Professional Documents
Culture Documents
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer #REF!
Part II Other General Requirements #REF!
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS #REF!
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) #REF!
PART C FINISHING WORKS #REF!
PART D PLUMBING/SANITARY WORKS #REF!
PART E ELECTRICAL WORKS #REF!
Total
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning/Const. Section/Division/Consultant Planning/Const. Section/Division/UPMO Planning/Construction Division/BOC
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Supply and Install 1500 liters Stainless Tank unit 2.00 25,000.00 50,000.00
b. Consumables (3% of Materials Cost) 1,500.00
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Solar LED Streetlight , 150W , 6500K w/ motion set 1.00 15,500.00 15,500.00
sensor and photoswitch ,IP 65RATED
b. Consumables (5% of Materials Cost) 775.00
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. 25 ft. Hot Dip Galvanized Street Light Pole w/ pc 1.00 24,985.00 24,985.00
complete accessories ( Galvanized anchor bolts,
Steel Base Plate, Nut and washer)
b. Consumables (5% of Materials Cost) 1,249.25
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. 5/8"øx30" Anchor Bolt w/ nut and washer pc. 1.00 393.54 393.54
-
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No of Unit/s No. of Day/s Hourly Rate Amount (PhP)
B. Equipment
Project : INSTALLATION OF STREET LIGHTS FOR BARANGAY SAYON Appropriation : PHP 6,606,882.17
Location : Barangay Sayon, Sta. Josefa, Agusan del Sur Source of Fund : LGSF - FALGU 2022
Project Description : Installation of Solar street lights including electrical and concrete finishes Target Start Date :
Total Project Duration : 65 C.D.
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT % TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Page 12 of 124
INSTALLATION OF STREET LIGHTS FOR BARANGAY SAYON
Barangay Sayon, Sta. Josefa, Agusan del Sur
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 One Bagger Mixer 4 - 6 ft3/min 1 29
2 Welding Machine 500 amp 1 30
3 Cutting Outfit 1 31
4 Plate Compactor 5 HP 1 32
5 Bar Cutter 1 33
6 Bar Bender 1 34
7 35
8 36
9 37
10 38
11 39
12 40
13 41
14 42
15 43
16 44
17 45
18 46
19 47
20 48
21 49
22 50
23 51
24 52
25 53
26 54
27 55
28 56
SUB-TOTAL SUB-TOTAL
TOTAL
Page 13 of 124
INSTALLATION OF STREET LIGHTS FOR BARANGAY SAYON
Barangay Sayon, Sta. Josefa, Agusan del Sur
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
ITEM NO. DESCRIPTION QUANTITY UNIT % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
TOTAL OF PART A As Submitted 12,757.50 11,991.93 56,593.76 81,343.19 20,335.79 5,083.95 106,762.93
TOTAL OF PART B As Submitted 519,075.30 168,937.95 35,301.74 723,314.99 180,828.75 45,207.19 949,350.93
PART C FINISHING
1027(1) CEMENT PLASTER FINISH As Submitted 0.27 64.80 sq.m. 9,360.36 3,751.58 375.16 208.13 13,487.10 25% 3,371.78 842.94 17,701.82
1032(1)a PAINTING WORKS (MASONRY) As Submitted 0.24 64.80 sq.m. 3,269.32 8,174.06 817.41 189.21 12,260.79 25% 3,065.20 766.30 16,092.29
TOTAL OF PART C As Submitted 12,629.68 11,925.64 1,192.57 25,747.89 6,436.98 1,609.24 33,794.11
PART D ELECTRICAL
1109(1) GROUNDING SYSTEM As Submitted 9.04 81.00 set 438,432.75 16,289.91 1,628.99 5,633.97 456,351.65 25% 114,087.91 28,521.98 598,961.54
1103(1) LIGHTING FIXTURES As Submitted 27.22 81.00 pcs 1,318,275.00 50,884.20 5,088.42 16,966.02 1,374,247.62 25% 343,561.91 85,890.48 1,803,700.01
TOTAL OF PART D As Submitted 1,756,707.75 67,174.11 6,717.41 1,830,599.27 457,649.82 114,412.46 2,402,661.55
PART E OTHER
1200(1) STREET LAMP POST As Submitted 45.24 81.00 pcs 2,124,974.25 144,840.15 14,484.02 28,201.22 2,284,298.42 25% 571,074.61 142,768.65 2,998,141.68
TOTAL OF PART E As Submitted 2,124,974.25 144,840.15 14,484.02 2,284,298.42 571,074.61 142,768.65 2,998,141.68
TOTAL OF PART II As Submitted 4,426,144.48 404,869.78 114,289.50 4,945,303.76 1,236,325.95 309,081.49 6,490,711.20
TOTAL OF (Project ID) As Submitted 4,426,144.48 404,869.78 114,289.50 4,945,303.76 1,236,325.950 309,081.49 6,490,711.20
GRAND TOTAL As Submitted 100.00 4,484,390.88 413,022.73 151,399.39 5,048,813.00 1,243,455.73 314,613.45 6,606,882.17
PART C FINISHING
1027(1) CEMENT PLASTER FINISH 64.80 sq.m. 13,487.10 15% 10% 25% 3,371.78 842.94 4,214.72 17,701.82
1032(1)a PAINTING WORKS (MASONRY) 64.80 sq.m. 12,260.79 15% 10% 25% 3,065.20 766.30 3,831.50 16,092.29
PART D ELECTRICAL
1109(1) GROUNDING SYSTEM 81.00 set 456,351.65 15% 10% 25% 114,087.91 28,521.98 142,609.89 598,961.54
1103(1) LIGHTING FIXTURES 81.00 pcs 1,374,247.62 15% 10% 25% 343,561.91 85,890.48 429,452.39 1,803,700.01
PART E OTHER
1200(1) STREET LAMP POST 81.00 pcs 2,284,298.42 15% 10% 25% 571,074.61 142,768.65 713,843.26 2,998,141.68
Total 5,048,813.00 1,243,455.73 314,613.45 1,558,069.18 6,606,882.17
Page 16 of 124
INSTALLATION OF STREET LIGHTS FOR BARANGAY SAYON
Barangay Sayon, Sta. Josefa, Agusan del Sur
BILL OF QUANTITIES
a. F1C1
= 1.00 m x 1.00 m x 0.10 m x 81 units
= 8.1 m3
a. POLE FOUNDATION - 01
= 1.00 m x 1.00 m x 0.20 m x 81 units
= 16.2 m3
Footing Rebars:
Pole - 01
= 1.00 m x 12 x 1.578 kg/m x 81 units
= 1533.82 kg.
Reinforcing Bars
Pole - 01 `
= 1.70 m x 8 x 1.578 kg/m x 81 units
= 1738.32 kg.
TIES
Pole - 01 `
= 1.34 m x 17 x 0.617 kg/m x 81 units
= 1138.48 kg.
Approved by:
INSTALLATION OF STREET LIGHTS FOR BARANGAY SAYON
Barangay Sayon, Sta. Josefa, Agusan del Sur
BILL OF QUANTITIES
a. Tubular Aluminum Framed Swing Door with Fixed Tinted Glass Panels both sides
with automatic door closer, 3 sets
= 2.10 m x 1.00 m
AD1 = 6.300 m2
Materials:
Glazzing Putty 1 gal 645.00 /gal
Flat Wall Enamel 1 gal 610.00 /gal
Quick Dry Enamel 1 gal 670.00 /gal
Paint Thinner 1L 75.00 /L
Tinting Color 1 pint 380.00 /pint
2,380.00
Labor:
952.00
Equipment:
95.20
TOTAL
3,427.20
Materials:
Red Oxide Primer 1 gal 799.00 /gal
Enamel Paint 1 gal 758.00 /gal
Paint Thinner 1 gal 300.00 /gal
Tinting Color 1 pint 380.00 /pint
2,237.00
Labor:
894.80
Equipment:
89.48
TOTAL
3,221.28
Cabinets:
2" x 2", 2mm Angle Bar 279.680 kg
2" x 2", 6mm thick Angle Bar 365.800 kg
1-1/2" x 1-1/2", 4.5mm thick Angle Bar 67.800 kg
1" x 1", 2mm Angle Bar 85.500 kg
3/4", 2mm Flat Bar 13.420 kg
1/4" Flat Bar 3.400 kg
3/4" Marine Plywood 25.000 pc
Welding Rods 30.000 kg
E. EQUIPMENT RENTAL RATES
Rental of equipment presented in the Detailed Unit Price Analysis (DUPA) are based on the prevailing
“Association of Carriers and Equipment Lessors, (ACEL) Inc.” rental rates approved for use by the DPWH
(Presently it is the 2014 ACEL Rates). Rental rates of equipment not indicated in the ACEL booklet shall be
taken from the rental rates prepared by the Bureau of Equipment. For simplicity in computation, the operated
rental rates are preferred over the bare rental rates as the former includes operator’s wages, fringe benefits,
fuel, oil, lubricants and equipment maintenance.
