

4" thk. CHB


Description Wall Total
Height Wall Area CHB in pcs
Length
- -
1st floor 12.80 3.40 43.52 544.00
2nd floor 17.00 3.20 54.40 680.00
- -
- -
4" thk CHB WALL

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
TOTAL 97.92 1,224.00

5" thk. CHB


Description Wall Total
Total Span Wall Area CHB in pcs
Length
- -
- -
- -
- -
- -
5" thk CHB WALL

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
TOTAL - -

6" thk. CHB


Description Wall Total
Total Span Wall Area CHB in pcs
Length
- -
1st floor 55.70 3.40 189.38 2,367.25
2nd floor 55.70 3.20 178.24 2,228.00
Roof Deck 55.70 1.00 55.70 696.25
Roof Deck 2 13.40 3.10 41.54 519.25
6" thk CHB WALL

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
TOTAL 464.86 5,810.75

REF DESCRIPTION QTY UNIT CHB PCS


I FOOTING 26.61 cu.m N/A
II FOOTING TIE BEAM 11.94 cu.m N/A
III WALL FOOTING 0.17 cu.m N/A
IV COLUMN 32.89 cu.m N/A
V GIRDER / BEAM 21.19 cu.m N/A
VI FLOOR SLAB / COUNTER TOP 51.03 cu.m N/A
VII COUNTER SIDE / RETAINING / SHEAR WALL 0.29 cu.m N/A
VIII 4" thk CHB WALL 97.92 sq.m 1,224.00
IX 5" thk CHB WALL - sq.m -
X 6" thk CHB WALL 464.86 sq.m 5,810.75
TOTAL 7,034.75
0.1 2.60
0.1 0.73
0.1 0.90
0.1 0.72
0.1 0.43
0.1 0.48
0.1 0.75
0.1 0.07
6.68
0.1 0.07
0.1 -
0.1 -
0.1 -
0.1 -
0.1 -
0.1 -
0.07
17.73 slab on fill
31.11 suspended
2.20 beam

under beams
ok
ok
ok
ok
ok
ok
ok
ok
ok
ok
ok
Commercial 6

Footing Main kg
F1 16 1.58 63.00 597.24
CF-1 16 1.58 17.00 161.16
CF-2 16 1.58 20.00 189.60
CF-3 16 1.58 16.00 151.68
CF-4 16 1.58 10.00 94.80
CF-5 16 1.58 11.00 104.28
CF-6 16 1.58 17.00 161.16
Stair Footing 12 0.89 3.00 16.02

1,475.94

FTB Main Ties KG


FTB-1 20 2.47 20.00 10 0.62 40.00 296.4
FTB-1 20 2.47 15.00 10 0.62 30.00 222.3
FTB-1 20 2.47 3.00 10 0.62 7.00 44.46
FTB-1 20 2.47 9.00 10 0.62 24.00 133.38
FTB-1 20 2.47 10.00 10 0.62 22.00 148.2
FTB-1 20 2.47 6.00 10 0.62 14.00 88.92
FTB-1 20 2.47 2.00 10 0.62 6.00 29.64
FTB-1 20 2.47 8.00 10 0.62 18.00 118.56
FTB-1 20 2.47 2.00 10 0.62 6.00 29.64
FTB-1 20 2.47 6.00 10 0.62 16.00 88.92
FTB-1 20 2.47 10.00 10 0.62 20.00 148.2
FTB-1 20 2.47 2.00 10 0.62 6.00 29.64
FTB-1 20 2.47 6.00 10 0.62 16.00 88.92
FTB-1 20 2.47 20.00 10 0.62 40.00 296.4

1763.58

WF Main Ties KG
WF-1 10 0.62 1.00 10 0.62 2 3.72

3.72

Column Main Ties Ties


C1-F1 20 2.47 181.00 10 0.62 180.00 10 0.62
C2-CF-1 20 2.47 27.00 10 0.62 34.00 10 0.62
C1-CF-2 20 2.47 40.00 10 0.62 40.00 10 0.62
C2-CF-2 20 2.47 13.00 10 0.62 17.00 10 0.62
C1-CF-3 20 2.47 40.00 10 0.62 40.00 10 0.62
SC-CF-3 16 1.58 10.00 10 0.62 14.00 10 0.62
SC 16 1.58 10.00 10 0.62 14.00 10 0.62
C1-CF-4 20 2.47 40.00 10 0.62 40.00 10 0.62
C1-CF-5 20 2.47 20.00 10 0.62 20.00 10 0.62
C2-CF-5 20 2.47 20.00 10 0.62 17.00 10 0.62
C1-CF-6 20 2.47 40.00 10 0.62 40.00 10 0.62
C2-CF-6 20 2.47 13.00 10 0.62 17.00 10 0.62
C1-F1 20 2.47 9.00 10 0.62 20.00 10 0.62

Beam Main Ties KG


2B-1 16 1.58 20.00 10 0.62 36.00 189.6
2B-1 16 1.58 15.00 10 0.62 27.00 142.2
2B-1 16 1.58 3.00 10 0.62 7.00 28.44
2B-2 16 1.58 2.00 10 0.62 6.00 18.96
2B-1 16 1.58 9.00 10 0.62 21.00 85.32
2B-2 16 1.58 3.00 10 0.62 7.00 28.44
2B-1 16 1.58 10.00 10 0.62 20.00 94.8
2B-2 16 1.58 4.00 10 0.62 9.00 37.92
2B-1 16 1.58 6.00 10 0.62 14.00 56.88
2B-1 16 1.58 8.00 10 0.62 16.00 75.84
2B-1 16 1.58 4.00 10 0.62 12.00 37.92
2B-1 16 1.58 10.00 10 0.62 18.00 94.8
2B-1 16 1.58 2.00 10 0.62 6.00 18.96
2B-1 16 1.58 6.00 10 0.62 16.00 56.88
2B-1 16 1.58 25.00 10 0.62 45.00 237
2B-1 16 1.58 3.00 10 0.62 7.00 28.44
2B-1 16 1.58 4.00 10 0.62 10.00 37.92

3B-1 16 1.58 16.00 10 0.62 36.00 151.68


3B-1 16 1.58 12.00 10 0.62 27.00 113.76
3B-1 16 1.58 2.00 10 0.62 7.00 18.96
3B-2 16 1.58 2.00 10 0.62 6.00 18.96
3B-1 16 1.58 9.00 10 0.62 21.00 85.32
3B-1 16 1.58 8.00 10 0.62 20.00 75.84
3B-1 16 1.58 4.00 10 0.62 14.00 37.92
3B-1 16 1.58 6.00 10 0.62 16.00 56.88
3B-1 16 1.58 4.00 10 0.62 12.00 37.92
3B-1 16 1.58 8.00 10 0.62 18.00 75.84
3B-1 16 1.58 2.00 10 0.62 6.00 18.96
3B-1 16 1.58 6.00 10 0.62 16.00 56.88
3B-1 16 1.58 16.00 10 0.62 36.00 151.68
3B-1 16 1.58 2.00 10 0.62 6.00 18.96
3B-1 16 1.58 6.00 10 0.62 14.00 56.88
RB-1 16 1.58 6.00 10 0.62 14.00 56.88
RB-1 16 1.58 6.00 10 0.62 14.00 56.88

2360.52
Floor Slab Main kg
Slab 10 0.62 143 531.96
Suspended Slab 12 0.89 284 1516.56
Canopy 10 0.62 14 52.08
Counter top 10 0.62 12 44.64
Ramp 10 0.62 4 14.88
Stair Steps 10 0.62 22 81.84
Stair bot 10 0.62 18 66.96
Stair Landing 10 0.62 7 26.04
Pathwalk 10 0.62 47.00 174.84
2509.8

Counter Side Main kg


Counter Side 10 0.62 5.00 18.6
Stair column 10 0.62 6 22.32
40.92

Total KG. 21,277.98

m
Floor Slab 2.6 6 15.6
4 14 56
6.7 9 60.3
8 6 48
9.65 7 67.55
11.15 13 144.95
16.7 8 133.6
14.75 5 73.75
10.65 9 95.85
8 4 32
6.25 6 37.5
4 4 16
781.1

2nd Floor 11.15 26 289.9


9.65 27 260.55
4.85 15 72.75
4 28 112
2.6 13 33.8
2.9 7 20.3
16.7 17 283.9
14.75 9 132.75
8 39 312
4 10 40
1557.95

Canopy 1.7 22 37.4


2.25 16 36
73.4

Counter Top 2.6 9 23.4


1.2 5 6
2.3 8 18.4
1.5 9 13.5
61.3

Ramp 1.65 5 8.25


1.75 5 8.75
17
KG
148.8
111.6
26.04
89.28
81.84
52.08
22.32
66.96
22.32
59.52
74.4
22.32
59.52
148.8

985.8

KG
7.44

7.44

KG KG KG
144.00 2682.42 669.6 535.68
28.00 400.14 126.48 104.16
32.00 592.8 148.8 119.04
14.00 192.66 63.24 52.08
32.00 592.8 148.8 119.04
9.00 94.80 52.08 33.48
9.00 94.8 52.08 33.48
32.00 592.8 148.8 119.04
16.00 296.4 74.4 59.52
14.00 296.4 63.24 52.08
32.00 592.8 148.8 119.04
14.00 192.66 63.24 52.08
16.00 133.38 74.4 59.52

6754.86 1833.96 1,458.24

KG
133.92
100.44
26.04
22.32
78.12
26.04
74.4
33.48
52.08
59.52
44.64
66.96
22.32
59.52
167.4
26.04
37.2

133.92
100.44
26.04
22.32
78.12
74.4
52.08
59.52
44.64
66.96
22.32
59.52
133.92
22.32
52.08
52.08
52.08

2083.2

119.43 0.84
FOOTING TIE BEAM Width Depth Total Span Qty. Surface Area

FTB-1 0.25 0.50 4.00 4.00 20.00


FTB-1 0.25 0.50 4.00 3.00 15.00
FTB-1 0.25 0.50 2.25 1.00 2.81
FTB-1 0.25 0.50 2.55 3.00 9.56
FTB-1 0.25 0.50 4.20 2.00 10.50
FTB-1 0.25 0.50 1.95 2.00 4.88
FTB-1 0.25 0.50 1.65 1.00 2.06
FTB-1 0.25 0.50 3.15 2.00 7.88
FTB-1 0.25 0.50 1.27 1.00 1.58
FTB-1 0.25 0.50 2.74 2.00 6.84
FTB-1 0.25 0.50 4.00 2.00 10.00
FTB-1 0.25 0.50 1.37 1.00 1.71
FTB-1 0.25 0.50 2.64 2.00 6.59
FTB-1 0.25 0.50 4.00 4.00 20.00

119.40

COLUMN Length Width Height Qty. Surface Area

C1-F1 0.40 0.40 9.20 9.00 99.36


C2-CF-1 0.25 0.40 9.20 2.00 19.32
C1-CF-2 0.40 0.40 9.20 2.00 22.08
C2-CF-2 0.25 0.40 9.20 1.00 9.66
C1-CF-3 0.40 0.40 9.20 2.00 22.08
SC-CF-3 0.25 0.25 9.20 1.00 6.90
SC 0.25 0.25 9.20 1.00 6.90
C1-CF-4 0.40 0.40 9.20 2.00 22.08
C1-CF-5 0.40 0.40 9.20 1.00 11.04
C2-CF-5 0.25 0.40 9.20 1.00 9.66
C1-CF-6 0.40 0.40 9.20 2.00 22.08
C2-CF-6 0.25 0.40 9.20 1.00 9.66
C1-F1 0.40 0.40 1.00 4.00 4.80

132.81

GIRDER / BEAM Length Width Height Qty. Surface Area

2B-1 4.00 0.25 0.40 4.00 7.20


2B-1 4.00 0.25 0.40 3.00 5.40
2B-1 2.05 0.25 0.40 1.00 1.02
2B-2 1.95 0.25 0.30 1.00 0.74
2B-1 2.55 0.25 0.40 3.00 3.66
2B-2 2.55 0.25 0.30 1.00 0.92
2B-1 4.20 0.25 0.40 2.00 3.76
2B-2 4.20 0.25 0.30 1.00 1.41
2B-1 1.95 0.25 0.40 2.00 1.96
2B-1 3.15 0.25 0.40 2.00 2.92
2B-1 1.65 0.25 0.40 2.00 1.72
2B-1 4.00 0.25 0.40 2.00 3.60
2B-1 1.27 0.25 0.40 1.00 0.71
2B-1 2.74 0.25 0.40 2.00 2.59
2B-1 4.00 0.25 0.40 5.00 9.00
2B-1 2.64 0.25 0.40 1.00 1.25
2B-1 1.00 0.25 0.40 2.00 1.20

