2021
FEBRUARY MARCH
NO WORK VALUE (%)
W2 W3 W4 W1 W2 W3 W4 W5
8 - 14 15 - 21 22 - 28 1-7 8 - 14 15- 21 22 - 28 29 - 4
A PRELIMINARY WORKS 20,165% 2,521% 2,521% 2,521% 2,521% 2,521% 2,521% 2,521% 2,521%
B PEK.FASADE 100,000%
C PEK.PEMBONGKARAN
C.1.10 Demolish Power Outlet , Data, Security Equipment 0,723% 0,362% 0,362%
D PEK.PEMASANGAN
Pek. Perapihan Bekas Signage / Tothem (Sticker Only;
D.1.1 0,898% 0,898%
1800 x 1200)
D.1.2 Pek. Perapian Plafond Akustik 12,087% 6,043% 6,043%
D.1.4 Pek. Perapihan Dinding Bekas AC, Power Outlet dll 8,571% 4,286% 4,286%
29,491%
D.1.5 Pek. Pengecatan Semua Dinding 4,545% 2,273% 2,273%
Pek. Pembuatan Power Outlet Baru disesuaikan
D.1.6 5,416% 5,416%
dengan kondisi existing
D.1.7 Pek. Screeding Lantai 18,993% 9,497% 9,497%
D.1.8 Pek. Perapian Exposed Beton (kolom dan balok) 2,971% 2,971%
16,300%
D.1.9 Pek. Springkler Relokasi by Landlord 0,000% 0,000% 0,000%
PLAN ACCUMULATION 3,566% 6,087% 16,300% 29,491% 54,956% 84,868% 97,479% 100,000%
CHECKED BY OWNER