You are on page 1of 1

PROJECT : 105/A, YANGON PARAMI ROAD PROJECT

CONTRACT WORK FOR : Yangon Parami Road Project


PAYMENT VALUATION NO. : 18
MILE STONE PROGRESS CLAIM FOR : WORK-DONE BY 11th JUNE 2020

MILE STONE PAYMENT SUMMARY Agreement (base on supplemental agree) Contractor's Claim

Previous Previous This This


Contract Total
Contract Work Accumulative Month Month Month Month
Item Description Amount Claimed
(%) (%) Completed Claimed Completed Claimed
(USD) (USD)
(%) (USD) (%) (USD)

A Civil Works
1 Upon signing contract 207,000 10.00% 10.00% 100.00% 207,000 207,000
Neighbouring Building Status Investigation +
31,050 1.50% 11.50% 100.00% 31,050 31,050
Engineering Office + Construction fence
2
3 Pile work 41,400 2.00% 13.50% 100.00% 41,400 41,400
4 Underground tank & footings 41,400 2.00% 15.50% 100.00% 41,400 41,400
5 Ground floor slab 51,750 2.50% 18.00% 100.00% 51,750 51,750
6 1st floor slab 51,750 2.50% 20.50% 100.00% 51,750 51,750
7 2nd floor slab 51,750 2.50% 23.00% 100.00% 51,750 51,750
8 3rd floor slab 51,750 2.50% 25.50% 100.00% 51,750 51,750
9 4th floor slab 51,750 2.50% 28.00% 100.00% 51,750 51,750
10 5th floor slab 51,750 2.50% 30.50% 100.00% 51,750 51,750
11 6th floor slab 51,750 2.50% 33.00% 100.00% 51,750 51,750
12 7th floor slab 51,750 2.50% 35.50% 100.00% 51,750 51,750
13 8th floor slab 51,750 2.50% 38.00% 100.00% 51,750 51,750
14 9th floor slab 51,750 2.50% 40.50% 100.00% 51,750 51,750
15 10 th floor slab 51,750 2.50% 43.00% 100.00% 51,750 51,750
16 11 floor slab 51,750 2.50% 45.50% 100.00% 51,750 51,750
17 Roof slab 20,700 1.00% 46.50% 100.00% 20,700 20,700
18 Elevator installed 41,400 2.00% 48.50% 100.00% 41,400 41,400
19 indoor brick walls (1/3) 10,350 0.50% 49.00% 100.00% 10,350 10,350
indoor brick walls (2/3) 20,700 1.00% 50.00% 100.00% 20,700 20,700
indoor brick walls 20,700 1.00% 51.00% 100.00% 20,700 20,700
20 External brick wall (1/3) 10,350 0.50% 51.50% 100.00% 10,350 10,350
External brick wall (2/3) 10,350 0.50% 52.00% 100.00% 10,350 10,350
External brick wall 10,350 0.50% 52.50% 100.00% 10,350 10,350
21 Tower crane installed 20,700 1.00% 53.50% 100.00% 20,700 20,700
22 Tower crane dissembled 20,700 1.00% 54.50% 100.00% 20,700 20,700
23 Fire-proof door installed 41,400 2.00% 56.50% 100.00% 41,400 41,400
Aluminium windows and door frame installed (1/3) 20,700 1.00% 57.50% 100.00% 20,700 20,700
24 Aluminium windows and door frame installed (2/3) 41,400 2.00% 59.50% 100.00% 41,400 41,400
25 Aluminium windows and door frame installed 41,400 2.00% 61.50% 100.00% 41,400 41,400
26 Exterior painting work 1/3 20,700 1.00% 62.50% 100.00% 20,700 20,700
27 Exterior painting work 2/3 20,700 1.00% 63.50% 100.00% 20,700 20,700
28 Exterior painting work 20,700 1.00% 64.50% 100.00% 20,700 20,700
29 Lobby stone decoration 31,050 1.50% 66.00%
30 Iron grill and hand rails 31,050 1.50% 67.50% 100.00% 31,050 31,050
scaffolding assemble (1/2) 20,700 1.00% 68.50% 100.00% 20,700 20,700
31 scaffolding assemble 10,350 0.50% 69.00% 100.00% 10,350 10,350
32 scaffolding dissemble 20,700 1.00% 70.00% 100.00% 20,700 20,700
33 Floor tiles and waterproofing 1/3 20,700 1.00% 71.00% 100.00% 20,700 20,700
34 Floor tiles and waterproofing 2/3 20,700 1.00% 72.00% 100.00% 20,700 20,700
35 Floor tiles and waterproofing 20,700 1.00% 73.00% 100.00% 20,700 20,700
36 Interior wall finishing 1/3 20,700 1.00% 74.00% 100.00% 20,700 20,700
37 Interior wall finishing 2/3 20,700 1.00% 75.00% 100.00% 20,700 20,700
38 Interior wall finishing 20,700 1.00% 76.00% 100.00% 20,700 20,700
Ceiling finishing (1/3) 20,700 1.00% 77.00% 100.00% 20,700 20,700
39 Ceiling finishing (2/3) 20,700 1.00% 78.00% 100.00% 20,700 20,700
40 Ceiling finishing 20,700 1.00% 79.00% 100.00% 20,700 20,700
Windows and Doors glass installed (1/2) 10,350 0.50% 79.50% 100.00% 10,350 10,350
41 Windows and Doors glass installed 10,350 0.50% 80.00% 100.00% 10,350 10,350
42 Sanitary wares installed 1/3 51,750 2.50% 82.50% 100.00% 51,750 51,750
43 Sanitary wares installed 2/3 51,750 2.50% 85.00% 100.00% 51,750 51,750
44 Sanitary wares installed 51,750 2.50% 87.50% 100.00% 51,750 51,750
45 Cabinet and Kitchen accessories 1/3 31,050 1.50% 89.00% 100.00% 31,050 31,050
46 Cabinet and Kitchen accessories 2/3 31,050 1.50% 90.50% 100.00% 31,050 31,050
47 Cabinet and Kitchen accessories 31,050 1.50% 92.00% 100.00% 31,050 31,050
48 Road and pavement recovering 20,700 1.00% 93.00% 100.00% 20,700 20,700
49 Apply BCC 20,700 1.00% 94.00% 50.00% 10,350 10,350
50 Obtain BCC 20,700 1.00% 95.00% -
51 Get YCDC water supply and EPC electricity 20,700 1.00% 96.00% -
52 Initial inspection and acceptance 20,700 1.00% 97.00% 50.00% 10,350.00 10,350
53 final inspection and acceptance 31,050 1.50% 98.50% -
54 As built drawing (3 copies) 10,350 0.50% 99.00% -
55 Public area checked and handover to the Owner 20,700 1.00% 100.00% -
Total For Civil Works (A) 2,070,000 100.00% 1,914,750 - 1,914,750

Page 1 of 1

You might also like