3B-1 4.00 0.25 0.40 4.00 7.20


3B-1 4.00 0.25 0.40 3.00 5.40
3B-1 2.05 0.25 0.40 1.00 1.02
3B-2 1.95 0.25 0.30 1.00 0.74
3B-1 2.55 0.25 0.40 3.00 3.66
3B-1 4.20 0.25 0.40 2.00 3.76
3B-1 1.95 0.25 0.40 2.00 1.96
3B-1 3.15 0.25 0.40 2.00 2.92
3B-1 1.65 0.25 0.40 2.00 1.72
3B-1 4.00 0.25 0.40 2.00 3.60
3B-1 1.27 0.25 0.40 1.00 0.71
3B-1 2.74 0.25 0.40 2.00 2.59
3B-1 4.00 0.25 0.40 4.00 7.20
3B-1 1.37 0.25 0.40 1.00 0.75
3B-1 2.64 0.25 0.40 2.00 2.51
RB-1 2.55 0.25 0.30 2.00 1.83
RB-1 2.74 0.25 0.30 2.00 1.94

98.54

FLOOR SLAB / COUNTER TOP Area

Slab 119.43
Suspended Slab 232.90
Canopy 7.58
240.48

Stair Steps
Stair bot
Stair Landing

COUNTER SIDE / RETAINING / SHEAR WALL

Stair column

Total Area= 492.69


unit weight kgs
25mm x 25mm Tubular Steel 30.588 1.08 33.03504
50mm x 50mm Tubular Steel 10.196 2.25 22.941
100mm x 250mm x 15mm Thk. C-Beam 14.3 41.9 599.17
Checkered Plate 4.65092 11.78 54.78784
100mm dia G.I Pipe 1
Septic Tank

Walls
L H thickness no. cu.m
Long Side 3.2 1.8 0.15 2 1.728
Short Side 1.8 1.8 0.15 2 0.972
Partition 1.8 1.8 0.1 1 0.324

Flooring
L W thickness no. cu.m
3.2 1.8 0.15 1 0.864

Cover
L W thickness no. cu.m
3.2 1.8 0.15 1 0.864

Reinforcement

Walls
L H L-H L-V Total Length
Long Side 3.2 1.8 49.68 52.48 102.16 m
Short Side 1.8 1.8 29.52 29.52 59.04 m
Partition 1.8 1.8 14.76 14.76 29.52 m

Flooring
L W L-H L-V Total Length
3.2 1.8 24.84 26.24 51.08 m

Cover L W L-H L-V Total Length


3.2 1.8 24.84 26.24 51.08 m

CHB 150mm L W Area Pcs


1.8 1.8 3.24 40.5

Sand 2.376
Gravel 4.752 43.2432 45.5
RSB 462.7504
Transformer Platform

Footing L W thickness no. cu.m


1 1.22 0.2 2 0.488

Column L W H no. cu.m


0.2 0.2 6 2 0.48

Beam W D L no. cu.m


0.2 0.2 2.743 1 0.10972

Walls
L H thickness no. cu.m
Short Side 1.22 2.429 0.152 2 0.90086752

Platform
L W thickness no. cu.m
2.743 1.22 0.152 1 0.50866192

Reinforcement

Footing L W L-H L-V Total Length


1 1.22 20 24.4 44.4 16mm

Column L W H no. Total Length


0.2 0.2 5.982 2 47.856 16mm
Ties 2.6 18 24 1.2 50.4 10mm

Beam W D L no. Total Length


0.2 0.2 2.743 1 10.972 16mm
Ties 1.1 10 14 1.2 28.8 10mm

Walls
L H L-H L-V Total Length
Short Side 1.22 2.429 28.56504 26.14704 54.71208 m

Platform L W L-H L-V Total Length


2.743 1.22 14.60584 16.12884 30.73468 m
Sand 1.2436247
Gravel 2.4872494
RSB 347.21012
Cistern Tank

Walls
L H thickness no. cu.m
Long Side 2.2 1.6 0.1 2 0.704
Short Side 1.4 1.6 0.1 2 0.448

Flooring
L W thickness no. cu.m
2.2 1.4 0.1 1 0.308

Cover
L W thickness no. cu.m
2.2 1.4 0.1 1 0.308

Reinforcement

Walls
L H L-H L-V Total Length
Long Side 2.2 1.6 31.36 32.56 63.92 m
Short Side 1.4 1.6 21.12 20.72 41.84 m

Flooring
L W L-H L-V Total Length
2.2 1.4 13.72 14.52 28.24 m

Cover L W L-H L-V Total Length


2.2 1.4 13.72 14.52 28.24 m

Sand 0.884
Gravel 1.768
RSB 256.3392
Stainless Steel Grill
Roof

C Purlins
L Unit Weight kg
13.675 2.355 32.20463
A
IC
ER
SH
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS UNIT

101(1) Removal of Structures and Obstruction

800 (1) Clearing and Grubbing

Surplus Common Excavation (For BASKETBALL COURT)

803 (1) a Structure Excavation, Common Soil

804 (1) a Embankment from Roadway/Structure Excavation

804 (1) b Embankment from Borrow

804 (4) Gravel Fill

1706(1) Overhaul, Cubic Meter-Kilometer

PART B PLAIN AND REINFORCED CONCRETE WORKS

900(1)c2 Structural Concrete (Footings and Slab on Fill), A, 28 days

Structural Concrete (Footing Tie Beams), 28 days, A


900(1)c3

Structural Concrete (Column), A, 28 days


900(1)c4

900(1)c5 Structural Concrete (Suspended Slab), A, 28 days

Structural Concrete (Beams/Girders), A, 28 days


900(1)c6

902 (1) a Reinforcing Steel (Deformed), Grade 40

903 (2) Formworks and Falseworks

PART C FINISHING

1046 (2) a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm

1046 (2) a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm

C.3 Fabricated Materials

1010 (4) Wooden Doors and Windows

1008(1)a Aluminum Glass Window (SLIDING Type)

1004 (2) Finishing Hardware


C.4 Finishing Works

1027 (1) Cement Plaster Finish

1051 (6) Railing

1003 (1) a1 Ceiling, Fiber Cement Board, 4.5mm, Metal Frame

1018 (1) Glazed Tiles and Trims

1018 (2) Unglazed Tiles

C.5 Painting Works

1032 (1) a Painting Works, Masonry/Concrete

1032 (1) b Painting Works, Wood

1032 (1) c Painting Works, Steel

411(2) Paint

C.6 Roof Framing and Roofing Works


Prepainted Metal Sheets Long Span, Rib Type, above 0.427 mm,
1014 (1) b2
Long Span
Prepainted Metal Sheets Long Span, Corrugated Type, above
1014(1)b1
0.427 mm, Long Span

1013(2)b1 Fabricated Metal Roofing Accessory, gauge 24, Gutters

1013(2)a1 Fabricated Metal Roofing Accessory, gauge 26, Ridge/Rolls

1013 (2) a2 Fabricated Metal Roofing Accessory, gauge 26, Flashings

1047 (2) a Structural Steel, Trusses

1047 (2) b Structural Steel Purlins

1047 (6) Metal Structure Accessories (Steel Plates)

1047 (3) a Metal Structure Accessories, Bolts

1047 (3)d Metal Structure Accessories (Cross bracing)

1047 (3) c Metal Structure Accessories, Turnbuckle

1047 (3) b Metal Structure Accessories, Sagrods

1047 (10) Structural Steel

PART D PLUMBING/SANITARY WORKS

1001 (8) Sewer Line Works


1002 (24) Cold Water Lines

1001 (9) Storm Drainage and Downspout

ls
1002 (27) Plumbing Works

ls
1002(8) Plumbing Fixtures

1001 (11) Septic Vault (Concrete/CHB)

1001 (5) b Catch Basin, chb chb

PART E ELECTRICAL

1100(10) Conduit, Boxes, and Fittings (Conduit Works/Conduit Rough-in)

1101(33) Wires and Wiring Devices

1102(1) Panelboard with Main and Branch Breakers

1103(1) Lighting Fixtures


A

A
N

N
IC

IC
RO

RO

RO
ER

ER
GN
AA

AA

AA
SH

SH
KI
BARANGAY
PUTING CACAO BACUNGAN MALUANLUAN MATULATULA CALUBASANHON
1 1 1

1 1 1 1

47.4 25.97 2.22

168

29.66 106.52 0.9

11.25 36.09

47.14 5.25 3.78 0.41

49.94 48.8 51.01 43.88

8.55 11.55 0.79

10.2 12.02 0.6

11.9

0.56 10.08

5369.88 11278.96 4019.32 2275.73

82.41 463.93 141.62 144.98

61.8 241.4 73.83 32.4

37.15

20.46

1
136.98 476.26 92 73.92

68

29.98

5.16

136.98 571.65 90.72 150.77

144

517.73 517.56 592.43

405 405

84.3 120.74 113.17

554.4 80 279

60 8 59 60

30 30

97.2 28.4 95.96

10324.58 1200.2 1463.68 1227.62

2669.2 263.73 359.75

237.99 47.1

56 40

24

24

156

1 1

1
1

1 1 1

1 1 1 1

1 1 1 1

1 1 1 1

1 1 1
1
A
IC
ER
SH

BAYANAN TOTAL
3

1 5

43.5 119.09

168

0.83 137.91

47.34

46.32 102.9

46.32 239.95

20.89

1.91 24.73

11.9

10.64

2888.97 25832.86

48.19 881.13

68.8 478.23

37.15

20.46

1
103.2 882.36

68

29.98

5.16

103.2 1053.32

144

474.05 2101.77

810

84.3 402.51

591.6 1505

58 245

60

197.6 419.16

1232.01 15448.09

3292.68

285.09

96

24

24

156

1 3

1
1

1 2

3
15 X 27 Standard Multi-Purpose Building ( Covered Court )
CONSTRUCTION ESTIMATE

CONCRETE WORKS

SLAB ( Length x Width x Thickness )


28.30 x 20.00 x 0.10 = 56.60 Cu.m.
2.40 x 4.20 x 0.10 x 2.00 = 2.02 Cu.m.
17.45 x 3.80 x 0.10 = 6.63 Cu.m.
5.50 x 1.50 x 0.10 x 4.00 = 3.30 Cu.m.
68.55 Cu.m.

MEZZANINE SLAB ( Length x Width x Thickness )


( 122.00 - 3.25 + 33.604 ) x 0.10 = 15.24 Cu.m.

LADDER ( Length x Width x Thickness )


( 0.312 + 1.092 ) x 3.00 = 4.21 Cu.m.

Columns (Height X Thickness X Quantity )


0.30 x 0.40 x 7.80 x 24.00 = 22.46 Cu.m.
0.30 x 0.40 x 5.63 x 3.00 = 2.03 Cu.m.
0.25 x 0.40 x 7.80 x 9.00 = 7.02 Cu.m.
31.51 Cu.m.

Footings ( Length x Width x Height x Quantity )


2.00 x 2.00 x 0.30 x 36.00 = 43.20 Cu.m.
0.50 x 0.25 x 0.45 x 33.15 = 1.86 Cu.m.
45.06 Cu.m.

Footing Tie Beam ( Length x Width x Height x Quantity )


0.30 x 0.25 x 144.83 = 10.86 Cu.m.
FTB1-B 0.25 x 0.30 x 15.00 x 2.00 = - Cu.m.
10.86 Cu.m.

Beam ( Length x Width x Height x Quantity )


FB1 0.3 x 0.4 x 93.96 11.28 Cu.m.
FB2 0.25 x 0.3 x 6.35 0.48 Cu.m.
FB3 0.3 x 0.15 x 31.9 1.44 Cu.m.
FB4 0.25 x 0.4 x 71.45 7.15 Cu.m.
RB1 0.3 x 0.4 x 106.4 12.77 Cu.m.
RB2 0.25 x 0.4 x 35.33 3.53 Cu.m.
36.65 Cu.m.