E.1 List of equipment adopted in the standard DUPA with make, model and capacity
FLYWHEEL
DESCRIPTION CAPACITY RENTAL RATE
HORSEPOWER
1. Earthmoving Equipment
1.1 Bulldozer 165 PhP 3,379.00
1.2 Payloader 1.50 m3/1.95 yd3 110 PhP 1,733.00
1.3 Motorized Road Grader 140 PhP 2,173.00
2. Compaction Equipment
2.1 Plate Compactor 5 PhP 123.00
3. Lifting Equipment
3.1 Crawler Crane 21-25 mt 145 PhP 1,522.00
3.2 Crawler Crane 36-40 mt 190 PhP 1,902.00
3.3 Crawler Crane 41-45 mt 190 PhP 2,151.00
3.4 Truck Mounted Crane 20-25 mT 200 PhP 1,631.00
3.5 Truck Mounted Crane 31-35 mt 238 PhP 1,861.00
3.6 Truck Mounted Crane 41-45 mt 246 PhP 2,606.00
3.7 Truck Mounted, Scissor Lift, Terrain 40 ft hts x 46 ft range PhP 1,386.00
4. Excavating Equipment
4.1 Backhoe 0.80 m3/1.04 yd3 99 PhP 1,537.00
4.2 Backhoe w/ Breaker 0.80 m /1.04 yd
3 3
99 PhP 1,998.10
4.3 Backhoe, Wheel Mounted 0.28 m3/0.37 yd3 50 PhP 922.00
4.4 Portable Breaker WACKER PORTABLE PETROL BREAKER,4BHF30S PhP 129.38
5. Foundation Equipment
5.1 Diesel Hammer 7500 kg-m PhP 1,286.00
5.2 Vibro Hammer 60 ton 201 PhP 2,123.00
5.3 Vibro Hammer w/ Hydraulic Power Pack 120 kN-m 222 PhP 4,118.00
5.4 Vibro Hammer 45000 kg-m 272.22 PhP 3,069.00
6 Concreting Equipment
6.1 Concrete Screeder 5.50 PhP 545.00
6.2 Concrete Paver PhP 6,765.00
6.3 One Bagger Mixer 4-6 ft3/min PhP 172.00
6.4 Transit Mixer 5-6 yd3 175 PhP 1,318.00
7 Hauling Equipment
7.1 Dump Truck 12 yd3 290 PhP 1,420.00
7.2 Cargo/Service Truck 2-5 mt 160 PhP 783.00
7.3 Boom Truck 2-5 mt 160 PhP 1,017.90
7.4 Cargo/Service Truck 9-10 mt 270 PhP 1,212.00
7.5 Water Truck/Pump 16000 L 360 PhP 2,450.00
8 Air Equipment
8.1 Air Compressor 356-450 cfm 130 PhP 965.00
8.2 Air Compressor 161-185 cfm 69 PhP 502.00
8.3 Air Compressor, Portable 120-160 cfm 51 PhP 450.00
8.4 Air Compressor 15-35 cfm 20 PhP 205.00
8.5 Diamond Drill PhP 201.25
8.6 Jackhammer PhP 150.00
8.7 Pneumatic Drilling Machine PhP 170.00
SOLID SIZE
FLYWHEEL
DESCRIPTION CAPACITY RENTAL RATE
HORSEPOWER
(mm)
9 Pumping Equipment
9.1 Water Pump, 100 mm suction Ø 50 16 PhP 266.25
9.2 Water Pump, 100 mm suction Ø 7.50 PhP 123.38
9.3 Pumpcrete PhP 2,076.00
CAPACITY
DESCRIPTION RENTAL RATE
kW kVA
10 Power Generating Equipment
10.1 Generator Set 301-350 kW 375 PhP 872.87
10.2 Generator Set 700 kW 875 PhP 2,147.27
FLYWHEEL
DESCRIPTION AMPERES RENTAL RATE
HORSEPOWER
11 Shop Equipment
11.1 Welding Machine 500 PhP 391.00
11.2 Welding Machine 300 48 PhP 371.00
FLYWHEEL
DESCRIPTION CAPACITY RENTAL RATE
HORSEPOWER
12 Special Support Equipment
12.1 Chainsaw HUSQVARNA 2100 CD with CR22, 7 ft Reach, 9 in Standard
PhP Blade 75.36
13. Miscellaneous Equipment
13.1 Concrete Vibrator Flexible Shaft Type 2" Head Ø with 5 Amperes Gasoline
PhP Drive Unit 91.25
13.2 Bar Cutter 25 mm Maximum Rebar Ø (Grade 40), SinglePhPPhase 219.75
13.3 Bar Bender 25 mm Maximum Rebar Ø, Three Phase PhP 351.50
14. Others
14.1 Drop Hammer w/ accessories 20 mt PhP 5,000.00
14.2 1 Air Compressor w/ 2 Jack Hammer PhP 1,265.00
14.3 Cutting Outfit PhP 45.45
Electrical
LED Downlight, Surface Mounted, 7Watts set 450.00
LED Downlight, Recessed Type, 7Watts set 450.00
25mm Ø Rigid Steel Conduit x 3.0m length 766.00
25mm Ø RSC Elbow pc. 201.00
25mm Ø Entrance Cap pc. 201.00
20mm Ø Electrical PVC Pipe, PNS14 pc. 96.00
20mm Ø PVC Long Elbow pc. 25.00
Utility Box, 2"x4" Plastic orange, heavy duty pc 32.00
Junction Box with cover, 4"x4" Plastic orange, heavy duty set 35.00
Three Gang Flush-Type Switch pc. 320.00
Double Gang Flush-Type Switch pc. 165.00
Single Gang Flush-Type Switch pc. 120.00
Double Gang Convenience Outlet pc. 367.00
Polarized 3-Prongs (ACU Outlet) pc. 472.00
Service Drop Wire m. 39.00
Panelboard ( PB1 ), Nema 1, indoor type 27,500.00
2 Pole,230 V, flush mounted type,
plug-in Main and Branches,complete
assymbly with circuit breakers
and grounding busbar
Main : 1-100AT/100AF,2P,ACB, 10kaic
Branches:
7-30AT/30AF,2P, 10kaic
5-20AT/20AF,2P, 10kaic
LED Light 3 eye 120W Cobra Type 6500K 6,425.00
Compact Fluorescent Lamp 12" White Globe 96.00
Forms
a. H-Frame 1.7 m x 1.2m, set 6.08
2 pcs H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
b. Shoring Jack, 3.8 m full extension 4.50
c. Adjustable U-head Jack, 0.6m 0.85
d. Adjustable Base Jack, 0.6m 0.85
e. 1-1/2" GI Pipe x 6.0 m 2.50
f. 1-1/2" GI Pipe x 3.0 m 1.25
g. 1-1/2" GI Pipe x 4.0 m 1.75
h. 1-1/2" GI Pipe x 1.0 m 0.50
i. Tie Rod x 0.60m 1.00
j. Round Wing Nut 0.15
Item No./Description : A.1.1(8) Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : mo
Output : 1
A. Labor
Name and Capacity No of Unit/s No. of Month/s Monthly Rate Amount (PhP)
B. Equipment
F. Materials
Sand
Source : Barangay Patrocinio
Ave. Hauling Distance (AHD= 8.00 km.
Cycle Time:
Without Load 8.00 km/trip / 25.00 km/hr = 0.32 hr/trip
With Load 8.00 km/trip / 20.00 km/hr = 0.40 hr/trip
Loading,Spot,Manuever,
Unloading,& Delay Time = 0.20 hr/trip
Total = 0.92 hr/trip
Labor Cost
Laborer {[( 1 man x 393.60 P/day ) / 8 hr/day ] x 0.92 hr/trip} / 10.00 cu m/trip = 4.53 P/cu m
Vat:12% 0.54 P/cu m
Equipment Cost 1,420.00 P/hr x 0.92 hr/trip / 10.00 cu m/trip = 130.64 P/cu m
Vat:12% 1,420.00 P/hr x 0.92 hr/trip / 10.00 cu m/trip x 0.12 = 15.68 P/cu m
30 of 124
Municipality of Sta. Josefa
OFFICE OF THE MUNICIPAL ENGINEER
Gravel
Source : Barangay Patrocinio
Ave. Hauling Distance (AHD= 8.00 km.
Cycle Time:
Without Load 8.00 km/trip / 25.00 km/hr = 0.32 hr/trip
With Load 8.00 km/trip / 20.00 km/hr = 0.40 hr/trip
Loading,Spot,Manuever,
Unloading,& Delay Time = 0.20 hr/trip
Total = 0.92 hr/trip
Labor Cost
Laborer {[( 1 man x 393.60 P/day ) / 8 hr/day ] x 0.92 hr/trip} / 10.00 cu m/trip = 4.53 P/cu m
Vat:12% 0.54 P/cu m
Equipment Cost 1,420.00 P/hr x 0.92 hr/trip / 10.00 cu m/trip = 130.64 P/cu m
Vat:12% 1,420.00 P/hr x 0.92 hr/trip / 10.00 cu m/trip x 0.12 = 15.68 P/cu m
31 of 124
Municipality of Sta. Josefa
OFFICE OF THE MUNICIPAL ENGINEER
A) Hauling Cost
Equipment: Cargo Truck 6-8 mt. tons w/ five (5) laborers (1 MT Ton = 1,100 kgs)
Capacity of Cargo Truck 8,000.00 kgs.
Ave.Hauling Distance,AHD 18.00 km
Trento to Loreto 18.00 km
Cycle Time:
Without Load Trento to Loreto 18.00 km / 25.00 km/hr = 0.72 hr
With Load Trento to Loreto 18.00 km / 20.00 km/hr = 0.90 hr
Laborer {[( 5.00 man x 393.60 P/d ) / 8.00 hr/d ] x 4.10 hr} / 8,000.00 kgs. = 0.13 /kg.
Vat:12% 0.02 /kg.
32 of 124
Municipality of Sta. Josefa
OFFICE OF THE MUNICIPAL ENGINEER
Cement
Source: Trento, Agusan del Sur
Ave. Hauling Distance 18.00 km.
A) Hauling Cost
Equipment: Cargo Truck 6-8 mt. tons w/ five (5) laborers (1 MT Ton = 1,100 kgs)
Capacity of Cargo Truck 200 bags
Ave.Hauling Distance,AHD 18.00 km
Trento to Loreto 18.00 km
Cycle Time:
Without Load Trento to Loreto 18.00 km / 25.00 km/hr = 0.72 hr
With Load Trento to Loreto 18.00 km / 20.00 km/hr = 0.90 hr
Labor Cost
Laborer {[( 5 man x 393.60 P/d ) / 8.00 hr/d ] x 2.95 hr} / 200 bags = 3.63 /bag
Vat:12% 0.44 /bag
33 of 124
Municipality of Sta. Josefa
OFFICE OF THE MUNICIPAL ENGINEER
Hauling Cost:
Equipment: Cargo Truck 6-8 mt. tons w/ five (5) laborers
Capacity of Cargo Truck 400 pcs./trip
Ave.Hauling Distance,AHD 18.00 km
Trento to Loreto 18.00 km
Cycle Time:
Without Load Trento to Loreto 18.00 km / 25.00 km/hr = 0.72 hr
With Load Trento to Loreto 18.00 km / 20.00 km/hr = 0.90 hr
Labor Cost
Laborer {[( 5 man x 393.60 P/d ) / 8.00 hr/d ] x 4.82 hr} / 400 P/pc = 2.96 /pc
Vat:12% 0.36 /pc
34 of 124
Municipality of Sta. Josefa
OFFICE OF THE MUNICIPAL ENGINEER
FORM LUMBER
Source: Sta. Josefa, Agusan del Sur
Ave. Hauling Distance 4.00 km.