REBAR WORKS

Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm. dia


10.00 x 2.00 x 2.00 x 36.000 x 1.58 = 2,275.20 Kgs
0.80 x 20.00 x 10.00 x 1.58 = - Kgs

Wall Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 12 mm.dia


3.00 x 33.15 x 1.00 x 0.888 = 88.31 Kgs
110.50 x 0.70 x 1.00 x 0.888 = 68.69 Kgs

Wall Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia


0.40 x 90.00 x 2.00 x 0.617 x 2.00 = - Kgs

Footing Tie Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Stirrups
724.15 x 1.10 x 0.617 = 491.48 Kgs
0.88 x 82.00 x 2.00 x 0.617 = - Kgs

Footing Tie Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm.dia/Main Bars
157.23 x 6.00 x 1.58 = 1,490.54 Kgs
157.23 x 6.00 x 1.58 = - Kgs
157.23 x 6.00 x 1.58 = - Kgs
Column ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 20 mm.dia/Main Bars
10.00 x 8.50 x 24.00 x 2.470 = 5,038.80 Kgs
10.00 x 6.28 x 3.00 x 2.470 = 465.35 Kgs
9.00 x 8.50 x 8.00 x 2.470 = 1,511.64 Kgs

Column ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Lateral Ties


14.00 x 40.00 x 24.00 x 0.617 = 8,292.48 Kgs
0.90 x 40.00 x 24.00 x 0.617 = 533.09 Kgs
0.90 x 28.90 x 3.00 x 0.617 = 48.14 Kgs
1.40 x 28.90 x 3.00 x 0.617 = 74.89 Kgs
1.30 x 40.00 x 9.00 x 0.617 = 288.76 Kgs

SOF ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Along X


66.00 x 28.00 x 1.00 x 0.617 = 1,140.22 Kgs

SOF ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Along Y


94.00 x 19.61 x 1.00 x 0.617 = 1,137.34 Kgs

Mezzanine Floor ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Along X


11.00 x 23.10 x 1.00 x 0.617 = 156.78 Kgs
16.00 x 6.97 x 1.00 x 0.617 = 68.81 Kgs

Mezzanine Floor ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Along Y


77.00 x 3.40 x 1.00 x 0.617 = 161.53 Kgs
23.00 x 4.68 x 1.00 x 0.617 = 66.41 Kgs

Beam ( Length x Width x Height x Theoretical Weight ) - 16 mm dia/ Main Bar


FB1 103.56 x 7.00 x 1.58 = 1,145.37 Kgs
FB2 6.75 x 6.00 x 1.58 = 63.99 Kgs
FB3 31.90 x 6.00 x 1.58 = 302.41 Kgs
FB4 79.45 x 7.00 x 1.58 = 878.72 Kgs
RB1 120.40 x 7.00 x 1.58 = 1,331.62 Kgs
RB2 40.13 x 7.00 x 1.58 = 443.84 Kgs

Beam ( Length x Width x Height x Theoretical Weight ) - 10 mm dia/ Stirrups


FB1 469.80 x 1.40 x 0.617 = 405.81 Kgs
FB2 31.75 x 1.10 x 0.617 = 21.55 Kgs
FB3 159.50 x 0.90 x 0.617 = 88.57 Kgs
FB4 357.25 x 1.30 x 0.617 = 286.55 Kgs
RB1 532.00 x 1.40 x 0.617 = 459.54 Kgs
RB2 176.65 x 1.30 x 0.617 = 141.69 Kgs

28,968.12 Kgs
TRUSSES

Main Truss ( Bottom Chord and Top Chord ) 100 x 100 x 6.35 (2L)
Length x Number x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kgs/Cu.m.)
23.63 x 2.00 x 10.00 x 0.0012296775 x 7850.00 = 4,561.99 Kgs.
3.00 x 3.00 x 1.00 x 0.0004320000 x 7850.00 = 30.52 Kgs.

Main Truss ( Web Members ) 50 x 50 x 6.35 (2L)


Length x Number x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kgs/Cu.m.)
16.09 x 2.00 x 10.00 x 0.00059467750 x 7850.00 = 1,502.23 Kgs.

Strut ( Bottom Chord and Top Chord ) 50 x 50 x 6.35 mm


Length x Number x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kgs/Cu.m.)
14.8000 x 1.00 x 20.00 x 0.00059467750 x 7850.00 = 1,381.79 Kgs.

Strut ( Web Members ) 37.5 x 37.5 x 5 mm


Length x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kgs/Cu.m.)
7.54 x 20.00 x 0.00035000000 x 7850.00 = 414.32 Kgs.

Cleats ( Main Truss) 75 x 75 x 6.35 (L)


Length x Number x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kgs/Cu.m.)
0.207 x 14.000 x 8.00 x 0.00091217750 x 7850.00 = - Kgs.

Cleats ( Rafter) 75 x 75 x 6.35 (L)


Length x Number x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kgs/Cu.m.)
0.050 x 14.000 x 6.00 x 0.00091217750 x 7850.00 = - Kgs.

Fascia Frame ( Web Members ) 25 x 4.00


Length x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kg/Cu.m. )
0.880 x 75.000 x 2.00 x 0.0001 x 7850.00 = 103.62 Kgs.
0.880 x 24.000 x 4.00 x 0.0001 x 7850.00 = 66.32 Kgs.
0.300 x 31.000 x 1.00 x 0.0001 x 7850.00 = 7.30 Kgs.
0.300 x 5.000 x 2.00 x 0.0001 x 7850.00 = 2.36 Kgs.

Fascia Frame ( Frame ) 25 x 25 x 5


Length x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kg/Cu.m. )
62.360 x 2.000 x 0.000225 x 7850.00 = 220.29 Kgs.
11.300 x 4.000 x 0.000225 x 7850.00 = 79.83 Kgs.
32.300 x 1.000 x 0.000225 x 7850.00 = 57.05 Kgs.
6.600 x 2.000 x 0.000225 x 7850.00 = 23.31 Kgs.

`` 8,370.57 Kgs.
PURLINS

Purlins 150 x 50 x 20 x 2 mm
Length x Quantity x Cross Sectional Area x Unit Weight of Steel ( 7850 kgs/Cu.m.)
30.30 x 40.00 x 0.000564 x 7850.00 = 5,366.01 Kgs.
15.85 x 9.00 x 0.000243 x 7850.00 = 272.11 Kgs.
5,638.12 Kgs.

ROOFING AND METAL ROOFING ACCESSORIES

Corrugated G.I. Sheet ( Length x Width x Quantity )


11.30 x 30.30 x 2.00 = 684.78 Sq.m.
3.00 x 15.85 x 1.00 = 47.55 Sq.m.
732.33 Sq.m.
Sagrod ( Length x Quantity x Number )
1.00 x 8.00 x 38.00 = 304.00 Pcs

Ridge Roll / Hip Roll = 30.30 L.m.

Gutter = 60.60 L.m.

Turn Buckle = 16.00 Pcs

Cross Bracing (16 mm dia Round Bar ) = 16.00 Pcs

Flashings = 127.65 L.m.

Bolts = 112.00 Pcs

GUSSET PLATES
Steel Plates ( Top of Column ) Length x Width x Thickness x Quantity x Unit Weight of Steel (7850 kg/Cu.m.)
0.30 x 0.30 x 0.012 x 10.00 x 7850.00 = 84.78 Kgs

Steel Plates ( Connection at Main Truss ) Length x Width x Thickness x Quantity x Unit Weight of Steel (7850 kg/Cu.m.)
0.30 x 0.40 x 0.012 x 10.00 x 7850.00 = 113.04 Kgs

Steel Plates ( Base Plate ) Length x Width x Thickness x Quantity x Unit Weight of Steel (7850 kg/Cu.m.)
0.30 x 0.40 x 0.012 x 3.00 x 7850.00 = 33.91 Kgs

Steel Plates ( Gusset Plates ) Length x Width x Thickness x Quantity x Unit Weight of Steel (7850 kg/Cu.m.)
0.20 x 0.25 x 0.00635 x 240.00 x 7850.00 = 598.17 Kgs
829.90 Kgs

SITE PREPARATION

Clearing and Grubbing - Length x Width


30.30 x 22.56 = 683.57 Sq.m.

Structure Excavation - Length x Width x Height


1.50 x 1.50 x 1.95 x 8.00 = 35.10 Cu.m.
0.30 x 0.25 x 72.00 = 5.40 Cu.m.
40.50 Cu.m.

Gravel Bedding - Length x Width x Height x Thickness


1.50 x 1.50 x 8.00 x 0.05 = 0.90 Cu.m.
0.10 x 0.25 x 84.00 = 2.10 Cu.m.
3.00 Cu.m.
Embankment from Structure Excavation ( Volume of Excavation - Volume of Structural Concrete )
40.50 - 14.12 = 26.38 Cu.m.
Embankment from Common Borrow - Length x Width x Thickness
0.39 x 0.80 x 27.00 x 2.00 = 16.85 Cu.m.
0.40 x 0.40 x 27.00 x 2.00 = 8.64 Cu.m.
16.00 x 28.00 x 0.29 = 129.92 Cu.m.
155.41 Cu.m.

FINISHING WORKS

Plaster Finish ( Length x Width x Quantity )


+
( 524.10 + 367.47 ) * 2.00 1783.14 sq.m.
1,783.14 sq.m.

Painting Works ( Length x Width x Quantity )


0.60 + 0.44
x 6.60 x 8.00 x 2.00 = 54.81 sq. m.
2.00

0.30 x 6.60 x 8.00 x 2.00 = 31.68 sq. m.


- sq. m.
+
Formworks and Falseworks ( Length x Width x Quantity )
0.60 + 0.44
x 6.60 x 8.00 x 1.00 = 27.46 sq. m.
2.00

0.30 x 6.60 x 8.00 x 1.00 = 15.84 sq. m.


43.30 sq. m.
8X8.5 BARANGAY HALL
CONSTRUCTION ESTIMATE

CONCRETE WORKS

COLUMNS(LENGTHXWIDTHXHEIGHTxNUMBER)

C1&C2 200X400
1ST FLOOR
0.2 X 0.4 X 4.7 X 10 = 3.76
2ND FLOOR
0.2 X 0.4 X 2.8 X 9= 2.016

STIFFENER COU0.15X0.15
0.15 X 0.15 X 1.3 X 10 = 0.2925

C3 250X350
0.25 X 0.35 X 7.55 X 4= 2.6425

8.711

FOOTING AND SLAB ON FILL


SLAB ON FILL
8.5 X 8 X 0.1 = 6.8

FOOTING
F1
1.8 X 1.8 X 0.3 X 10 = 9.72

F2
1.2 X 1.2 X 0.25 X 4= 1.44
17.96

FOOTING TIE BEAM HXWXL


FTB 200X300
0.2 X 0.3 X 48.13 X 1= 2.8878
WALL FOOTING
0.054 x 5.52 0.29808
3.19

BEAMS/GIRDERS
FB1,FB2,FB3,FB4
0.2 0.4 46.53 3.7224

FB5
0.2 0.3 18.85 1.131

ROOF BEAM
RB1&RB2
0.2 0.35 44.54 3.1178
7.97
SUSPENDED SLAB
8.5 X 8 X 0.125 = 8.5
minus stair BUTAS 1.8 2.65 4.77
3.73
1.4625 X 1 1.4625
CANOPY
0.6 1.8 6 0.1 0.648
0.8 0.6 2 0.1 0.096

5.94

FINISHING WORKS

CHB

1st floor
150 mm

whole area 2.82 x 24.98 = 70.4436


doors and windows (deduction) - 12.09
58.3536 sq.m.

100mm

whole area 2.82 x 14.93 = 42.1026


doors and windows (deduction) - 2.94
39.1626 sq.m.

2nd Floor
150 mm
whole area 2.4 x 25.03 = 60.072
doors and windows (deduction) - 13.83
46.242 sq.m.

100mm
whole area 2.4 x 7.66 = 18.384
doors and windows (deduction) - 1.26
17.124 sq.m.

150mm
parapet wall 1.3 27.25 35.425

150mm 140.02 sq.m.


100mm 56.29 sq.m.
TOTAL AREA 196.3072

PLASTER FINISH

CHB 196.3072
x 2 392.6144
COLUMNS
C3
1.2 X 5.63 X 4 27.024
C1 C2
1.2 X 5.63 X 10 67.56

BEAM 2ND FLOOR


0.8 X 65.38 52.304

Total Plaster Finish


539.5024 X 1.1 = 593.45 = Painting Works Masonry/ Concrete

unglazed Tiles
1.8 2.2 3.96
1.88 1.1 2.068
8 1.4 2 22.4

stair
1.88 2.9 2 10.904
39.33
GLAZED TILES
1st floor slab 46.25 46.25
2nd floor 47.19 47.19
cr1st f 6.56 1.8 11.808
c2nd 5.96 1.8 10.728
115.976
CEILING
68 68 SQM

SITE PREPARATION

Clearing and Grubbing - Length x Width


8 X 8.5 = 68 SQ.M.

ROOFING AND METAL ROOFING ACCESSORIES

Rib Type G.I. Sheet ( Length x Width x Quantity )


8.00 x 9.50 x 1.00
Purlins
Area
0.00015 + 0.000141 + 0.000045 = 0.000336
sq.m. pcs plus1 length(m) kg/m3
0.000336 x 12.00 x 8.00 x 7850.00 = 253.21

TRUSSES pcs
Area 0.00030 + 0.000264 + 0 = 0.000564
top chord
0.001128 x 4 x 9.33 x 7850 = 330.46
bottom chord
0.001128 4 9.29 7850 = 329.04

web member
Area 0.00032 + 0.000277178 + 0 = 0.000595
0.00119 x 4 x 11.72 x 7850 = 437.93

gusset plates pcs thickness

1097.44

BOLTS
AREA PCS LENGTH
0.00020096 32 0.3 7850 15.14

GUTTER 8 L.M.

FASCIA BOARD 8 L.M.

FLASHING 27 L.M.

STEEL PLATES
Gusset plate
2.5999 4 0.00635 7850 518.39
steel plate 0.0006 8 7850 37.68
556.07

REBAR WORKS

Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm. dia


1.80 x 20.00 x 10.00 x 1.58
1.20 x 12.00 x 4.00 x 1.58

Wall Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia


6.06 x 10.00 x 1.00 x 0.617
Wall Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia
5.52 x 2.00 x 1.00 x 0.617 x 1.00

Footing Tie Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Stirrups

1.00 x 20.00 x 2.00 x 0.617


1.00 x 21.00 x 3.00 x 0.617
1.00 x 31.00 x 1.00 x 0.617
1.00 x 2.00 x 1.00 x 0.617
1.00 x 16.00 x 1.00 x 0.617
1.00 x 17.00 x 1.00 x 0.617
1.00 x 20.00 x 1.00 x 0.617
1.00 x 20.00 x 1.00 x 0.617
1.00 x 14.00 x 2.00 x 0.617
1.00 x 14.00 x 2.00 x 0.617
1.00 x 21.00 x 1.00 x 0.617
1.00 x 27.00 x 2.00 x 0.617
1.00 x 28.00 x 1.00 x 0.617

Footing Tie Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm.dia/Main Bars
8.50 x 4.00 x 3.00 x 1.00 x 1.580
8.00 x 4.00 x 3.00 x 1.00 x 1.580
3.00 x 4.00 x 1.00 x 1.00 x 1.580

Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Stirrups


FB1
1.20 x 31.00 x 1.00 x 0.617
FB2
1.20 x 31.00 x 1.00 x 0.617
1.20 x 26.00 x 1.00 x 0.617
1.20 x 21.00 x 1.00 x 0.617
1.20 x 21.00 x 1.00 x 0.617
1.20 x 17.00 x 1.00 x 0.617
1.20 x 19.00 x 1.00 x 0.617
FB3
1.20 x 21.00 x 1.00 x 0.617
1.20 x 26.00 x 1.00 x 0.617
1.20 x 20.00 x 2.00 x 0.617
1.20 x 21.00 x 1.00 x 0.617
1.20 x 20.00 x 1.00 x 0.617
1.20 x 18.00 x 1.00 x 0.617
FB4
1.20 x 14.00 x 2.00 x 0.617
1.20 x 14.00 x 2.00 x 0.617
FB5
1.00 x 21.00 x 3.00 x 0.617
1.00 x 28.00 x 2.00 x 0.617
1.00 x 21.00 x 1.00 x 0.617

Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm.dia/Main Bars


FB1
5.00 x 8.00 x 1.00 x 1.580
FB2
5.00 x 6.00 x 1.00 x 1.580
8.00 x 6.00 x 1.00 x 1.580
3.00 x 6.00 x 1.00 x 1.580
4.15 x 6.00 x 1.00 x 1.580

FB3
3.00 x 5.00 x 1.00 x 1.580
8.00 x 5.00 x 1.00 x 1.580
2.85 x 5.00 x 2.00 x 1.580
4.15 x 5.00 x 1.00 x 1.580

FB4
1.50 x 5.00 x 4.00 x 1.580

FB5
4.15 x 4.00 x 2.00 x 1.580
3.00 x 4.00 x 1.00 x 1.580

Column ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm.dia/Main Bars


8.30 x 8.00 x 9.00 x 1.580
4.70 x 8.00 x 1.00 x 1.580
8.30 x 6.00 x 4.00 x 1.580

Column ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Lateral Ties


1st floor
1.20 x 10.00 x 39.00 x 0.617
1.20 x 4.00 x 39.00 x 0.617

2nd floor
1.20 x 9.00 x 26.00 x 0.617
1.20 x 4.00 x 26.00 x 0.617

SOF ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Along X


8.00 x 15.00 x 1.00 x 0.617

SOF ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Along Y


8.50 x 14.00 x 1.00 x 0.617
SUSPENDED SLAB ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 12 mm.dia
discontinue
ALONG SHORT SPAN
s1 ( L/3 x pieces xtheoretical weight
0.85 x 14.00 x 0.89
0.93 x 10.00 x 0.89

s2 ( L/3 x pieces xtheoretical weight


0.85 x 10.00 x 0.89

s3 ( L/3 x pieces xtheoretical weight


0.48 x 9.00 x 0.89
0.48 x 10.00 x 0.89
0.33 x 10.00 x 0.89
0.27 x 9.00 x 0.89
0.48 x 7.00 x 0.89

ALONG LONG SPAN


s1 ( L/3 x pieces xtheoretical weight
1.35 x 9.00 x 0.89
1.35 x 7.00 x 0.89
0.95 x 10.00 x 0.89

s3 ( L/3 x pieces xtheoretical weight


0.81 x 5.00 x 0.89
0.93 x 5.00 x 0.89
0.93 x 4.00 x 0.89

CONTINUES
1.75 x 27.00 x 0.89
1.83 x 27.00 x 0.89
1.75 x 18.00 x 0.89
1.17 x 18.00 x 0.89
1.74 x 5.00 x 0.89
1.90 x 5.00 x 0.89

2.43 x 17.00 x 0.89


2.43 x 14.00 x 0.89
1.48 x 10.00 x 0.89
1.42 x 3.00 x 0.89
1.56 x 9.00 x 0.89
1.56 x 7.00 x 0.89
1.56 x 10.00 x 0.89

BOTTOM BARS
along short span
s1 ( Total l x pieces xtheoretical weight
1.615 x 17.00 x 0.888
1.26 x 17.00 x 0.888
1.770 x 12.00 x 0.888
s2 ( L/3 x pieces xtheoretical weight
1.62 x 14.00 x 0.888
1.26 x 14.00 x 0.888

s3 ( L/3 x pieces xtheoretical weight


0.91 x 17.00 x 0.888
0.91 x 14.00 x 0.888
0.91 x 19.00 x 0.888
0.51 x 18.00 x 0.888
0.63 x 19.00 x 0.888
along long span
s1 ( Total l x pieces xtheoretical weight
2.570 x 34.00 x 0.888
2.57 x 28.00 x 0.888
1.810 x 38.00 x 0.888

s2 ( L/3 x pieces xtheoretical weight


1.59 x 13.00 x 0.888
1.59 x 11.00 x 0.888

s3 ( L/3 x pieces xtheoretical weight


1.62 x 5.00 x 0.888
1.26 x 5.00 x 0.888
1.77 x 5.00 x 0.888
1.59 x 3.00 x 0.888
1.77 x 3.33 x 0.888

STAIRS Reinforcement
length no
0.51 4.00 16.00 0.617
6.17 4.00 1.00 0.617
1.00 50.00 1.00 0.617
1.00 48.00 1.00 0.617

EARTHWORKS

GRAVEL FILL
1.80 1.80 0.10 10.000
1.20 1.20 0.10 4.000
8.00 8.50 0.10 1.000

Structure EXCAVATION
1.80 1.80 1.50 10.000
1.20 1.20 1.50 4.000
EMBANKMENT FROM STRUCTURE EXCAV

EMBANKMENT FROM BORROW


1.80 1.80 0.30 10.000
1.20 1.20 0.25 4.000
0.20 0.40 1.20 10.000
0.25 0.35 1.25 4.000

8.50 x 8.00 x 0.20

13.6 - 12.56 =

68 593.63 40,366.84

window 1 window 2
1.8 0.6
1.2 0.7
2.16 0.42
x 10 3
21.6 + 1.26
total 22.86
8.85

7.55

cu.m.

cu.m.

AREA TRAPEZOID
0.54
0.27
0.054

cu.m.

LENGTH
FB1 4.9
FB2 18.35
FB3 18.56
FB4 4.72
FB5 18.85
65.38
RB1 36.64
cu.m. RB2 7.9

SUSPENDED SLAB + CANOPY


4.48

1st floor
150mm
LENGTH WALL area no. total area
1ST FLOOR 150 mm d1 1.89 1 1.89
24.98 d2 1.68 1 1.68
1ST FLOOR 100 mm d3 1.26 0 0
0
14.93 w1 1.92 4 7.68
w2 0.42 2 0.84
12.09
2ND Floor 150 MM
25.03

100mm
7.66

parapet length
27.25
ks Masonry/ Concrete

ORIES

= 76.00 Sq.m.
kg

0.015
0.001128

kg

kg

0.001189
kg

1 0.3002
2 0.3677
kg 3 0.228
4 0.2352
5 0.2667
6 0.2669
kg 7 0.2714
8 0.3924
9 0.2714

9 0.2714
2.5999

kg
kg
kg

= 568.80 Kgs
= 91.01 Kgs

) - 10 mm.dia
= 37.39 Kgs 9.2
) - 10 mm.dia
= 6.81 Kgs

ight ) - 10 mm.dia/Stirrups LENGTH OF FTB NO. OF STIRRUPS


SPACING m
= 24.68 Kgs 2.45 m 0.05 0.1
= 38.87 Kgs 2.7 m No: 1 6
= 19.13 Kgs 4.7 m X2 2 12
= 1.23 Kgs 2.73 m LENGTH 4.05 0.1 1.2
= 9.87 Kgs 1.68 m
= 10.49 Kgs 1.9 m 2.85
= 12.34 Kgs 2.43 m 14.25
= 12.34 Kgs 2.4 m
= 17.28 Kgs 1.13 m
= 17.28 Kgs 1.23 m
= 12.96 Kgs 2.65 m
= 33.32 Kgs 3.75 m
= 17.28 Kgs 4.05 m

ight ) - 16 mm.dia/Main Bars


= 161.16 Kgs
= 151.68 Kgs
= 18.96 Kgs

m.dia/Stirrups LENGTH BEAM NO. OF STIRRUPS


SPACING m
= 22.95 Kgs 4.8 m 0.05 0.1
m No: 1 2
= 22.95 Kgs 4.7 m X2 2 4
= 19.25 Kgs 3.75 m LENGTH 1.23 0.1 0.4
= 15.55 Kgs 2.8 m
= 15.55 Kgs 2.7 m 2.85
= 12.59 Kgs 1.9 m 14.25
= 14.07 Kgs 2.4 m

= 15.55 Kgs 2.7 m


= 19.25 Kgs 3.75 m
= 29.62 Kgs 2.45 m
= 15.55 Kgs 2.73 m
= 14.81 Kgs 2.43 m
= 13.33 Kgs 2.05

= 20.73 Kgs 1.13 NO. OF STIRRUPS


= 20.73 Kgs 1.23 SPACING m
0.05 0.1
= 38.87 Kgs 2.65 No: 1 2
= 34.55 Kgs 4.05 X2 2 4
= 12.96 Kgs 2.8 LENGTH 2.8 0.1 0.4

2.85
m.dia/Main Bars 14.25

= 63.20 Kgs

= 47.40 Kgs
= 75.84 Kgs
= 28.44 Kgs
= 39.34 Kgs

= 23.70 Kgs
= 63.20 Kgs
= 45.03 Kgs
= 32.79 Kgs

= 47.40 Kgs

= 52.46 Kgs
= 18.96 Kgs

mm.dia/Main Bars NO. OF LATERAL TIES


= 944.21 Kgs SPACING m
= 59.41 Kgs 0.05 0.1
= 314.74 Kgs No: 2 3
X2 4 6
mm.dia/Lateral Ties LENGTH 2.8 0.2 0.6