Hauling Cost:
Equipment: Cargo Truck 6-8 mt. tons w/ five (5) laborers
Capacity of Cargo Truck 10,000.00 bd.ft
Ave.Hauling Distance,AHD 4.00 km
Cycle Time:
Without Load 4.00 km / 25.00 km/hr = 0.16 hr
With Load 4.00 km / 20.00 km/hr = 0.20 hr
Labor Cost
Laborer {[( 5.00 man x 393.60 P/d ) / 8.00 hr/d ] x 5.36 hr} / 10,000 bd.ft = 0.13 /bdft
Vat:12% 0.02 /bdft
35 of 124
DETAILED UNIT PRICE ANALYSIS (DUPA)
INSTALLATION OF STREET LIGHTS FOR BARANGAY SAYON
Item No./Description : B.5 Project Billboard/ Signboard
Unit of Measurement : ea
Output : 1
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
20.11
Minor Tools (10% of labor cost)
F. Materials
A. Labor
B. Equipment
F. Materials
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
37,089.78
a. Mobilization/ Demobilization (.75% of Total Civil Works)
F. Materials
No. of
No. of
Designation Person/ Hourly Rate Amount (PhP)
Hour/s
s
A. Labor
F. Materials
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor
F. Materials
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Gravel m3 0 1,500.00 -
b. Sand m3 0 1,500.00 -
c. Portland Cement bag 0.00 315.00 -
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
a. Exhaust Fan (Wall Mounted, Industrial Type) set 1.00 23,000.00 23,000.00
with complete accessories
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.79% 179,400.00
Part II Other General Requirements 1.32% 298,011.60
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.06% 465,674.32
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 41.15% 9,322,038.01
PART C FINISHING WORKS 41.88% 9,488,671.47
PART D PLUMBING/SANITARY WORKS 8.30% 1,879,763.91
PART E ELECTRICAL WORKS 4.51% 1,022,805.76
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 6.00 mo - - 179,400.00 179,400.00 8% 14,352.00 23,250.24 217,002.24
#REF! Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 179,400.00 179,400.00 14,352.00 23,250.24 217,002.24
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 4,219.35 701.16 70.12 4,990.63 20% 998.13 718.65 6,707.41
#REF! Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 lot 137,035.54 5,871.36 - 142,906.90 8% 11,432.55 18,520.73 172,860.18
#REF! Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 150,114.07 150,114.07 8% 12,009.13 19,454.78 181,577.98
#REF! Mobilization/ Demobilization
As Evaluated
As Submitted 141,254.89 6,572.52 150,184.18 298,011.60 24,439.81 38,694.16 361,145.57
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 413.71 m3 - 4,050.84 90,945.52 94,996.36 20% 18,999.27 13,679.48 127,675.11
#REF! Structure Excavation
As Evaluated
As Submitted #REF! 257.76 m3 - 5,129.79 33,125.91 38,255.70 20% 7,651.14 5,508.82 51,415.66
#REF! Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 335.90 m3 168,999.69 6,684.89 43,168.03 218,852.61 20% 43,770.52 31,514.78 294,137.91
#REF! Embankment from Borrow
As Evaluated
As Submitted #REF! 90.34 m3 92,722.72 14,742.74 6,104.20 113,569.65 20% 22,713.93 16,354.03 152,637.61
#REF! Gravel Fill
As Evaluated
As Submitted 261,722.40 30,608.26 173,343.65 465,674.32 93,134.86 67,057.11 625,866.29
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 384.71 m3 2,120,502.28 45,575.73 81,398.22 2,247,476.23 20% 449,495.25 323,636.58 3,020,608.06
#REF! Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 68,853.89 kg 5,260,751.34 398,400.40 192,181.69 5,851,333.43 20% 1,170,266.69 842,592.01 7,864,192.13
#REF! Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,577.60 m2 559,407.22 424,623.97 239,197.16 1,223,228.35 20% 244,645.67 176,144.88 1,644,018.90
#REF! Forms and Falseworks
As Evaluated
As Submitted 7,940,660.85 868,600.10 512,777.07 9,322,038.01 1,864,407.61 1,342,373.47 12,528,819.09
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 300.27 L 113,952.46 12,018.58 1,201.86 127,172.91 20% 25,434.58 18,312.90 170,920.39
#REF! Soil Poisoning
As Evaluated
As Submitted 113,952.46 12,018.58 1,201.86 127,172.91 25,434.58 18,312.90 170,920.39
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 285.37 m2 213,274.69 23,736.07 15,205.93 252,216.69 20% 50,443.34 36,319.20 338,979.23
#REF! 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 961.80 m2 997,044.68 96,225.37 61,644.42 1,154,914.47 20% 230,982.89 166,307.68 1,552,205.04
#REF! 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 1,210,319.37 119,961.44 76,850.35 1,407,131.16 281,426.23 202,626.88 1,891,184.27
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s 433,002.94 50,834.10 35.06 483,872.10 20% 96,774.42 69,677.58 650,324.10
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 70.87 m 2
57,082.95 46,010.38 4,601.04 107,694.37 20% 21,538.87 15,507.99 144,741.23
#REF! Jalousie Window
As Evaluated
As Submitted #REF! 146.88 m 2
331,658.71 143,036.64 94,067.66 568,763.02 20% 113,752.60 81,901.87 764,417.49
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 65.28 m2 64,898.65 7,151.83 4,703.38 76,753.87 20% 15,350.77 11,052.56 103,157.20
1005(5) Window Grilles
As Evaluated
As Submitted #REF! 43.00 set 69,230.00 - - 69,230.00 20% 13,846.00 9,969.12 93,045.12
#REF! Locksets
As Evaluated
As Submitted #REF! 172.00 pc 29,670.00 - - 29,670.00 20% 5,934.00 4,272.48 39,876.48
#REF! Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 42,780.00 7,534.56 753.46 51,068.02 20% 10,213.60 7,353.79 68,635.41
#REF! Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 1,028,323.26 254,567.51 104,160.60 1,387,051.38 277,410.26 199,735.39 1,864,197.03
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,161.01 m2 327,358.90 50,145.88 5,014.59 382,519.37 20% 76,503.87 55,082.79 514,106.03
#REF! Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 4,355.83 m2 535,997.40 219,472.70 21,947.27 777,417.37 20% 155,483.47 111,948.10 1,044,848.94
#REF! Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 32,539.47 2,280.61 3,442.20 38,262.28 20% 7,652.46 5,509.77 51,424.51
#REF! 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 144.00 m 368,883.66 4,975.88 7,510.25 381,369.79 20% 76,273.96 54,917.25 512,561.00
#REF! 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 661.00 m2 472,532.04 114,938.49 11,493.85 598,964.38 20% 119,792.88 86,250.87 805,008.13
#REF! Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 841.24 m2 137,132.64 32,702.45 3,270.24 173,105.33 20% 34,621.07 24,927.17 232,653.57
#REF! Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m2 90,833.57 49,361.26 4,936.13 145,130.95 20% 29,026.19 20,898.86 195,056.00
#REF! Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m2 39,017.17 15,160.60 1,516.06 55,693.83 20% 11,138.77 8,019.91 74,852.51
#REF! Unglazed Tiles
As Evaluated
As Submitted 2,004,294.85 489,037.86 59,130.58 2,552,463.30 510,492.67 367,554.72 3,430,510.69
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,943.76 m2 928,271.28 556,643.83 55,664.38 1,540,579.49 20% 308,115.90 221,843.45 2,070,538.84
#REF! Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 247.39 m 2
31,330.11 30,949.93 3,094.99 65,375.03 20% 13,075.01 9,414.00 87,864.04
#REF! Wood Painting
As Evaluated
As Submitted #REF! 125.09 m 2
29,447.96 14,788.77 1,478.88 45,715.60 20% 9,143.12 6,583.05 61,441.77
#REF! Metal Painting
As Evaluated
As Submitted 989,049.35 602,382.53 60,238.25 1,651,670.12 330,334.03 237,840.50 2,219,844.65
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 841.24 m2 561,698.51 87,584.64 8,758.46 658,041.62 20% 131,608.32 94,757.99 884,407.93
#REF! Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 64.20 m 22,129.07 1,125.36 112.54 23,366.96 20% 4,673.39 3,364.84 31,405.19
#REF! Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 13,759.38 459.38 45.94 14,264.70 20% 2,852.94 2,054.12 19,171.76
#REF! Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 128.40 m 79,390.88 1,907.39 190.74 81,489.01 20% 16,297.80 11,734.42 109,521.23
#REF! Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 7,703.59 kg 529,660.72 38,722.29 102,550.91 670,933.92 20% 134,186.78 96,614.48 901,735.18
#REF! Structural Steel, Trusses
As Evaluated
As Submitted #REF! 10,028.53 kg 667,503.16 39,803.67 86,248.68 793,555.51 20% 158,711.10 114,271.99 1,066,538.60
#REF! Structural Steel, Purlins
As Evaluated
As Submitted #REF! 128.40 m 28,062.78 2,397.51 239.75 30,700.05 20% 6,140.01 4,420.81 41,260.87
#REF! Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 17,254.92 3,742.82 374.28 21,372.02 20% 4,274.40 3,077.57 28,723.99
#REF! Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 293.65 kg 13,431.58 3,961.05 396.11 17,788.74 20% 3,557.75 2,561.58 23,908.07
#REF! Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 628.56 kg 29,612.91 8,478.67 847.87 38,939.44 20% 7,787.89 5,607.28 52,334.61
#REF! Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 52.00 pc 11,362.00 1,367.26 1.37 12,730.63 20% 2,546.13 1,833.21 17,109.97
#REF! Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,973,865.90 189,550.07 199,766.65 2,363,182.60 472,636.51 340,298.29 3,176,117.40
Sub-Total C.6
As Evaluated
As Submitted 7,319,805.21 1,667,517.99 501,348.30 9,488,671.47 1,897,734.28 1,366,368.68 12,752,774.43
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 61,935.78 7,997.18 799.72 70,732.68 20% 14,146.54 10,185.51 95,064.73
#REF! Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 36,418.49 5,565.61 556.56 42,540.65 20% 8,508.13 6,125.85 57,174.63
#REF! Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 222,670.40 33,925.50 3,392.55 259,988.45 20% 51,997.69 37,438.34 349,424.48
#REF! Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 238,609.25 28,879.03 2,887.90 270,376.18 20% 54,075.24 38,934.17 363,385.59
#REF! Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 98,649.30 15,975.50 1,597.55 116,222.35 20% 23,244.47 16,736.02 156,202.84
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 30.00 units 25,378.48 5,258.70 9,486.93 40,124.11 20% 8,024.82 5,777.87 53,926.80
#REF! Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 1,006,426.81 66,684.25 6,668.43 1,079,779.49 20% 215,955.90 155,488.25 1,451,223.64
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,690,088.50 164,285.76 25,389.64 1,879,763.91 375,952.79 270,686.01 2,526,402.71
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 252,555.11 13,240.03 1,324.00 267,119.14 20% 53,423.83 38,465.16 359,008.13
#REF! Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 264,123.72 15,362.24 1,536.22 281,022.18 20% 56,204.44 40,467.19 377,693.81
#REF! Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 289,732.15 3,242.10 324.21 293,298.46 20% 58,659.69 42,234.98 394,193.13
#REF! Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 138,066.70 7,781.04 778.10 146,625.84 20% 29,325.17 21,114.12 197,065.13
#REF! Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 31,261.60 3,162.31 316.23 34,740.14 20% 6,948.03 5,002.58 46,690.75
#REF! Fire Alarm System
As Evaluated
As Submitted 975,739.28 42,787.72 4,278.77 1,022,805.760 204,561.160 147,284.030 1,374,650.950
TOTAL OF PART E
As Evaluated
As Submitted 18,188,016.25 2,773,799.83 1,217,137.43 22,178,953.470 4,435,790.700 3,193,769.300 29,808,513.470
TOTAL OF PART III
As Evaluated
As Submitted 18,329,271.14 2,780,372.35 1,546,721.61 22,656,365.070 4,474,582.510 3,255,713.700 30,386,661.280
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.88% 174,416.67
Part II Other General Requirements 1.34% 266,902.71
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.02% 403,085.90
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 40.71% 8,109,993.87
PART C FINISHING WORKS 41.42% 8,249,700.71
PART D PLUMBING/SANITARY WORKS 8.94% 1,781,358.80
PART E ELECTRICAL WORKS 4.69% 933,590.76
`
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.83 mo - - 174,416.67 174,416.67 8% 13,953.33 22,604.40 210,974.40
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 174,416.67 174,416.67 13,953.33 22,604.40 210,974.40
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 4,219.35 701.16 70.12 4,990.63 20% 998.13 718.65 6,707.41
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 L.S. 124,212.14 5,871.36 - 130,083.50 8% 10,406.68 16,858.82 157,349.00
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 131,828.58 131,828.58 8% 10,546.29 17,084.98 159,459.85
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 128,431.49 6,572.52 131,898.69 266,902.71 21,951.10 34,662.45 323,516.26
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 365.45 m3 - 3,578.30 80,336.56 83,914.87 20% 16,782.97 12,083.74 112,781.58
803(1)a Structure Excavation
As Evaluated
804(1)a As Submitted #REF! 223.43 m3 - 4,446.57 28,714.00 33,160.58 20% 6,632.12 4,775.12 44,567.82
Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 288.09 m3 144,945.28 5,733.40 37,023.75 187,702.43 20% 37,540.49 27,029.15 252,272.07
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 78.20 m3 80,262.53 12,761.59 5,283.91 98,308.02 20% 19,661.60 14,156.35 132,125.97
804(4) Gravel Fill
As Evaluated
As Submitted 225,207.81 26,519.87 151,358.23 403,085.90 80,617.18 58,044.36 541,747.44
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 335.41 m3 1,848,763.15 39,735.27 70,967.17 1,959,465.58 20% 391,893.12 282,163.04 2,633,521.74
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 59,947.73 kg 4,580,280.08 346,867.84 167,323.24 5,094,471.16 20% 1,018,894.23 733,603.85 6,846,969.24
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,225.34 m2 482,956.42 366,593.18 206,507.53 1,056,057.13 20% 211,211.43 152,072.23 1,419,340.79
903(2) Forms and Falseworks
As Evaluated
As Submitted 6,911,999.65 753,196.28 444,797.93 8,109,993.87 1,621,998.78 1,167,839.12 10,899,831.77
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 259.98 L 98,662.41 10,405.94 1,040.59 110,108.94 20% 22,021.79 15,855.69 147,986.42
1000(1) Soil Poisoning
As Evaluated
As Submitted 98,662.41 10,405.94 1,040.59 110,108.94 22,021.79 15,855.69 147,986.42
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 267.94 m2 200,248.17 22,286.30 14,277.17 236,811.65 20% 47,362.33 34,100.88 318,274.86
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 838.99 m2 869,734.37 83,938.58 53,773.19 1,007,446.13 20% 201,489.23 145,072.24 1,354,007.60
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 1,069,982.54 106,224.88 68,050.36 1,244,257.78 248,851.56 179,173.12 1,672,282.46
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 371,477.02 45,575.40 4,557.54 421,609.97 20% 84,321.99 60,711.84 566,643.80
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 59.98 m2 48,311.49 38,940.35 3,894.03 91,145.87 20% 18,229.17 13,125.00 122,500.04
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 122.40 m2 276,382.26 119,197.20 78,389.72 473,969.18 20% 94,793.84 68,251.56 637,014.58
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 54.40 m2 54,082.21 5,959.86 3,919.49 63,961.56 20% 12,792.31 9,210.46 85,964.33
1005(5) Window Grills
As Evaluated
As Submitted #REF! 39.00 set 62,790.00 - - 62,790.00 20% 12,558.00 9,041.76 84,389.76
1004(2)a Locksets
As Evaluated
As Submitted #REF! 156.00 pc 26,910.00 - - 26,910.00 20% 5,382.00 3,875.04 36,167.04
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 35,650.00 6,278.80 627.88 42,556.68 20% 8,511.34 6,128.16 57,196.18
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 875,602.99 215,951.61 91,388.66 1,182,943.26 236,588.65 170,343.82 1,589,875.73
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,000.20 m2 282,016.84 43,200.23 4,320.02 329,537.10 20% 65,907.42 47,453.34 442,897.86
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,825.21 m2 470,703.09 192,736.90 19,273.69 682,713.67 20% 136,542.73 98,310.77 917,567.17
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 32,539.47 2,280.61 3,442.20 38,262.28 20% 7,652.46 5,509.77 51,424.51
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 127.60 m 326,871.91 4,409.19 6,654.92 337,936.01 20% 67,587.20 48,662.79 454,186.00
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 565.91 m 2
404,554.63 98,403.69 9,840.37 512,798.69 20% 102,559.74 73,843.01 689,201.44
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 723.31 m2 117,908.57 28,118.03 2,811.80 148,838.40 20% 29,767.68 21,432.73 200,038.81
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m2 90,833.57 49,361.26 4,936.13 145,130.95 20% 29,026.19 20,898.86 195,056.00
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m 2
39,017.17 15,160.60 1,516.06 55,693.83 20% 11,138.77 8,019.91 74,852.51
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,764,445.25 433,670.50 52,795.18 2,250,910.93 450,182.19 324,131.18 3,025,224.30
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,336.71 m2 814,287.77 488,292.89 48,829.29 1,351,409.96 20% 270,281.99 194,603.03 1,816,294.98
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 218.61 m 2
27,685.34 27,349.38 2,734.94 57,769.66 20% 11,553.93 8,318.83 77,642.42
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 112.50 m2 26,484.10 13,300.31 1,330.03 41,114.44 20% 8,222.89 5,920.48 55,257.81
1032(1)c Metal Painting
As Evaluated
As Submitted 868,457.21 528,942.59 52,894.26 1,450,294.06 290,058.81 208,842.34 1,949,195.21
Sub-Total C.5
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
C.6 Roof Framing and Roofing Works
As Submitted #REF! 723.31 m2 482,955.73 75,306.42 7,530.64 565,792.80 20% 113,158.56 81,474.16 760,425.52
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 55.20 m 19,026.86 967.60 96.76 20,091.22 20% 4,018.24 2,893.14 27,002.60
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 13,759.38 459.38 45.94 14,264.70 20% 2,852.94 2,054.12 19,171.76
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 110.40 m 68,261.31 1,640.00 164.00 70,065.32 20% 14,013.06 10,089.41 94,167.79
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 6,440.06 kg 442,786.65 32,371.13 85,730.68 560,888.46 20% 112,177.69 80,767.94 753,834.09
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 8,515.07 kg 566,766.62 33,796.68 73,232.43 673,795.74 20% 134,759.15 97,026.59 905,581.48
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 110.40 m 24,128.75 2,061.41 206.14 26,396.30 20% 5,279.26 3,801.07 35,476.63
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 17,254.92 3,742.82 374.28 21,372.02 20% 4,274.40 3,077.57 28,723.99
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 248.16 kg 11,350.86 3,347.44 334.74 15,033.05 20% 3,006.61 2,164.76 20,204.42
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 528.07 kg 24,878.59 7,123.15 712.32 32,714.06 20% 6,542.81 4,710.82 43,967.69
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 44.00 pc 9,614.00 1,156.91 1.16 10,772.07 20% 2,154.41 1,551.18 14,477.66
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,680,783.68 161,972.96 168,429.09 2,011,185.74 402,237.13 289,610.76 2,703,033.63
Sub-Total C.6
As Evaluated
As Submitted 6,357,934.08 1,457,168.48 434,598.15 8,249,700.71 1,649,940.13 1,187,956.91 11,087,597.75
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 58,263.03 7,564.90 756.49 66,584.42 20% 13,316.88 9,588.16 89,489.46
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 33,718.88 5,133.33 513.33 39,365.54 20% 7,873.11 5,668.64 52,907.29
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 199,334.23 30,425.25 3,042.53 232,802.00 20% 46,560.40 33,523.49 312,885.89
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 238,261.49 28,747.56 2,874.76 269,883.80 20% 53,976.76 38,863.27 362,723.83
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 84,032.12 13,731.75 1,373.18 99,137.05 20% 19,827.41 14,275.74 133,240.20
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 26.00 units 21,994.68 4,557.54 455.75 27,007.97 20% 5,401.59 3,889.15 36,298.71
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 975,792.19 64,350.75 6,435.08 1,046,578.02 20% 209,315.60 150,707.23 1,406,600.85
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,611,396.61 154,511.08 15,451.11 1,781,358.80 356,271.75 256,515.68 2,394,146.23
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 214,950.11 10,977.08 1,097.71 227,024.90 20% 45,404.98 32,691.59 305,121.47
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 246,853.14 13,128.02 1,312.80 261,293.96 20% 52,258.79 37,626.33 351,179.08