= 288.76 Kgs
= 115.50 Kgs 2.85

= 173.25 Kgs
= 77.00 Kgs 2.85

14.25
m.dia/Along X
= 74.04 Kgs 13.33333

m.dia/Along Y
= 73.42 Kgs
Weight ) - 12 mm.dia 4.766667

= 10.57 Kgs 13.5


= 8.29 Kgs 9.5

= 7.55 Kgs 9.5

= 3.81 Kgs 8.1


= 4.23 Kgs 9.333333
= 2.96 Kgs 9.333333
= 2.13 Kgs 8.833333
= 2.96 Kgs 7

= 10.79 Kgs 8.5


= 8.39 Kgs 7
= 8.44 Kgs 9.333333

= 3.60 Kgs 4.766667


= 4.14 Kgs 4.766667
= 3.32 Kgs 3.333333

= 41.96 Kgs 27
= 43.96 Kgs 27
= 27.97 Kgs 17.66667
= 18.65 Kgs 17.66667
= 7.74 Kgs 4.766667
= 8.44 Kgs 4.766667

= 36.73 Kgs 17
= 30.25 Kgs 14
= 13.17 Kgs 9.333333
= 3.77 Kgs 2.666667
= 12.47 Kgs 8.1
= 9.70 Kgs 7
= 13.85 Kgs 9.333333

L L/6 L/5
= 24.38 Kgs 13.5 2.55 0.425 0.51
= 19.02 Kgs 9.5 2.1 0.42 0.42
= 18.86 Kgs 2.8 0.466667 0.56
= 20.08 Kgs 9.5 2.55 0.425 0.51
= 15.66 Kgs 9.5 2.1 0.42 0.42

= 13.74 Kgs 8.1 1.43 0.238333 0.286


= 11.31 Kgs 9.333333 1.43 0.238333 0.286
= 15.35 Kgs 9.333333 1.43 0.238333 0.286
= 8.15 Kgs 8.833333 0.8 0.133333 0.16
= 10.63 Kgs 7 1 0.166667 0.2

L L/6 L/5
= 77.59 Kgs 13.5 4.05 0.675 0.81
= 63.90 Kgs 9.5 4.05 0.675 0.81
= 61.08 Kgs 2.85 0.475 0.57

= 18.35 Kgs 9.5 2.65 0.53 0.53


= 15.53 Kgs 9.5 2.65 0.53 0.53

= 7.19 Kgs 8.1 2.55 0.425 0.51


= 5.59 Kgs 9.333333 2.1 0.42 0.42
= 7.86 Kgs 9.333333 2.8 0.466667 0.56
= 4.24 Kgs 8.833333 2.65 0.53 0.53
= 5.23 Kgs 7 2.8 0.466667 0.56

= 20.14 Kgs
= 15.23 Kgs REMEMBER
= 30.85 Kgs 49.36 THEORETICAL WEIGHT
= 29.62 Kgs 0.006167 (d)(d) IN mm

5,149.25 Kgs

= 3.24 CU.M
= 0.58 CU.M
= 6.80 CU.M
10.62 CU.M

= 48.60 CU.M
= 8.64 CU.M
57.24
57.24

= 9.72 CU.M
= 1.44 CU.M
= 0.96 CU.M
= 0.44 CU.M
12.56
= 13.6

1.04
1st floor 2nd floor
100mm 150mm 100mm
total area no. total are no. total area no. total area
0 1 1.89 0
1 1.68 0 0
1 1.26 0 1 1.26
0 0 0
0 6 11.52 0
0 1 0.42 0
2.94 13.83 1.26
O. OF STIRRUPS

0.2
13.75
14 SAY 30

O. OF STIRRUPS

0.15 0.2
3 -0.85
6 -1 SAY 13
0.9

O. OF STIRRUPS

0.15 0.2
3 7
6 7 SAY 21
0.9

OF LATERAL TIES

0.15
13.33333
0 14 SAY 26
0
TOTAL L
1.62 16.2
1.26 16.2
1.77 11.4
1.62 13.25
1.26 13.25

0.91 17
0.91 14
0.91 18.6667
0.51 17.6667
0.63 18.6667

TOTAL L
2.57 34
2.57 28
1.81 37.3333

1.59 12.75
1.59 10.5

1.62 4.76667
1.26 4.76667
1.77 4.76667
1.59 2.66667
1.77 3.33333
8X8.5 BARANGAY HALL
CONSTRUCTION ESTIMATE

CONCRETE WORKS

COLUMNS(LENGTHXWIDTHXHEIGHTxNUMBER)

C1,C2,C3, C4 250X350
1ST FLOOR
0.25 X 0.35 X 5.3 X 15 =
2ND FLOOR
0.25 X 0.35 X 2.8 X 15 =

STIFFENER COULMN 0.15X0.15


0.15 X 0.15 X 1.3 X 10 =

FOOTING AND SLAB ON FILL


SLAB ON FILL
8.5 X 8 X 0.1 =
ramp
5.97 1.2 0.1 =
KITCHEN SINK
1ST
1.8 X 0.63 X 0.1
0.78 X 0.6 X 0.1
2ND
1.88 0.6 0.1

FOOTING
F1
1.25 X 1.25 X 0.3 X 4=

F2
1.75 X 1.75 X 0.3 X 4=
f3
2.2 2.2 0.3 6

FOOTING TIE BEAM HXWXL


FTB 200X300
0.2 X 0.3 X 48.13 X 1=
WALL FOOTING
0.054 x 5.52
BEAMS/GIRDERS
FB1,FB2,FB3,FB4
0.2 0.4 46.53

FB5
0.2 0.3 18.85

ROOF BEAM
RB1&RB2
0.2 0.35 44.54

SUSPENDED SLAB
8.5 X 8 X 0.125 =
minus stair BUTAS
1.8 X 2.65 0.125
stair
1.4625 X 1
CANOPY
0.6 1.8 6 0.1
0.8 0.6 2 0.1

FINISHING WORKS

CHB

1st floor
150 mm

whole area 2.82 x 24.98 = 70.4436


doors and windows (deduction) - 12.09
58.35 sq.m.

100mm

whole area 2.82 x 14.93 = 42.1026


doors and windows (deduction) - 2.94
39.16 sq.m.

2nd Floor
150 mm
whole area 2.4 x 25.03 = 60.072
doors and windows (deduction) - 13.83
46.24 sq.m.

100mm
whole area 2.4 x 7.66 = 18.384
doors and windows (deduction) - 1.26
17.12 sq.m.

150mm
parapet wall 1.3 27.25 35.425

150mm 140.02 sq.m.


100mm 56.28 sq.m.
TOTAL AREA 196.295

PLASTER FINISH

CHB 196.295
x 2 392.59
COLUMNS
C3
1.2 X 5.63 X 4 27.024
C1 C2
1.2 X 5.63 X 10 67.56

BEAM 2ND FLOOR


0.8 X 65.38 52.304

Total Plaster Finish


539.478 X 1.1 = 593.43 total plaster Finish
68
661.43 = Painting Works Masonry
unglazed Tiles
c.r.
1.8 2.2 3.96
1.88 1.1 2.068
6.03

Stair 0

GLAZED TILES

cr1st f 6.56 1.8 11.808


c2nd 5.96 1.8 10.728
working table 2.73
25.27

CEILING
68 68 SQM

SITE PREPARATION

Clearing and Grubbing - Length x Width


8 X 8.5 = 68 SQ.M.

ROOFING AND METAL ROOFING ACCESSORIES

Rib Type G.I. Sheet ( Length x Width x Quantity )


8.00 x 9.50 x 1.00

Purlins
Area
0.00015 + 0.000141 + 0.000045 =
sq.m. pcs plus1 length(m) kg/m3
0.000336 x 12.00 x 8.00 x 7850.00 =

TRUSSES pcs
Area 0.00030 + 0.000264 + 0 =
top chord
0.001128 x 4 x 9.33 x 7850 =
bottom chord
0.001128 4 9.29 7850 =

web member
Area 0.00032 + 0.000277178 + 0 =
0.00119 x 4 x 11.72 x 7850 =

BOLTS
AREA PCS LENGTH
0.00020096 32 0.3 7850

GUTTER 8 L.M.

FASCIA BOARD 8 L.M.

FLASHING 27 L.M.
STEEL PLATES
Gusset plate
2.5999 4 0.00635 7850
steel plate 0.0006 8 7850

REBAR WORKS

Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm. dia


1.75 x 18.00 x 4.00 x 1.58
1.25 x 12.00 x 4.00 x 1.58
2.20 22.00 6.00 1.58

Wall Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia


6.06 x 10.00 x 1.00 x 0.617

Wall Footing ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia


5.52 x 2.00 x 1.00 x 0.617 x

Footing Tie Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Stirrups

1.00 x 20.00 x 2.00 x 0.617


1.00 x 21.00 x 3.00 x 0.617
1.00 x 31.00 x 1.00 x 0.617
1.00 x 2.00 x 1.00 x 0.617
1.00 x 16.00 x 1.00 x 0.617
1.00 x 17.00 x 1.00 x 0.617
1.00 x 20.00 x 1.00 x 0.617
1.00 x 20.00 x 1.00 x 0.617
1.00 x 14.00 x 2.00 x 0.617
1.00 x 14.00 x 2.00 x 0.617
1.00 x 21.00 x 1.00 x 0.617
1.00 x 27.00 x 2.00 x 0.617
1.00 x 28.00 x 1.00 x 0.617

Footing Tie Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm.dia/Main Bars
8.50 x 4.00 x 3.00 x 1.00 x
8.00 x 4.00 x 3.00 x 1.00 x
3.00 x 4.00 x 1.00 x 1.00 x

Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Stirrups


FB1
1.20 x 31.00 x 1.00 x 0.617
FB2
1.20 x 31.00 x 1.00 x 0.617
1.20 x 26.00 x 1.00 x 0.617
1.20 x 21.00 x 1.00 x 0.617
1.20 x 21.00 x 1.00 x 0.617
1.20 x 17.00 x 1.00 x 0.617
1.20 x 19.00 x 1.00 x 0.617
FB3
1.20 x 21.00 x 1.00 x 0.617
1.20 x 26.00 x 1.00 x 0.617
1.20 x 20.00 x 2.00 x 0.617
1.20 x 21.00 x 1.00 x 0.617
1.20 x 20.00 x 1.00 x 0.617
1.20 x 18.00 x 1.00 x 0.617
FB4
1.20 x 14.00 x 2.00 x 0.617
1.20 x 14.00 x 2.00 x 0.617
FB5
1.00 x 21.00 x 3.00 x 0.617
1.00 x 28.00 x 2.00 x 0.617
1.00 x 21.00 x 1.00 x 0.617

Beam ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm.dia/Main Bars


FB1
5.00 x 8.00 x 1.00 x 1.580
FB2
5.00 x 6.00 x 1.00 x 1.580
8.00 x 6.00 x 1.00 x 1.580
3.00 x 6.00 x 1.00 x 1.580
4.15 x 6.00 x 1.00 x 1.580

FB3
3.00 x 5.00 x 1.00 x 1.580
8.00 x 5.00 x 1.00 x 1.580
2.85 x 5.00 x 2.00 x 1.580
4.15 x 5.00 x 1.00 x 1.580

FB4
1.50 x 5.00 x 4.00 x 1.580

FB5
4.15 x 4.00 x 2.00 x 1.580
3.00 x 4.00 x 1.00 x 1.580

Column ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 16 mm.dia/Main Bars


8.90 x 6.00 x 4.00 x 1.580
6.10 x 8.00 x 1.00 x 1.580
8.90 x 8.00 x 5.00 x 1.580
8.90 x 8.00 x 4.00 x 1.580
Column ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Lateral Ties
1st floor
1.20 x 10.00 x 45.00 x 0.617
1.20 x 4.00 x 45.00 x 0.617

2nd floor
1.20 x 9.00 x 26.00 x 0.617
1.20 x 4.00 x 26.00 x 0.617

SOF ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Along X


8.00 x 15.00 x 1.00 x 0.617

SOF ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 10 mm.dia/Along Y


8.50 x 14.00 x 1.00 x 0.617

SUSPENDED SLAB ( Length of Reinforcement x Quantity x Number x Theoretical Weight ) - 12 mm.dia


discontinue
ALONG SHORT SPAN
s1 ( L/3 x pieces xtheoretical weight
0.85 x 14.00 x 0.89
0.93 x 10.00 x 0.89

s2 ( L/3 x pieces xtheoretical weight


0.85 x 10.00 x 0.89

s3 ( L/3 x pieces xtheoretical weight


0.48 x 9.00 x 0.89
0.48 x 10.00 x 0.89
0.33 x 10.00 x 0.89
0.27 x 9.00 x 0.89
0.48 x 7.00 x 0.89

ALONG LONG SPAN


s1 ( L/3 x pieces xtheoretical weight
1.35 x 9.00 x 0.89
1.35 x 7.00 x 0.89
0.95 x 10.00 x 0.89

s3 ( L/3 x pieces xtheoretical weight


0.81 x 5.00 x 0.89
0.93 x 5.00 x 0.89
0.93 x 4.00 x 0.89

CONTINUES
1.75 x 27.00 x 0.89
1.83 x 27.00 x 0.89
1.75 x 18.00 x 0.89
1.17 x 18.00 x 0.89
1.74 x 5.00 x 0.89
1.90 x 5.00 x 0.89