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 280,778.60 5,187.36 518.74 286,484.69 20% 57,296.94 41,253.80 385,035.43
1102(21) Panel Board
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 1.00 l.s. 116,676.70 6,700.34 670.03 124,047.07 20% 24,809.41 17,862.78 166,719.26
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 31,261.60 3,162.31 316.23 34,740.14 20% 6,948.03 5,002.58 46,690.75
1208(1) Fire Alarm System
As Evaluated
As Submitted 890,520.14 39,155.11 3,915.51 933,590.760 186,718.150 134,437.080 1,254,745.990
TOTAL OF PART E
As Evaluated
As Submitted 15,997,058.30 2,430,550.82 1,050,120.93 19,477,730.040 3,895,545.990 2,804,793.150 26,178,069.180
TOTAL OF PART III
As Evaluated
As Submitted 16,125,489.79 2,437,123.34 1,356,436.29 19,919,049.420 3,931,450.420 2,862,060.000 26,712,559.840
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.87% 149,500.00
Part II Other General Requirements 1.38% 235,229.87
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.99% 339,231.05
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 40.37% 6,897,949.72
PART C FINISHING WORKS 41.00% 7,005,704.85
PART D PLUMBING/SANITARY WORKS 9.66% 1,650,672.78
PART E ELECTRICAL WORKS 4.73% 808,079.22
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.00 mo - - 149,500.00 149,500.00 8% 11,960.00 19,375.20 180,835.20
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 149,500.00 149,500.00 11,960.00 19,375.20 180,835.20
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 4,219.35 701.16 70.12 4,990.63 20% 998.13 718.65 6,707.41
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 112,329.46 4,892.80 - 117,222.26 8% 9,377.78 15,192.00 141,792.04
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 113,016.98 113,016.98 8% 9,041.36 14,647.00 136,705.34
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 116,548.81 5,593.96 113,087.10 235,229.87 19,417.27 30,557.65 285,204.79
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 313.84 m3 - 3,072.96 68,991.18 72,064.14 20% 14,412.83 10,377.24 96,854.21
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 185.75 m3 - 3,696.69 23,871.57 27,568.26 20% 5,513.65 3,969.83 37,051.74
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 240.28 m3 120,890.87 4,781.91 30,879.47 156,552.26 20% 31,310.45 22,543.53 210,406.24
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 66.06 m3 67,802.33 10,780.44 4,463.62 83,046.39 20% 16,609.28 11,958.68 111,614.35
804(4) Gravel Fill
As Evaluated
As Submitted 188,693.21 22,332.01 128,205.85 339,231.05 67,846.21 48,849.28 455,926.54
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 286.11 m3 1,577,024.01 33,894.81 60,536.11 1,671,454.93 20% 334,290.99 240,689.51 2,246,435.43
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 51,041.57 kg 3,899,808.83 295,335.27 142,464.79 4,337,608.88 20% 867,521.78 624,615.68 5,829,746.34
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,873.07 m2 406,505.62 308,562.39 173,817.90 888,885.91 20% 177,777.18 127,999.57 1,194,662.66
903(2) Forms and Falseworks
As Evaluated
As Submitted 5,883,338.46 637,792.47 376,818.80 6,897,949.72 1,379,589.95 993,304.76 9,270,844.43
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 219.68 L 83,368.56 8,792.90 879.29 93,040.74 20% 18,608.15 13,397.87 125,046.76
1000(1) Soil Poisoning
As Evaluated
As Submitted 83,368.56 8,792.90 879.29 93,040.74 18,608.15 13,397.87 125,046.76
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 250.52 m2 187,229.13 20,837.37 13,348.95 221,415.45 20% 44,283.09 31,883.82 297,582.36
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 716.18 m2
742,424.06 71,651.78 45,901.96 859,977.80 20% 171,995.56 123,836.80 1,155,810.16
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 929,653.19 92,489.15 59,250.91 1,081,393.25 216,278.65 155,720.62 1,453,392.52
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 309,951.11 40,316.70 4,031.67 354,299.48 20% 70,859.90 51,019.13 476,178.51
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 49.10 m2 39,548.09 31,876.81 3,187.68 74,612.58 20% 14,922.52 10,744.21 100,279.31
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 97.92 m 2
221,105.81 95,357.76 62,711.78 379,175.34 20% 75,835.07 54,601.25 509,611.66
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 43.52 m2 43,265.77 4,767.89 3,135.59 51,169.25 20% 10,233.85 7,368.37 68,771.47
1005 (5) Window Grills
As Evaluated
As Submitted #REF! 35.00 set 56,350.00 - - 56,350.00 20% 11,270.00 8,114.40 75,734.40
1004(2)a Locksets
As Evaluated
As Submitted #REF! 140.00 pc 24,150.00 - - 24,150.00 20% 4,830.00 3,477.60 32,457.60
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 28,520.00 5,023.04 502.30 34,045.34 20% 6,809.07 4,902.53 45,756.94
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 722,890.77 177,342.20 73,569.02 973,801.99 194,760.41 140,227.49 1,308,789.89
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 839.37 m2 236,669.14 36,253.73 3,625.37 276,548.25 20% 55,309.65 39,822.95 371,680.85
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,294.60 m2 405,410.00 166,001.60 16,600.16 588,011.76 20% 117,602.35 84,673.69 790,287.80
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 32,539.47 2,280.61 3,442.20 38,262.28 20% 7,652.46 5,509.77 51,424.51
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 111.20 m 284,860.16 3,842.49 5,799.58 294,502.23 20% 58,900.45 42,408.32 395,811.00
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 470.83 m2 336,584.36 81,870.63 8,187.06 426,642.06 20% 85,328.41 61,436.46 573,406.93
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 605.38 m2 98,684.51 23,533.60 2,353.36 124,571.47 20% 24,914.29 17,938.29 167,424.05
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m2 90,833.57 49,361.26 4,936.13 145,130.95 20% 29,026.19 20,898.86 195,056.00
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m 2
39,017.17 15,160.60 1,516.06 55,693.83 20% 11,138.77 8,019.91 74,852.51
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,524,598.38 378,304.52 46,459.92 1,949,362.83 389,872.57 280,708.25 2,619,943.65
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 3,729.66 m2 700,304.27 419,941.96 41,994.20 1,162,240.42 20% 232,448.08 167,362.62 1,562,051.12
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 189.83 m2 24,040.56 23,748.84 2,374.88 50,164.29 20% 10,032.86 7,223.66 67,420.81
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 99.91 m 2
23,520.23 11,811.86 1,181.19 36,513.28 20% 7,302.66 5,257.91 49,073.85
1032(1)c Metal Painting
As Evaluated
As Submitted 747,865.07 455,502.65 45,550.27 1,248,917.99 249,783.60 179,844.19 1,678,545.78
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 605.38 m2 404,212.95 63,028.20 6,302.82 473,543.97 20% 94,708.79 68,190.33 636,443.09
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 46.20 m 15,924.65 809.84 80.98 16,815.48 20% 3,363.10 2,421.43 22,600.01
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 26.21 m 13,759.38 459.38 45.94 14,264.70 20% 2,852.94 2,054.12 19,171.76
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 92.40 m 57,131.75 1,372.61 137.26 58,641.62 20% 11,728.32 8,444.39 78,814.33
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 5,176.53 kg 355,912.58 26,019.96 68,910.45 450,842.99 20% 90,168.60 64,921.39 605,932.98
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 7,001.60 kg 466,029.43 27,789.66 60,216.08 554,035.17 20% 110,807.03 79,781.06 744,623.26
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 92.40 m 20,194.71 1,725.31 172.53 22,092.56 20% 4,418.51 3,181.33 29,692.40
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 17,254.92 3,742.82 374.28 21,372.02 20% 4,274.40 3,077.57 28,723.99
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 202.67 kg 9,270.15 2,733.82 273.38 12,277.35 20% 2,455.47 1,767.94 16,500.76
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 427.58 kg 20,144.28 5,767.64 576.76 26,488.68 20% 5,297.74 3,814.37 35,600.79
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 36.00 pc 7,866.00 946.57 0.95 8,813.51 20% 1,762.70 1,269.15 11,845.36
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,387,700.80 134,395.82 137,091.44 1,659,188.05 331,837.60 238,923.08 2,229,948.73
Sub-Total C.6
As Evaluated
As Submitted 5,396,076.76 1,246,827.24 362,800.85 7,005,704.85 1,401,140.98 1,008,821.50 9,415,667.33
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 53,235.69 6,916.48 691.65 60,843.81 20% 12,168.76 8,761.51 81,774.08
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 29,669.47 4,538.94 453.89 34,662.30 20% 6,932.46 4,991.37 46,586.13
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 169,995.05 25,937.75 2,593.78 198,526.58 20% 39,705.32 28,587.83 266,819.73
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 237,739.85 28,616.09 2,861.61 269,217.55 20% 53,843.51 38,767.33 361,828.39
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 77,029.37 12,475.25 1,247.53 90,752.14 20% 18,150.43 13,068.31 121,970.88
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 20.00 units 16,918.98 3,505.80 350.58 20,775.36 20% 4,155.07 2,991.65 27,922.08
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 911,427.61 58,606.75 5,860.68 975,895.04 20% 195,179.01 140,528.89 1,311,602.94
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,496,016.01 140,597.06 14,059.71 1,650,672.78 330,134.56 237,696.89 2,218,504.23
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 188,973.34 9,867.88 986.79 199,828.00 20% 39,965.60 28,775.23 268,568.83
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 176,776.79 9,928.25 992.83 187,697.87 20% 37,539.57 27,028.49 252,265.93
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 280,778.60 3,242.10 324.21 284,344.91 20% 56,868.98 40,945.67 382,159.56
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 95,286.70 5,619.64 561.96 101,468.30 20% 20,293.66 14,611.44 136,373.40
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 31,261.60 3,162.31 316.23 34,740.14 20% 6,948.03 5,002.58 46,690.75
1208(1) Fire Alarm System
As Evaluated
As Submitted 773,077.02 31,820.18 3,182.02 808,079.220 161,615.840 116,363.410 1,086,058.470
TOTAL OF PART E
As Evaluated
As Submitted 13,737,201.47 2,079,368.96 885,067.22 16,701,637.620 3,340,327.540 2,405,035.840 22,447,001.000
TOTAL OF PART III
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 13,853,750.28 2,084,962.92 1,147,654.31 17,086,367.490 3,371,704.810 2,454,968.690 22,913,040.990
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.18% 139,533.33
Part II Other General Requirements 1.50% 177,479.23
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.02% 238,727.17
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 41.26% 4,871,069.17
PART C FINISHING WORKS 43.02% 5,079,310.85
PART D PLUMBING/SANITARY WORKS 8.09% 955,069.67
PART E ELECTRICAL WORKS 2.92% 345,030.64
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted Err:509 4.67 mo - - 139,533.33 139,533.33 8% 11,162.67 18,083.52 168,779.52
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 139,533.33 139,533.33 11,162.67 18,083.52 168,779.52
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.06 1.00 ea 4,219.35 701.16 70.12 4,990.63 20% 998.13 718.65 6,707.41
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 1.25 1.00 l.s. 89,810.36 4,892.80 - 94,703.16 8% 7,576.25 12,273.53 114,552.94
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 77,785.44 77,785.44 8% 6,222.84 10,080.99 94,089.27
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 94,029.71 5,593.96 77,855.56 177,479.23 14,797.22 23,073.17 215,349.62
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted Err:509 244.62 m3 - 2,395.20 53,774.61 56,169.80 20% 11,233.96 8,088.45 75,492.21
803(1)a Structure Excavation
As Evaluated
As Submitted Err:509 139.08 m3 - 2,767.89 17,873.80 20,641.69 20% 4,128.34 2,972.40 27,742.43
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted Err:509 159.64 m3 80,318.87 3,177.06 20,516.06 104,012.00 20% 20,802.40 14,977.73 139,792.13
804(1)b Embankment from Borrow
As Evaluated
As Submitted Err:509 46.06 m3 47,274.83 7,516.61 3,112.24 57,903.68 20% 11,580.74 8,338.13 77,822.55
804(4) Gravel Fill
As Evaluated
As Submitted 127,593.71 15,856.76 95,276.70 238,727.17 47,745.44 34,376.71 320,849.32
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 2.14 201.23 m3 1,109,169.70 23,839.26 42,576.91 1,175,585.88 20% 235,117.18 169,284.37 1,579,987.43
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted Err:509 36,154.58 kg 2,762,374.87 209,196.59 100,912.93 3,072,484.40 20% 614,496.88 442,437.75 4,129,419.03
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted Err:509 1,312.79 m2 284,910.07 216,264.01 121,824.81 622,998.89 20% 124,599.78 89,711.84 837,310.51
903(2) Forms and Falseworks
As Evaluated
As Submitted 4,156,454.64 449,299.86 265,314.66 4,871,069.17 974,213.84 701,433.96 6,546,716.97
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted Err:509 159.89 L 60,678.25 6,399.75 639.97 67,717.97 20% 13,543.59 9,751.39 91,012.95
1000(1) Soil Poisoning
As Evaluated
As Submitted 60,678.25 6,399.75 639.97 67,717.97 13,543.59 9,751.39 91,012.95
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted Err:509 147.30 m2 110,086.42 12,251.89 7,848.88 130,187.19 20% 26,037.44 18,746.96 174,971.59
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted Err:509 522.79 m2 541,947.38 52,303.66 33,507.06 627,758.10 20% 125,551.62 90,397.17 843,706.89
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 652,033.80 64,555.55 41,355.93 757,945.29 151,589.06 109,144.13 1,018,678.48
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted Err:509 1.00 l.s. 225,039.36 26,293.50 2,629.35 253,962.21 20% 50,792.44 36,570.56 341,325.21
1010(4) Wooden Dooor
As Evaluated
As Submitted Err:509 34.93 m2 28,134.72 22,677.33 2,267.73 53,079.78 20% 10,615.96 7,643.49 71,339.23
1009(1)a Jalousie Window
As Evaluated
As Submitted Err:509 73.44 m2 165,829.36 71,518.32 47,033.83 284,381.51 20% 56,876.30 40,950.94 382,208.75
1005 (1) Steel Casement Window
As Evaluated
As Submitted Err:509 32.64 m2 32,449.33 3,575.92 2,351.69 38,376.93 20% 7,675.39 5,526.28 51,578.60
1005(5) Window Grill
As Evaluated
As Submitted Err:509 24.00 set 38,640.00 - - 38,640.00 20% 7,728.00 5,564.16 51,932.16
1004(2)a Locksets
As Evaluated
As Submitted Err:509 96.00 pc 16,560.00 - - 16,560.00 20% 3,312.00 2,384.64 22,256.64
1004(2)g Hinges
As Evaluated
As Submitted Err:509 1.00 l.s. 21,390.00 3,767.28 376.73 25,534.01 20% 5,106.80 3,676.90 34,317.71
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 528,042.76 127,832.35 54,659.33 710,534.44 142,106.89 102,316.97 954,958.30
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted Err:509 584.99 m2 164,944.04 25,266.65 2,526.67 192,737.36 20% 38,547.47 27,754.18 259,039.01
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted Err:509 2,313.83 m 2
284,723.43 116,584.56 11,658.46 412,966.45 20% 82,593.29 59,467.17 555,026.91
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted Err:509 33.00 m 16,269.73 1,140.31 1,721.10 19,131.14 20% 3,826.23 2,754.88 25,712.25
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted Err:509 92.12 m 235,983.07 3,183.18 4,804.47 243,970.73 20% 48,794.15 35,131.79 327,896.67
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted Err:509 332.94 m 2
238,010.32 57,893.53 5,789.35 301,693.19 20% 60,338.64 43,443.82 405,475.65
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted Err:509 434.28 m 2
70,793.07 16,882.24 1,688.22 89,363.54 20% 17,872.71 12,868.35 120,104.60
1038(1) Reflective Insulation
As Evaluated
As Submitted Err:509 71.55 m 2
56,266.70 30,576.75 3,057.67 89,901.13 20% 17,980.23 12,945.76 120,827.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted Err:509 20.05 m 2
15,435.96 5,997.83 599.78 22,033.57 20% 4,406.71 3,172.83 29,613.11
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,082,426.33 257,525.05 31,845.73 1,371,797.11 274,359.43 197,538.78 1,843,695.32
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted Err:509 2,553.91 m2 479,538.10 287,558.10 28,755.81 795,852.02 20% 159,170.40 114,602.69 1,069,625.11
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted Err:509 133.27 m2 16,877.66 16,672.85 1,667.29 35,217.80 20% 7,043.56 5,071.36 47,332.72
1032(1)b Wood Painting
As Evaluated
As Submitted Err:509 62.73 m2 14,767.53 7,416.25 741.63 22,925.41 20% 4,585.08 3,301.26 30,811.75
1032(1)c Metal Painting
As Evaluated
As Submitted 511,183.30 311,647.21 31,164.72 853,995.23 170,799.04 122,975.31 1,147,769.58
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted Err:509 434.28 m2 289,969.91 45,214.49 4,521.45 339,705.84 20% 67,941.17 48,917.64 456,564.65
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted Err:509 32.90 m 11,340.28 576.70 57.67 11,974.66 20% 2,394.93 1,724.35 16,093.94
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted Err:509 26.21 m 13,761.03 459.44 45.94 14,266.41 20% 2,853.28 2,054.36 19,174.05
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted Err:509 65.80 m 40,684.73 977.46 97.75 41,759.94 20% 8,351.99 6,013.43 56,125.36
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted Err:509 3,535.91 kg 243,111.67 17,773.34 47,070.37 307,955.38 20% 61,591.08 44,345.58 413,892.04
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted Err:509 5,170.61 kg 344,157.97 20,522.38 44,468.96 409,149.30 20% 81,829.86 58,917.50 549,896.66
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted Err:509 65.80 m 14,381.08 1,228.63 122.86 15,732.58 20% 3,146.52 2,265.49 21,144.59
1003(11) Fascia Board
As Evaluated
As Submitted Err:509 277.47 kg 17,254.82 3,742.80 374.28 21,371.90 20% 4,274.38 3,077.55 28,723.83
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted Err:509 146.82 kg 6,715.56 1,980.46 198.05 8,894.07 20% 1,778.81 1,280.75 11,953.63
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted Err:509 314.91 kg 14,836.14 4,247.83 424.78 19,508.75 20% 3,901.75 2,809.26 26,219.76
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted Err:509 26.00 pc 5,681.00 683.63 0.68 6,365.31 20% 1,273.06 916.60 8,554.97
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted Err:509 1.00 l.s. 80,435.45 12,895.37 27,305.85 120,636.67 20% 24,127.33 17,371.68 162,135.68
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 1,082,329.63 110,302.54 124,688.64 1,317,320.81 263,464.16 189,694.19 1,770,479.16
Sub-Total C.6
As Evaluated
As Submitted 3,916,694.08 878,262.44 284,354.33 5,079,310.85 1,015,862.17 731,420.77 6,826,593.79
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted Err:509 1.00 l.s. 25,908.47 3,242.10 324.21 29,474.78 20% 5,894.96 4,244.37 39,614.11
1001(8) Sewer Line Works
As Evaluated
As Submitted Err:509 1.00 l.s. 6,669.70 1,026.67 102.67 7,799.04 20% 1,559.81 1,123.06 10,481.91
1002(6) Cold Water Line Works
As Evaluated
As Submitted Err:509 1.00 l.s. 81,064.44 12,385.50 1,238.55 94,688.49 20% 18,937.70 13,635.14 127,261.33
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted Err:509 1.00 l.s. 120,729.47 14,373.78 1,437.38 136,540.63 20% 27,308.13 19,661.85 183,510.61
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted Err:509 1.00 l.s. 65,652.92 10,770.00 1,077.00 77,499.92 20% 15,499.98 11,159.99 104,159.89
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted Err:509 16.00 units 13,535.19 2,804.64 280.46 16,620.29 20% 3,324.06 2,393.32 22,337.67
1001(6)b1 Catch basin
As Evaluated
As Submitted Err:509 1.00 lot 550,883.29 37,784.75 3,778.48 592,446.52 20% 118,489.30 85,312.30 796,248.12
SPL-2 Fire Protection System
As Evaluated
As Submitted 864,443.48 82,387.44 8,238.74 955,069.67 191,013.94 137,530.03 1,283,613.64
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted Err:509 1.00 l.s. 103,351.88 7,512.92 751.29 111,616.09 20% 22,323.22 16,072.72 150,012.03
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted Err:509 1.00 l.s. 81,392.02 5,985.68 598.57 87,976.27 20% 17,595.25 12,668.58 118,240.10