2.43 x 17.00 x 0.89


2.43 x 14.00 x 0.89
1.48 x 10.00 x 0.89
1.42 x 3.00 x 0.89
1.56 x 9.00 x 0.89
1.56 x 7.00 x 0.89
1.56 x 10.00 x 0.89

BOTTOM BARS
along short span
s1 ( Total l x pieces xtheoretical weight
1.615 x 17.00 x 0.888
1.26 x 17.00 x 0.888
1.770 x 12.00 x 0.888

s2 ( L/3 x pieces xtheoretical weight


1.62 x 14.00 x 0.888
1.26 x 14.00 x 0.888

s3 ( L/3 x pieces xtheoretical weight


0.91 x 17.00 x 0.888
0.91 x 14.00 x 0.888
0.91 x 19.00 x 0.888
0.51 x 18.00 x 0.888
0.63 x 19.00 x 0.888
along long span
s1 ( Total l x pieces xtheoretical weight
2.570 x 34.00 x 0.888
2.57 x 28.00 x 0.888
1.810 x 38.00 x 0.888

s2 ( L/3 x pieces xtheoretical weight


1.59 x 13.00 x 0.888
1.59 x 11.00 x 0.888

s3 ( L/3 x pieces xtheoretical weight


1.62 x 5.00 x 0.888
1.26 x 5.00 x 0.888
1.77 x 5.00 x 0.888
1.59 x 3.00 x 0.888
1.77 x 3.33 x 0.888

STAIRS Reinforcement
length no
0.51 4.00 16.00 0.617
6.17 4.00 1.00 0.617
1.00 50.00 1.00 0.617
1.00 48.00 1.00 0.617

ramp reinforcement 10 mm
1.20 x 16.00 x 1.00 x 0.617
5.97 x 4.00 x 1.00 x 0.617

EARTHWORKS

GRAVEL FILL
1.25 1.25 0.10 4.000
1.75 1.75 0.10 4.000
2.20 2.20 0.10 6.000
8.00 8.50 0.05 1.000
1.20 6.00 0.10 1.000
2.40 1.20 0.10 1.000

Structure EXCAVATION
1.25 1.25 2.00 4.000
1.75 1.75 2.00 4.000
2.20 2.20 2.00 6.000
Septic Vault hukay
2.4 1.2 1.8

EMBANKMENT FROM STRUCTURE EXCAV

nahukay para sa footing =


Ibawas mo 'to sa nahukay para sa footing
1.25 1.25 0.30 4.000
1.75 1.70 0.30 4.000
2.20 2.20 0.30 6.000

0.25 0.35 1.70 14.000

8.50 x 8.00 x 0.30


EMBANKMENT FROM STRUCTURE EXCAV

EMBANKMENT FROM BORROW 99.24 -

ramp area
1.25 x 0.28 0.35
0.5 3.22 0.28 0.4508
0.4508 x

68 593.63 40,366.84

window 1 window 2
1.8 0.6
1.2 0.7
2.16 0.42
x 10 3
21.6 + 1.26
total 22.86

RAILING
STAIRS
2'DIA. STAINLESS PIPE RAILING
7.48 M

2'' STAINLESS SQUARE TUBE VERTICAL MEMBER


0.92 X 4 = 3.68 M

5/8'' DIA. STAINLESS PLAIN ROUND BAR INTERMEDIATE MEMBER SPACED AT 0.10 M
4.43 X 7 = 31.01 M

HALLWAY
2'' X 3'' TUBULAR PIPE RAILING
2.43 + 2.73 =
2.43 + 2.1 + 2.73 =

2" X 6 MM FLAT BAR VERTICAL MEMBER


1ST FLOOR 0.9 X 8 = 7.2
2ND FLOOR 0.9 X 12 = 10.8

5/8'' DIA. PLAIN ROUND BAR INTERMEDIATE MEMBER


1ST FLOOR 1.06 X 14 = 14.84
1.21 X 14 = 16.94
2ND FLOOR 1.06 X 14 = 14.84
0.9 X 14 = 12.6
1.21 X 14 = 16.94
76.16

RAMP
38MM DIA. STAINLESS SLEEL PIPE HANDRAIL W/ 38 MM DIA. VERTICAL SS. PIPE SUPPORT
SPACED @ 600 MM. O.C.

6.19 X 2.00 = 12.38


0.37 X 1 0.37
0.9 X 11 9.9
22.65
X 2
45.3
STAIRS
2.51
0.26
2.25
0.4
5.42

STAIR NOSING
16 PCS.

GRILLS
12 mm SQUARE PLAIN BAR W/ 2 '' W/ 6 mm FLAT BAR STUD
1.6 X 1.2 X 10 =
0.6 X 0.7 X 3=

painting works wood


cabinet 1
0.7 0.7 1
cab2
0.7 0.9 1
cab3
0.7 0.82 3

doors
1 2.1 4 2

ceiling
8 8.5
SEPTIC VAULT
4.8 + 3.6 X 1.8 =
8.4 X 1.8 = 15.12 X
E

8.85

7.55
6.95625

3.675

0.2925

10.92 cu.m.

6.8

0.7164

0.1134
0.0468

0.1128

1.875

3.675

8.712
22.05 cu.m.

AREA TRAPEZOID
0.54
2.8878 0.27
0.054
0.29808
3.19 cu.m.
LENGTH
FB1 4.9
3.7224 FB2 18.35
FB3 18.56
FB4 4.72
1.131 FB5 18.85
65.38

3.1178 RB1 36.64


7.97 cu.m. RB2 7.9

8.5

0.59625
7.90375
1.4625

0.648
0.096
SUSPENDED SLAB + CANOPY
8.65
10.11

LENGTH WALL area


1ST FLOOR 150 mm d1 1.89
24.98 d2 1.68
1ST FLOOR 100 mm d3 1.26

14.93 w1 1.92
w2 0.42

2ND Floor 150 MM


25.03

100mm
7.66
parapet length
27.25

total plaster Finish

= Painting Works Masonry/ Concrete


CESSORIES

= 76.00 Sq.m.

0.000336

253.21 kg

0.015
0.000564 0.001128

330.46 kg

329.04 kg

0.000595 0.001189
437.93 kg

1 0.3002
2 0.3677
1097.44 kg 3 0.228
4 0.2352
5 0.2667
6 0.2669
15.14 kg 7 0.2714
8 0.3924
9 0.2714

9 0.2714
2.5999
2

518.39 kg
37.68 kg
556.07 kg

= 199.08 Kgs
= 94.80 Kgs
= 458.83 Kgs

= 37.39 Kgs 9.2

1.00 = 6.81 Kgs

) - 10 mm.dia/Stirrups LENGTH OF FTB NO. OF STI

= 24.68 Kgs 2.45 m


= 38.87 Kgs 2.7 m No:
= 19.13 Kgs 4.7 m X2
= 1.23 Kgs 2.73 m LENGTH 4.05
= 9.87 Kgs 1.68 m
= 10.49 Kgs 1.9 m 2.85
= 12.34 Kgs 2.43 m 14.25
= 12.34 Kgs 2.4 m
= 17.28 Kgs 1.13 m
= 17.28 Kgs 1.23 m
= 12.96 Kgs 2.65 m
= 33.32 Kgs 3.75 m
= 17.28 Kgs 4.05 m

) - 16 mm.dia/Main Bars
1.580 = 161.16 Kgs
1.580 = 151.68 Kgs
1.580 = 18.96 Kgs

LENGTH BEAM NO. OF STI

= 22.95 Kgs 4.8 m


m No:
= 22.95 Kgs 4.7 m X2
= 19.25 Kgs 3.75 m LENGTH 1.23
= 15.55 Kgs 2.8 m
= 15.55 Kgs 2.7 m 2.85
= 12.59 Kgs 1.9 m 14.25
= 14.07 Kgs 2.4 m

= 15.55 Kgs 2.7 m


= 19.25 Kgs 3.75 m
= 29.62 Kgs 2.45 m
= 15.55 Kgs 2.73 m
= 14.81 Kgs 2.43 m
= 13.33 Kgs 2.05

= 20.73 Kgs 1.13 NO. OF STI


= 20.73 Kgs 1.23

= 38.87 Kgs 2.65 No:


= 34.55 Kgs 4.05 X2
= 12.96 Kgs 2.8 LENGTH 2.8

2.85
a/Main Bars 14.25

= 63.20 Kgs

= 47.40 Kgs
= 75.84 Kgs
= 28.44 Kgs
= 39.34 Kgs

= 23.70 Kgs
= 63.20 Kgs
= 45.03 Kgs
= 32.79 Kgs

= 47.40 Kgs

= 52.46 Kgs
= 18.96 Kgs

dia/Main Bars NO. OF LATE


= 337.49 Kgs
= 77.10 Kgs
= 562.48 Kgs No:
= 449.98 Kgs X2
dia/Lateral Ties LENGTH 2.8

= 333.18 Kgs
= 133.27 Kgs 2.85

= 173.25 Kgs
= 77.00 Kgs 2.85

14.25

= 74.04 Kgs 13.33333

= 73.42 Kgs

ht ) - 12 mm.dia 4.766667

= 10.57 Kgs 13.5


= 8.29 Kgs 9.5

= 7.55 Kgs 9.5

= 3.81 Kgs 8.1


= 4.23 Kgs 9.333333
= 2.96 Kgs 9.333333
= 2.13 Kgs 8.833333
= 2.96 Kgs 7

= 10.79 Kgs 8.5


= 8.39 Kgs 7
= 8.44 Kgs 9.333333

= 3.60 Kgs 4.766667


= 4.14 Kgs 4.766667
= 3.32 Kgs 3.333333

= 41.96 Kgs 27
= 43.96 Kgs 27
= 27.97 Kgs 17.66667
= 18.65 Kgs 17.66667
= 7.74 Kgs 4.766667
= 8.44 Kgs 4.766667

= 36.73 Kgs 17
= 30.25 Kgs 14
= 13.17 Kgs 9.333333
= 3.77 Kgs 2.666667
= 12.47 Kgs 8.1
= 9.70 Kgs 7
= 13.85 Kgs 9.333333

L
= 24.38 Kgs 13.5 2.55
= 19.02 Kgs 9.5 2.1
= 18.86 Kgs 2.8

= 20.08 Kgs 9.5 2.55


= 15.66 Kgs 9.5 2.1

= 13.74 Kgs 8.1 1.43


= 11.31 Kgs 9.333333 1.43
= 15.35 Kgs 9.333333 1.43
= 8.15 Kgs 8.833333 0.8
= 10.63 Kgs 7 1

L
= 77.59 Kgs 13.5 4.05
= 63.90 Kgs 9.5 4.05
= 61.08 Kgs 2.85

= 18.35 Kgs 9.5 2.65


= 15.53 Kgs 9.5 2.65

= 7.19 Kgs 8.1 2.55


= 5.59 Kgs 9.333333 2.1
= 7.86 Kgs 9.333333 2.8
= 4.24 Kgs 8.833333 2.65
= 5.23 Kgs 7 2.8

= 20.14 Kgs
= 15.23 Kgs REMEMBER
= 30.85 Kgs 49.36 THEORETICAL WEIGHT
= 29.62 Kgs 0.006167 (d)(d)

= 11.85 Kgs
= 14.73 Kgs

5,439.61 Kgs

= 0.63 CU.M f1
= 1.23 CU.M f2
= 2.90 CU.M f3
= 3.40 CU.M slab
0.72 ramp
0.29 septic
9.17 CU.M

= 12.50 CU.M
= 24.50 CU.M
58.08
95.08
+ 5.18
100.26

68
-
95.08

= 1.88 CU.M 16.24


3.57 20.4
8.71 78.84
99.24
= 2.08 CU.M

16.24
78.84

= 20.4
FROM STRUCTURE EXCAV = 99.24

95.08 = 4.16
length
1.2
+ 0.54096
4.70

5.16
7.26
19.2
1.26
20.46

0.49

0.63

1.722
2.842

16.8

68
87.64
12.5 = 189
1st floor 2nd floor
150mm 100mm 150mm 100mm
no. total area no. total are no. total area no. total area
1 1.89 0 1 1.89 0
1 1.68 1 1.68 0 0
0 0 1 1.26 0 1 1.26
0 0 0 0
4 7.68 0 6 11.52 0
2 0.84 0 1 0.42 0
12.09 2.94 13.83 1.26
NO. OF STIRRUPS
SPACING m
0.05 0.1 0.2
1 6 13.75
2 12 14 SAY 30
0.1 1.2