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted Err:509 1.00 l.s. 41,923.25 2,377.54 237.75 44,538.54 20% 8,907.71 6,413.55 59,859.80
1102(21) Panel Board
As Evaluated
As Submitted Err:509 1.00 l.s. 69,672.75 4,106.66 410.67 74,190.08 20% 14,838.02 10,683.37 99,711.47
1003(1) Lighting Fixtures
As Evaluated
As Submitted Err:509 1.00 l.s. 24,016.60 2,448.24 244.82 26,709.66 20% 5,341.93 3,846.19 35,897.78
1208(1) Fire Alarm System
As Evaluated
As Submitted 320,356.50 22,431.04 2,243.10 345,030.640 69,006.130 49,684.410 463,721.180
TOTAL OF PART E
As Evaluated
As Submitted 9,385,542.41 1,448,237.54 655,427.54 11,489,207.500 2,297,841.520 1,654,445.880 15,441,494.900
TOTAL OF PART III
As Evaluated
As Submitted 9,479,572.12 1,453,831.50 872,816.44 11,806,220.060 2,323,801.410 1,695,602.570 15,825,624.040
GRAND TOTAL
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.33% 119,600.00
Part II Other General Requirements 1.61% 144,825.02
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.96% 176,373.15
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 40.62% 3,659,022.64
PART C FINISHING WORKS 42.50% 3,828,028.85
PART D PLUMBING/SANITARY WORKS 9.00% 811,095.90
PART E ELECTRICAL WORKS 2.98% 268,637.93
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.00 mo - - 119,600.00 119,600.00 8% 9,568.00 15,500.16 144,668.16
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 119,600.00 119,600.00 9,568.00 15,500.16 144,668.16
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 4,219.35 701.16 70.12 4,990.63 20% 998.13 718.65 6,707.41
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 76,734.52 3,914.24 - 80,648.76 8% 6,451.90 10,452.08 97,552.74
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 59,185.63 59,185.63 8% 4,734.85 7,670.46 71,590.94
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 80,953.87 4,615.40 59,255.75 144,825.02 12,184.88 18,841.19 175,851.09
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 196.98 m3 - 1,928.73 43,301.95 45,230.68 20% 9,046.14 6,513.22 60,790.04
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 105.37 m3 - 2,097.01 13,541.58 15,638.59 20% 3,127.72 2,251.96 21,018.27
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 111.83 m3 56,264.47 2,225.58 14,371.78 72,861.83 20% 14,572.37 10,492.10 97,926.30
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 33.92 m3 34,814.64 5,535.46 2,291.95 42,642.05 20% 8,528.41 6,140.46 57,310.92
804(4) Gravel Fill
As Evaluated
As Submitted 91,079.11 11,786.78 73,507.25 176,373.15 35,274.64 25,397.74 237,045.53
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 151.93 m3 837,430.56 17,998.80 32,145.86 887,575.22 20% 177,515.04 127,810.83 1,192,901.09
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 27,248.42 kg 2,081,903.61 157,664.03 76,054.49 2,315,622.12 20% 463,124.42 333,449.58 3,112,196.12
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 960.52 m2 208,458.19 158,232.39 89,134.72 455,825.30 20% 91,165.06 65,638.84 612,629.20
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,127,792.36 333,895.22 197,335.06 3,659,022.64 731,804.52 526,899.25 4,917,726.41
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 115.60 L 43,870.20 4,627.00 462.70 48,959.90 20% 9,791.98 7,050.23 65,802.11
1000(1) Soil Poisoning
As Evaluated
As Submitted 43,870.20 4,627.00 462.70 48,959.90 9,791.98 7,050.23 65,802.11
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 129.91 m2 97,089.80 10,805.46 6,922.25 114,817.50 20% 22,963.50 16,533.72 154,314.72
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 399.98 m2 414,637.07 40,016.87 25,635.83 480,289.76 20% 96,057.95 69,161.73 645,509.44
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 511,726.86 50,822.32 32,558.08 595,107.26 119,021.45 85,695.45 799,824.16
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 163,513.44 20,158.35 2,015.84 185,687.63 20% 37,137.53 26,739.02 249,564.18
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 24.05 m2 19,371.31 15,613.79 1,561.38 36,546.49 20% 7,309.30 5,262.69 49,118.48
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 48.96 m2 110,552.90 47,678.88 31,355.89 189,587.67 20% 37,917.53 27,300.62 254,805.82
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 21.76 m2 21,632.88 2,383.94 1,567.79 25,584.62 20% 5,116.92 3,684.18 34,385.72
1005(5) Window Grill
As Evaluated
As Submitted #REF! 20.00 set 32,200.00 - - 32,200.00 20% 6,440.00 4,636.80 43,276.80
1004(2)a Locksets
As Evaluated
As Submitted #REF! 80.00 pc 13,800.00 - - 13,800.00 20% 2,760.00 1,987.20 18,547.20
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 14,260.00 2,511.52 251.15 17,022.67 20% 3,404.53 2,451.26 22,878.46
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 375,330.54 88,346.49 36,752.05 500,429.08 100,085.81 72,061.77 672,576.66
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 424.17 m2 119,599.16 18,320.58 1,832.06 139,751.80 20% 27,950.36 20,124.26 187,826.42
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,783.22 m 2
219,430.35 89,849.26 8,984.93 318,264.53 20% 63,652.91 45,830.09 427,747.53
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 16,269.73 1,140.31 1,721.10 19,131.14 20% 3,826.23 2,754.88 25,712.25
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 73.42 m 188,079.43 2,537.01 3,829.18 194,445.63 20% 38,889.13 28,000.17 261,334.93
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 237.86 m 2
170,040.05 41,360.47 4,136.05 215,536.56 20% 43,107.31 31,037.26 289,681.13
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 315.48 m 2
51,427.18 12,264.00 1,226.40 64,917.58 20% 12,983.52 9,348.13 87,249.23
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
56,266.70 30,576.75 3,057.67 89,901.13 20% 17,980.23 12,945.76 120,827.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
15,435.96 5,997.83 599.78 22,033.57 20% 4,406.71 3,172.83 29,613.11
1018(2) Unglazed Tiles
As Evaluated
As Submitted 836,548.57 202,046.20 25,387.17 1,063,981.94 212,796.40 153,213.38 1,429,991.72
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,946.86 m2 365,554.60 219,207.17 21,920.72 606,682.48 20% 121,336.50 87,362.28 815,381.26
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 104.49 m2 13,232.89 13,072.31 1,307.23 27,612.42 20% 5,522.48 3,976.19 37,111.09
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 50.14 m2 11,803.67 5,927.80 592.78 18,324.25 20% 3,664.85 2,638.69 24,627.79
1032(1)c Metal Painting
As Evaluated
As Submitted 390,591.15 238,207.27 23,820.73 652,619.15 130,523.83 93,977.16 877,120.14
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 315.48 m2 210,646.83 32,845.78 3,284.58 246,777.19 20% 49,355.44 35,535.92 331,668.55
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 23.90 m 8,238.08 418.94 41.89 8,698.92 20% 1,739.78 1,252.64 11,691.34
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 13,761.03 459.44 45.94 14,266.41 20% 2,853.28 2,054.36 19,174.05
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 47.80 m 29,555.17 710.07 71.01 30,336.25 20% 6,067.25 4,368.42 40,771.92
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 2,271.38 kg 156,168.85 11,417.15 30,236.82 197,822.82 20% 39,564.56 28,486.49 265,873.87
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 3,687.15 kg 245,418.25 14,634.46 31,710.71 291,763.42 20% 58,352.68 42,013.93 392,130.03
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 47.80 m 10,447.05 892.53 89.25 11,428.83 20% 2,285.77 1,645.75 15,360.35
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 17,254.82 3,742.80 374.28 21,371.90 20% 4,274.38 3,077.55 28,723.83
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 101.34 kg 4,635.30 1,366.98 136.70 6,138.98 20% 1,227.80 884.01 8,250.79
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 214.42 kg 10,101.82 2,892.32 289.23 13,283.37 20% 2,656.67 1,912.80 17,852.84
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 18.00 pc 3,933.00 473.28 0.47 4,406.76 20% 881.35 634.57 5,922.68
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 80,435.45 12,895.37 27,305.85 120,636.67 20% 24,127.33 17,371.68 162,135.68
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 790,595.64 82,749.13 93,586.74 966,931.52 193,386.29 139,238.12 1,299,555.93
Sub-Total C.6
As Evaluated s
As Submitted 2,948,662.97 666,798.41 212,567.47 3,828,028.85 765,605.76 551,236.11 5,144,870.72
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 25,126.47 3,188.07 318.81 28,633.34 20% 5,726.67 4,123.20 38,483.21
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 6,669.70 1,026.67 102.67 7,799.04 20% 1,559.81 1,123.06 10,481.91
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 71,630.53 10,949.50 1,094.95 83,674.98 20% 16,735.00 12,049.20 112,459.18
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 120,381.71 14,286.14 1,428.61 136,096.46 20% 27,219.29 19,597.89 182,913.64
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 54,992.49 9,154.50 915.45 65,062.44 20% 13,012.49 9,368.99 87,443.92
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 12.00 units 10,151.39 2,103.48 210.35 12,465.22 20% 2,493.04 1,794.99 16,753.25
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 443,205.57 31,053.50 3,105.35 477,364.42 20% 95,472.88 68,740.48 641,577.78
SPL-2 Fire Protection System
As Evaluated
As Submitted 732,157.87 71,761.85 7,176.18 811,095.90 162,219.18 116,797.81 1,090,112.89
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 81,127.67 6,579.01 657.90 88,364.58 20% 17,672.92 12,724.50 118,762.00
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 66,742.63 4,701.19 470.12 71,913.94 20% 14,382.79 10,355.61 96,652.34
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 27,898.66 1,945.26 194.53 30,038.44 20% 6,007.69 4,325.54 40,371.67
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 48,282.75 3,025.96 302.60 51,611.31 20% 10,322.26 7,432.03 69,365.60
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,016.60 2,448.24 244.82 26,709.66 20% 5,341.93 3,846.19 35,897.78
1208(1) Fire Alarm System
As Evaluated
As Submitted 248,068.31 18,699.66 1,869.97 268,637.930 53,727.590 38,683.870 361,049.390
TOTAL OF PART E
As Evaluated
As Submitted 7,147,760.61 1,102,941.92 492,455.93 8,743,158.470 1,748,631.690 1,259,014.780 11,750,804.940
TOTAL OF PART III
As Evaluated
As Submitted 7,228,714.48 1,107,557.32 671,311.68 9,007,583.490 1,770,384.570 1,293,356.130 12,071,324.190
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.83% 114,616.67
Part II Other General Requirements 1.81% 113,034.02
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.79% 112,005.65
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 39.14% 2,446,979.17
PART C FINISHING WORKS 40.29% 2,518,481.06
PART D PLUMBING/SANITARY WORKS 12.10% 756,311.11
PART E ELECTRICAL WORKS 3.03% 189,708.23
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 3.83 mo - - 114,616.67 114,616.67 8% 9,169.33 14,854.32 138,640.32
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 114,616.67 114,616.67 9,169.33 14,854.32 138,640.32
TOTAL OF PART I
As Evalauted
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 4,219.35 701.16 70.12 4,990.63 20% 998.13 718.65 6,707.41
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 63,384.94 3,914.24 - 67,299.18 8% 5,383.93 8,721.97 81,405.08
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 40,744.21 40,744.21 8% 3,259.54 5,280.45 49,284.20
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 67,604.29 4,615.40 40,814.32 113,034.02 9,641.60 14,721.07 137,396.69
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 144.01 m3 - 1,410.07 31,657.60 33,067.67 20% 6,613.53 4,761.74 44,442.94
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 66.34 m3 - 1,320.26 8,525.65 9,845.91 20% 1,969.18 1,417.81 13,232.90
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 64.02 m3 32,210.06 1,274.09 8,227.50 41,711.65 20% 8,342.33 6,006.48 56,060.46
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 21.78 m3 22,354.45 3,554.31 1,471.66 27,380.42 20% 5,476.08 3,942.78 36,799.28
804(4) Gravel Fill
As Evaluated
As Submitted 54,564.51 7,558.74 49,882.41 112,005.65 22,401.12 16,128.81 150,535.58
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 102.63 m3 565,691.43 12,158.34 21,714.80 599,564.57 20% 119,912.91 86,337.30 805,814.78
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 18,342.24 kg 1,401,430.82 106,131.34 51,195.98 1,558,758.15 20% 311,751.63 224,461.17 2,094,970.95
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 608.26 m2 132,008.47 100,202.43 56,445.55 288,656.45 20% 57,731.29 41,566.53 387,954.27
903(2) Forms and Falseworks
As Evaluated
As Submitted 2,099,130.72 218,492.11 129,356.34 2,446,979.17 489,395.83 352,365.00 3,288,740.00
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 75.31 L 28,580.14 3,014.35 301.44 31,895.93 20% 6,379.19 4,593.01 42,868.13
1000(1) Soil Poisoning
As Evaluated
As Submitted 28,580.14 3,014.35 301.44 31,895.93 6,379.19 4,593.01 42,868.13
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 112.48 m2 84,063.28 9,355.69 5,993.49 99,412.46 20% 19,882.49 14,315.39 133,610.34
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 227.17 m2 235,494.53 22,727.72 14,559.95 272,782.20 20% 54,556.44 39,280.64 366,619.28
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 319,557.81 32,083.40 20,553.45 372,194.66 74,438.93 53,596.03 500,229.62
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 101,987.52 14,899.65 1,489.97 118,377.14 20% 23,675.43 17,046.31 159,098.88
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 13.71 m2 11,042.86 8,900.84 890.08 20,833.78 20% 4,166.76 3,000.06 28,000.60
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 24.48 m2 55,276.45 23,839.44 15,677.94 94,793.84 20% 18,958.77 13,650.31 127,402.92
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 10.88 m2 10,816.44 1,191.97 783.90 12,792.31 20% 2,558.46 1,842.09 17,192.86
1005 (5) Window Grill
As Evaluated
As Submitted #REF! 16.00 set 25,760.00 - - 25,760.00 20% 5,152.00 3,709.44 34,621.44
1004(2)a Locksets
As Evaluated
As Submitted #REF! 64.00 pc 11,040.00 - - 11,040.00 20% 2,208.00 1,589.76 14,837.76
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 7,130.00 1,255.76 125.58 8,511.34 20% 1,702.27 1,225.63 11,439.24
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 223,053.27 50,087.66 18,967.47 292,108.41 58,421.69 42,063.60 392,593.70
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 263.35 m2 74,254.28 11,374.51 1,137.45 86,766.24 20% 17,353.25 12,494.34 116,613.83
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,252.61 m 2
154,137.26 63,113.96 6,311.40 223,562.62 20% 44,712.52 32,193.02 300,468.16
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 16,269.73 1,140.31 1,721.10 19,131.14 20% 3,826.23 2,754.88 25,712.25
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 55.82 m 142,993.65 1,928.85 2,911.27 147,833.76 20% 29,566.75 21,288.06 198,688.57
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 142.77 m2 102,062.63 24,825.67 2,482.57 129,370.87 20% 25,874.17 18,629.40 173,874.44
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 196.68 m2 32,061.30 7,645.76 764.58 40,471.63 20% 8,094.33 5,827.92 54,393.88
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m2 56,266.70 30,576.75 3,057.67 89,901.13 20% 17,980.23 12,945.76 120,827.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m2 15,435.96 5,997.83 599.78 22,033.57 20% 4,406.71 3,172.83 29,613.11
1018(2) Unglazed Tiles
As Evaluated
As Submitted 593,481.52 146,603.63 18,985.81 759,070.96 151,814.19 109,306.21 1,020,191.36
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,339.81 m2 251,571.10 150,856.23 15,085.62 417,512.95 20% 83,502.59 60,121.86 561,137.40
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 75.71 m2 9,588.11 9,471.76 947.18 20,007.05 20% 4,001.41 2,881.02 26,889.48
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 37.55 m2 8,839.80 4,439.35 443.93 13,723.09 20% 2,744.62 1,976.13 18,443.84
1032(1)c Metal Painting
As Evaluated
As Submitted 269,999.01 164,767.34 16,476.73 451,243.09 90,248.62 64,979.01 606,470.72
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 196.68 m2 131,323.76 20,477.08 2,047.71 153,848.54 20% 30,769.71 22,154.19 206,772.44
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 14.90 m 5,135.87 261.18 26.12 5,423.17 20% 1,084.63 780.94 7,288.74
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 13,761.03 459.44 45.94 14,266.41 20% 2,853.28 2,054.36 19,174.05
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 29.80 m 18,425.61 442.68 44.27 18,912.56 20% 3,782.51 2,723.41 25,418.48
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 1,008.85 kg 69,363.53 5,071.01 13,429.91 87,864.45 20% 17,572.89 12,652.48 118,089.82
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 2,143.69 kg 142,684.90 8,508.40 18,436.45 169,629.75 20% 33,925.95 24,426.68 227,982.38
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 29.80 m 6,513.01 556.43 55.64 7,125.09 20% 1,425.02 1,026.01 9,576.12
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 17,254.82 3,742.80 374.28 21,371.90 20% 4,274.38 3,077.55 28,723.83
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 55.85 kg 2,554.58 753.36 75.34 3,383.28 20% 676.66 487.19 4,547.13
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 113.93 kg 5,367.50 1,536.81 153.68 7,057.99 20% 1,411.60 1,016.35 9,485.94
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 10.00 pc 2,185.00 262.94 0.26 2,448.20 20% 489.64 352.54 3,290.38
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 80,435.45 12,895.37 27,305.85 120,636.67 20% 24,127.33 17,371.68 162,135.68
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 495,005.07 54,967.49 61,995.44 611,968.01 122,393.60 88,123.38 822,484.99
Sub-Total C.6
As Evaluated
As Submitted 1,929,676.83 451,523.88 137,280.33 2,518,481.06 503,696.22 362,661.24 3,384,838.52
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 24,344.47 2,863.86 286.39 27,494.71 20% 5,498.94 3,959.24 36,952.89
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 6,669.70 1,026.67 102.67 7,799.04 20% 1,559.81 1,123.06 10,481.91
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 61,212.22 9,334.00 933.40 71,479.62 20% 14,295.92 10,293.06 96,068.60
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 120,033.95 14,154.67 1,415.47 135,604.09 20% 27,120.82 19,526.99 182,251.90
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 37,835.63 6,372.25 637.23 44,845.10 20% 8,969.02 6,457.69 60,271.81
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 8.00 units 6,767.59 1,402.32 140.23 8,310.15 20% 1,662.03 1,196.66 11,168.84
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 427,508.07 30,245.75 3,024.58 460,778.40 20% 92,155.68 66,352.09 619,286.17
SPL-2 Fire Protection System
As Evaluated
As Submitted 684,371.63 65,399.51 6,539.95 756,311.11 151,262.22 108,908.79 1,016,482.12
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 58,446.68 1,781.63 178.16 60,406.47 20% 12,081.29 8,698.53 81,186.29
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 47,552.56 2,903.74 290.37 50,746.67 20% 10,149.33 7,307.52 68,203.52
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 21,148.61 1,512.98 151.30 22,812.89 20% 4,562.58 3,285.06 30,660.53
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 26,892.75 1,945.26 194.53 29,032.54 20% 5,806.51 4,180.69 39,019.74
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,016.60 2,448.24 244.82 26,709.66 20% 5,341.93 3,846.19 35,897.78
1208(1) Fire Alarm System
As Evaluated
As Submitted 178,057.20 10,591.85 1,059.19 189,708.230 37,941.640 27,317.990 254,967.860
TOTAL OF PART E
As Evaluated
As Submitted 4,945,800.90 753,566.09 324,118.21 6,023,485.220 1,204,697.030 867,381.830 8,095,564.080
TOTAL OF PART III
As Evaluated
As Submitted 4,945,800.90 753,566.09 324,118.21 6,023,485.220 1,204,697.030 867,381.830 8,095,564.080
TOTAL OF (Project ID)
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF (Project ID)
As Evaluated
As Submitted 5,013,405.19 758,181.49 479,549.20 6,251,135.910 1,223,507.960 896,957.220 8,371,601.090
GRAND TOTAL
As Evaluated