NO. OF STIRRUPS
SPACING m
0.05 0.1 0.15 0.2
1 2 3 -0.85
2 4 6 -1 SAY 13
0.1 0.4 0.9

NO. OF STIRRUPS
SPACING m
0.05 0.1 0.15 0.2
1 2 3 7
2 4 6 7 SAY 21
0.1 0.4 0.9

NO. OF LATERAL TIES


SPACING m
0.05 0.1 0.15
2 3 13.33333
4 6 0 14 SAY 26
0.2 0.6 0
L/6 L/5 TOTAL L
0.425 0.51 1.62 16.2
0.42 0.42 1.26 16.2
0.466667 0.56 1.77 11.4

0.425 0.51 1.62 13.25


0.42 0.42 1.26 13.25

0.238333 0.286 0.91 17


0.238333 0.286 0.91 14
0.238333 0.286 0.91 18.6667
0.133333 0.16 0.51 17.6667
0.166667 0.2 0.63 18.6667

L/6 L/5 TOTAL L


0.675 0.81 2.57 34
0.675 0.81 2.57 28
0.475 0.57 1.81 37.3333

0.53 0.53 1.59 12.75


0.53 0.53 1.59 10.5

0.425 0.51 1.62 4.76667


0.42 0.42 1.26 4.76667
0.466667 0.56 1.77 4.76667
0.53 0.53 1.59 2.66667
0.466667 0.56 1.77 3.33333
CAL WEIGHT
IN mm
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 64.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 180 C.D.
Project Description : Complete construction of 2-Storey 12-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF! #REF!
Part II Other General Requirements #REF! #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF! -
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF! -
PART C FINISHING WORKS #REF! #REF!
PART D PLUMBING/SANITARY WORKS #REF! #REF!
PART E ELECTRICAL WORKS #REF! #REF!

Total #REF! #REF!

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor #REF! A. Total Direct Cost #REF!
2. Materials #REF! B. OCM and Profit #REF!
3. Rental of Equipment #REF! C. Value Added Tax (12%) #REF!
4. Provisional Sum / Daywork D. Total Construction Cost #REF!
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit #REF! E. Eng'g & Administrative Overhead, 0.5% #REF!
6. Value Added Tax (12%) #REF! F. RROW Acquisition
7. EAO, 0.5% #REF! G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST #REF! H. TOTAL ESTIMATED COST #REF!
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 6.00 mo #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
#REF! Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 lot #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
#REF! Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
#REF! Mobilization/ Demobilization
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 413.71 m3 - - - - 20% - - -
#REF! Structure Excavation
As Evaluated
As Submitted #REF! 257.76 m3 - - - - 20% - - -
#REF! Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 335.90 m3 - - - - 20% - - -
#REF! Embankment from Borrow
As Evaluated
As Submitted #REF! 90.34 m3 - - - - 20% - - -
#REF! Gravel Fill
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 384.71 m3 - - - - 20% - - -
#REF! Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 68,853.89 kg - - - - 20% - - -
#REF! Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,577.60 m2 - - - - 20% - - -
#REF! Forms and Falseworks
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 300.27 L - - - - 20% - - -
#REF! Soil Poisoning
As Evaluated
As Submitted - - - - - - -
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 285.37 m2 - - - - 20% - - -
#REF! 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 961.80 m2 - - - - 20% - - -
#REF! 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted - - - - - - -
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s #REF! #REF! - #REF! 20% #REF! #REF! #REF!
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 70.87 m2 - - - - 20% - - -
#REF! Jalousie Window
As Evaluated
As Submitted #REF! 146.88 m2 #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 65.28 m2 - 30,846.01 - 30,846.01 20% 6,169.20 4,441.83 41,457.04
1005(5) Window Grilles
As Evaluated
As Submitted #REF! 43.00 set - - - - 20% - - -
#REF! Locksets
As Evaluated
As Submitted #REF! 172.00 pc - - - - 20% - - -
#REF! Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,161.01 m2 - - - - 20% - - -
#REF! Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 4,355.83 m 2
- - - - 20% - - -
#REF! Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 144.00 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 661.00 m 2
- - - - 20% - - -
#REF! Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 841.24 m 2
- - - - 20% - - -
#REF! Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m 2
- - - - 20% - - -
#REF! Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m 2
- - - - 20% - - -
#REF! Unglazed Tiles
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,943.76 m2 - - - - 20% - - -
#REF! Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 247.39 m 2
- - - - 20% - - -
#REF! Wood Painting
As Evaluated
As Submitted #REF! 125.09 m 2
- - - - 20% - - -
#REF! Metal Painting
As Evaluated
As Submitted - - - - - - -
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 841.24 m2 - - - - 20% - - -
#REF! Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 64.20 m - - - - 20% - - -
#REF! Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m - - - - 20% - - -
#REF! Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 128.40 m - - - - 20% - - -
#REF! Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 7,703.59 kg #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Structural Steel, Trusses
As Evaluated
As Submitted #REF! 10,028.53 kg - - - - 20% - - -
#REF! Structural Steel, Purlins
As Evaluated
As Submitted #REF! 128.40 m - - - - 20% - - -
#REF! Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg - - - - 20% - - -
#REF! Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 293.65 kg - - - - 20% - - -
#REF! Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 628.56 kg - - - - 20% - - -
#REF! Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 52.00 pc - - - - 20% - - -
#REF! Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.6
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 30.00 units #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Catch basin
As Evaluated
As Submitted #REF! 1.00 lot #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-2 Fire Protection System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
#REF! Fire Alarm System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART E
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART III
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 55.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 175 C.D.
Project Description : Complete construction of 2-Storey 10-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF! #REF!
Part II Other General Requirements #REF! #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF! 0.00
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF! 0.00
PART C FINISHING WORKS #REF! #REF!
PART D PLUMBING/SANITARY WORKS #REF! #REF!
PART E ELECTRICAL WORKS #REF! #REF!
`

Total #REF! #REF!

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor #REF! A. Total Direct Cost #REF!
2. Materials #REF! B. OCM and Profit #REF!
3. Rental of Equipment #REF! C. Value Added Tax (12%) #REF!
4. Provisional Sum / Daywork D. Total Construction Cost #REF!
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit #REF! E. Eng'g & Administrative Overhead, 0.5% #REF!
6. Value Added Tax (12%) #REF! F. RROW Acquisition
7. EAO, 0.5% #REF! G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST #REF! H. TOTAL ESTIMATED COST #REF!
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.83 mo #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 L.S. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 365.45 m3 - - - - 20% - - -
803(1)a Structure Excavation
As Evaluated
804(1)a As Submitted #REF! 223.43 m3 - - - - 20% - - -
Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 288.09 m3 - - - - 20% - - -
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 78.20 m3 - - - - 20% - - -
804(4) Gravel Fill
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 335.41 m3 - - - - 20% - - -
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 59,947.73 kg - - - - 20% - - -
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,225.34 m2 - - - - 20% - - -
903(2) Forms and Falseworks
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 259.98 L - - - - 20% - - -
1000(1) Soil Poisoning
As Evaluated
As Submitted - - - - - - -
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 267.94 m2 - - - - 20% - - -
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 838.99 m2 - - - - 20% - - -
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted - - - - - - -
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 59.98 m2 - - - - 20% - - -
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 122.40 m2 #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 54.40 m 2
- 25,705.01 - 25,705.01 20% 5,141.00 3,701.52 34,547.53
1005(5) Window Grills
As Evaluated
As Submitted #REF! 39.00 set - - - - 20% - - -
1004(2)a Locksets
As Evaluated
As Submitted #REF! 156.00 pc - - - - 20% - - -
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,000.20 m2 - - - - 20% - - -
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,825.21 m2 - - - - 20% - - -
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 127.60 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 565.91 m 2
- - - - 20% - - -
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 723.31 m2 - - - - 20% - - -
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m2 - - - - 20% - - -
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m2 - - - - 20% - - -
1018(2) Unglazed Tiles
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,336.71 m2 - - - - 20% - - -
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 218.61 m2 - - - - 20% - - -
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 112.50 m2 - - - - 20% - - -
1032(1)c Metal Painting
As Evaluated
As Submitted - - - - - - -
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 723.31 m2 - - - - 20% - - -
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 55.20 m - - - - 20% - - -
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m - - - - 20% - - -
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 110.40 m - - - - 20% - - -
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 6,440.06 kg #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 8,515.07 kg - - - - 20% - - -
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 110.40 m - - - - 20% - - -
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg - - - - 20% - - -
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 248.16 kg - - - - 20% - - -
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 528.07 kg - - - - 20% - - -
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 44.00 pc - - - - 20% - - -
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.6
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 26.00 units #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-2 Fire Protection System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1003(1) Lighting Fixtures
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1208(1) Fire Alarm System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART E
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART III
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 46.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 150 C.D.
Project Description : Complete construction of 2-Storey 8-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF! #REF!
Part II Other General Requirements #REF! #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF! 0.00
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF! 0.00
PART C FINISHING WORKS #REF! #REF!
PART D PLUMBING/SANITARY WORKS #REF! #REF!
PART E ELECTRICAL WORKS #REF! #REF!

Total #REF! #REF!

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor #REF! A. Total Direct Cost #REF!
2. Materials #REF! B. OCM and Profit #REF!
3. Rental of Equipment #REF! C. Value Added Tax (12%) #REF!
4. Provisional Sum / Daywork D. Total Construction Cost #REF!
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit #REF! E. Eng'g & Administrative Overhead, 0.5% #REF!
6. Value Added Tax (12%) #REF! F. RROW Acquisition
7. EAO, 0.5% #REF! G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST #REF! H. TOTAL ESTIMATED COST #REF!
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.00 mo #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 313.84 m3 - - - - 20% - - -
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 185.75 m3 - - - - 20% - - -
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 240.28 m3 - - - - 20% - - -
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 66.06 m3 - - - - 20% - - -
804(4) Gravel Fill
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 286.11 m3 - - - - 20% - - -
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 51,041.57 kg - - - - 20% - - -
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,873.07 m2 - - - - 20% - - -
903(2) Forms and Falseworks
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 219.68 L - - - - 20% - - -
1000(1) Soil Poisoning
As Evaluated
As Submitted - - - - - - -
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 250.52 m2 - - - - 20% - - -
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 716.18 m2 - - - - 20% - - -
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted - - - - - - -
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 49.10 m2 - - - - 20% - - -
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 97.92 m2 #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 43.52 m2 - 20,564.01 - 20,564.01 20% 4,112.80 2,961.22 27,638.03
1005 (5) Window Grills
As Evaluated
As Submitted #REF! 35.00 set - - - - 20% - - -
1004(2)a Locksets
As Evaluated
As Submitted #REF! 140.00 pc - - - - 20% - - -
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 839.37 m2 - - - - 20% - - -
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,294.60 m2 - - - - 20% - - -
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 111.20 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 470.83 m2 - - - - 20% - - -
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 605.38 m 2
- - - - 20% - - -
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m 2
- - - - 20% - - -
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m 2
- - - - 20% - - -
1018(2) Unglazed Tiles
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 3,729.66 m2 - - - - 20% - - -
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 189.83 m 2
- - - - 20% - - -
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 99.91 m2 - - - - 20% - - -
1032(1)c Metal Painting
As Evaluated
As Submitted - - - - - - -
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 605.38 m2 - - - - 20% - - -
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 46.20 m - - - - 20% - - -
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m - - - - 20% - - -
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 92.40 m - - - - 20% - - -
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 5,176.53 kg #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 7,001.60 kg - - - - 20% - - -
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 92.40 m - - - - 20% - - -
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg - - - - 20% - - -
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 202.67 kg - - - - 20% - - -
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 427.58 kg - - - - 20% - - -
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 36.00 pc - - - - 20% - - -
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.6
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 20.00 units #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-2 Fire Protection System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1208(1) Fire Alarm System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART E
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART III
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 32.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 140 C.D.
Project Description : Complete construction of 2-Storey 6-Classroom School Buidling (stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF! #REF!
Part II Other General Requirements #REF! #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF! 0.00
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF! 0.00
PART C FINISHING WORKS #REF! #REF!
PART D PLUMBING/SANITARY WORKS #REF! #REF!
PART E ELECTRICAL WORKS #REF! #REF!

Total #REF! #REF!

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor #REF! A. Total Direct Cost #REF!
2. Materials #REF! B. OCM and Profit #REF!
3. Rental of Equipment #REF! C. Value Added Tax (12%) #REF!
4. Provisional Sum / Daywork D. Total Construction Cost #REF!
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit #REF! E. Eng'g & Administrative Overhead, 0.5% #REF!
6. Value Added Tax (12%) #REF! F. RROW Acquisition
7. EAO, 0.5% #REF! G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST #REF! H. TOTAL ESTIMATED COST #REF!
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.67 mo #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 244.62 m3 - - - - 20% - - -
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 139.08 m3 - - - - 20% - - -
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 159.64 m3 - - - - 20% - - -
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 46.06 m3 - - - - 20% - - -
804(4) Gravel Fill
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 201.23 m3 - - - - 20% - - -
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 36,154.58 kg - - - - 20% - - -
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,312.79 m2 - - - - 20% - - -
903(2) Forms and Falseworks
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 159.89 L - - - - 20% - - -
1000(1) Soil Poisoning
As Evaluated
As Submitted - - - - - - -
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 147.30 m2 - - - - 20% - - -
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 522.79 m2 - - - - 20% - - -
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted - - - - - - -
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1010(4) Wooden Dooor
As Evaluated
As Submitted #REF! 34.93 m2 - - - - 20% - - -
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 73.44 m2 #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 32.64 m2 - 15,423.00 - 15,423.00 20% 3,084.60 2,220.91 20,728.51
1005(5) Window Grill
As Evaluated
As Submitted #REF! 24.00 set - - - - 20% - - -
1004(2)a Locksets
As Evaluated
As Submitted #REF! 96.00 pc - - - - 20% - - -
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 584.99 m2 - - - - 20% - - -
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 2,313.83 m 2
- - - - 20% - - -
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 92.12 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 332.94 m 2
- - - - 20% - - -
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 434.28 m 2
- - - - 20% - - -
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
- - - - 20% - - -
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
- - - - 20% - - -
1018(2) Unglazed Tiles
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 2,553.91 m2 - - - - 20% - - -
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 133.27 m 2
- - - - 20% - - -
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 62.73 m 2
- - - - 20% - - -
1032(1)c Metal Painting
As Evaluated
As Submitted - - - - - - -
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 434.28 m2 - - - - 20% - - -
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 32.90 m - - - - 20% - - -
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m - - - - 20% - - -
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 65.80 m - - - - 20% - - -
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 3,535.91 kg #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 5,170.61 kg - - - - 20% - - -
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 65.80 m - - - - 20% - - -
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg - - - - 20% - - -
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 146.82 kg - - - - 20% - - -
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 314.91 kg - - - - 20% - - -
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 26.00 pc - - - - 20% - - -
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.6
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 16.00 units #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-2 Fire Protection System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1208(1) Fire Alarm System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART E
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART III
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
GRAND TOTAL
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING Appropriation :

( 9.5m x 23.00m ) Source of Fund :


Project ID : Target Start Date :
Location : Total Project Duration : 120 C.D.
Project Description : Complete construction of 2-Storey 4-Classroom School Buidling (with stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF! #REF!
Part II Other General Requirements #REF! #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF! -
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF! -
PART C FINISHING WORKS #REF! #REF!
PART D PLUMBING/SANITARY WORKS #REF! #REF!
PART E ELECTRICAL WORKS #REF! 27,404.00

Total #REF! #REF!

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor #REF! A. Total Direct Cost #REF!
2. Materials #REF! B. OCM and Profit #REF!
3. Rental of Equipment #REF! C. Value Added Tax (12%) #REF!
4. Provisional Sum / Daywork D. Total Construction Cost #REF!
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit #REF! E. Eng'g & Administrative Overhead, 0.5% #REF!
6. Value Added Tax (12%) #REF! F. RROW Acquisition
7. EAO, 0.5 % #REF! G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST #REF! H. TOTAL ESTIMATED COST #REF!
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted - 4.00 mo #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.04 1.00 ea #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.84 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.37 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted Err:509 196.98 m3 - - - - 20% - - -
803(1)a Structure Excavation
As Evaluated
As Submitted 0.05 105.37 m3 - - - - 20% - - -
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.20 111.83 m3 - - - - 20% - - -
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.10 33.92 m3 - - - - 20% - - -
804(4) Gravel Fill
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 2.90 151.93 m3 - - - - 20% - - -
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 21.81 27,248.42 kg - - - - 20% - - -
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 2.50 960.52 m2 - - - - 20% - - -
903(2) Forms and Falseworks
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted - 115.60 L - - - - 20% - - -
1000(1) Soil Poisoning
As Evaluated
As Submitted - - - - - - -
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.82 129.91 m2 - - - - 20% - - -
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 5.91 399.98 m2 - - - - 20% - - -
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted - - - - - - -
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 0.72 1.00 l.s. 26,000.00 - - 26,000.00 20% 5,200.00 3,744.00 34,944.00
1010(4) Wooden Doors
As Evaluated
As Submitted 3.56 24.05 m2 - - - - 20% - - -
1009(1)a Jalousie Window
As Evaluated
As Submitted 3.28 48.96 m2 #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1005 (1) Steel Casement Window
As Evaluated
As Submitted - 21.76 m2 - 10,282.00 - 10,282.00 20% 2,056.40 1,480.61 13,819.01
1005(5) Window Grill
As Evaluated
As Submitted - 20.00 set - - - - 20% - - -
1004(2)a Locksets
As Evaluated
As Submitted 0.20 80.00 pc - - - - 20% - - -
1004(2)g Hinges
As Evaluated
As Submitted - 1.00 l.s. 12,400.00 2,865.28 286.53 15,551.81 20% 3,110.36 2,239.46 20,901.63
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 0.40 424.17 m2 - - - - 20% - - -
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 2.37 1,783.22 m 2
- - - - 20% - - -
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted Err:509 33.00 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted 0.34 73.42 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a2
stiffener As Evaluated
As Submitted 3.11 237.86 m 2
- - - - 20% - - -
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 14.58 315.48 m 2
- - - - 20% - - -
1038(1) Reflective Insulation
As Evaluated
As Submitted 4.21 71.55 m 2
- - - - 20% - - -
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 1.82 20.05 m 2
- - - - 20% - - -
1018(2) Unglazed Tiles
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 1.65 1,946.86 m2 - - - - 20% - - -
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted - 104.49 m 2
- - - - 20% - - -
1032(1)b Wood Painting
As Evaluated
As Submitted - 50.14 m 2
- - - - 20% - - -
1032(1)c Metal Painting
As Evaluated
As Submitted - - - - - - -
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted - 315.48 m2 - - - - 20% - - -
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.01 23.90 m - - - - 20% - - -
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.03 26.21 m - - - - 20% - - -
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted Err:509 47.80 m - - - - 20% - - -
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted - 2,271.38 kg #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 0.03 3,687.15 kg - - - - 20% - - -
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted - 47.80 m - - - - 20% - - -
1003(11) Fascia Board
As Evaluated
As Submitted - 277.47 kg - - - - 20% - - -
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted - 101.34 kg - - - - 20% - - -
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted - 214.42 kg - - - - 20% - - -
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted - 18.00 pc - - - - 20% - - -
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1.06 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.6
As Evaluated s
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.33 1.00 l.s. - - - - 20% - - -
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.37 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(6) Cold Water Line Works
As Evaluated
As Submitted 0.09 1.00 l.s. - #VALUE! #VALUE! #VALUE! 20% #VALUE! #VALUE! #VALUE!
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted - 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.79 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.07 12.00 units #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(6)b1 Catch basin
As Evaluated
As Submitted 1.03 1.00 lot #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-2 Fire Protection System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.46 1.00 l.s. - - - - 20% - - -
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.95 1.00 l.s. - - - - 20% - - -
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 0.26 1.00 l.s. 1,404.00 - 26,000.00 27,404.00 20% 5,480.80 3,946.18 36,830.98
1102(21) Panel Board
As Evaluated
As Submitted 1.16 1.00 l.s. - - - - 20% - - -
1003(1) Lighting Fixtures
As Evaluated
As Submitted - 1.00 l.s. - - - - 20% - - -
1208(1) Fire Alarm System
As Evaluated
As Submitted 1,404.00 - 26,000.00 27,404.000 5,480.800 3,946.180 36,830.980
TOTAL OF PART E
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART III
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION

FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING Appropriation :


( 9.5m x 14.00m ) Source of Fund :
Project ID : Target Start Date :
Location : Total Project Duration : 115 C.D.
Project Description : Complete construction of 2-Storey 2-Classroom School Buidling (with stairwall 5m width, steel casement window
at rear portion with security grilles for the front jalousie windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF! #REF!
Part II Other General Requirements #REF! #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF! 0.00
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF! 0.00
PART C FINISHING WORKS #REF! #REF!
PART D PLUMBING/SANITARY WORKS #REF! #REF!
PART E ELECTRICAL WORKS #REF! #REF!

Total #REF! #REF!

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor #REF! A. Total Direct Cost #REF!
2. Materials #REF! B. OCM and Profit #REF!
3. Rental of Equipment #REF! C. Value Added Tax (12%) #REF!
4. Provisional Sum / Daywork D. Total Construction Cost #REF!
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit #REF! E. Eng'g & Administrative Overhead, 0.5% #REF!
6. Value Added Tax (12%) #REF! F. RROW Acquisition
7. EAO, 0.5% #REF! G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST #REF! H. TOTAL ESTIMATED COST #REF!
Note: 1. Prices of Materials were based on CMPD 2017 2nd Quarter and Labor based on June 2017 rates in National Capital Region (NCR).
2. Based on approved plans for Upgraded Calamity Resilient Design DepEd School Buildings (Revised 3-24-2017)

Prepared by: Checked by: Submitted by: Noted:

JUNNEL RAY C. BAUTISTA ROSELYN C. NIEBRES EDGARDO C. GARCES WALTER R. OCAMPO


Engineeer II Engineer IV Engineer V Director IV
BOC-CSSD BOC-CSSD BOC-CSSD Bureau of Construction
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 3.83 mo #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART I
As Evalauted
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 8% #REF! #REF! #REF!
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART II
As Evaluated

(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 144.01 m3 - - - - 20% - - -
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 66.34 m3 - - - - 20% - - -
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 64.02 m3 - - - - 20% - - -
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 21.78 m3 - - - - 20% - - -
804(4) Gravel Fill
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 102.63 m3 - - - - 20% - - -
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 18,342.24 kg - - - - 20% - - -
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 608.26 m2 - - - - 20% - - -
903(2) Forms and Falseworks
As Evaluated
As Submitted - - - - - - -
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 75.31 L - - - - 20% - - -
1000(1) Soil Poisoning
As Evaluated
As Submitted - - - - - - -
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 112.48 m2 - - - - 20% - - -
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 227.17 m2 - - - - 20% - - -
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted - - - - - - -
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 13.71 m2 - - - - 20% - - -
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 24.48 m2 #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 10.88 m2 - 5,141.00 - 5,141.00 20% 1,028.20 740.30 6,909.50
1005 (5) Window Grill
As Evaluated
As Submitted #REF! 16.00 set - - - - 20% - - -
1004(2)a Locksets
As Evaluated
As Submitted #REF! 64.00 pc - - - - 20% - - -
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 263.35 m2 - - - - 20% - - -
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,252.61 m 2
- - - - 20% - - -
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 55.82 m #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 142.77 m 2
- - - - 20% - - -
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 196.68 m 2
- - - - 20% - - -
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
- - - - 20% - - -
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
- - - - 20% - - -
1018(2) Unglazed Tiles
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,339.81 m2 - - - - 20% - - -
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 75.71 m 2
- - - - 20% - - -
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 37.55 m 2
- - - - 20% - - -
1032(1)c Metal Painting
As Evaluated
As Submitted - - - - - - -
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 196.68 m2 - - - - 20% - - -
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 14.90 m - - - - 20% - - -
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m - - - - 20% - - -
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 29.80 m - - - - 20% - - -
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 1,008.85 kg #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 2,143.69 kg - - - - 20% - - -
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 29.80 m - - - - 20% - - -
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg - - - - 20% - - -
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 55.85 kg - - - - 20% - - -
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 113.93 kg - - - - 20% - - -
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 10.00 pc - - - - 20% - - -
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Sub-Total C.6
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 8.00 units #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
SPL-2 Fire Protection System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. #REF! #REF! #REF! #REF! 20% #REF! #REF! #REF!
1208(1) Fire Alarm System
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART E
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF PART III
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL OF (Project ID)
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF (Project ID)
As Evaluated
As Submitted #REF! #REF! #REF! #REF! #REF! #REF! #REF!
GRAND TOTAL
As Evaluated

You might also like