BAHRIA HOUSING PROJECT
Assignment # 1
01-398191-085
MSPM 2-D
Site prep Pile Caps Structural Steel Plumbing and Electrical Interior and Roofing
1.1 1.2 1.3 1.4 1.5
Mobilisation Cut-off Piles and Building Erect Steel Frame Install Water Lines And Wiring Install Dry Wall and Felt
1.1.1 1.2.1 1.3.1 1.4.1 1.5.1
Evacuation Framework and rebar Holoirb Floors Install Gas Lines and Switches Install Carpets and Vents
1.1.2 1.2.2 1.3.2 1.4.2 1.5.2
Pilling Concrete Install B/K Features & FixturesInstall painting And artwork
1.1.3 1.2.3 1.4.3 1.5.3
Mobilisation Cut-off Piles and Building Erect Steel Frame Install Water Lines and Wiring Install Dry Wall and Felt
1.1.1 1.2.1 1.3.1 1.4.1 1.5.1
$5000 $10000 $30000 $20000 $50000
Evacuation Holoirb Floors Install Gas Lines and Switches Install Carpets and Vents
Framework and rebar
1.1.2 1.3.2 1.4.2 1.5.2
1.2.2
$3000 $20000 $30000 $30000
$20000
Concrete
Pilling Frame Exterior Wall Install painting and artwork
1.2.3 Install B/K Features & Fixtures
1.1.3 1.3.2 1.5.3
$10000 1.4.3
$2000 ----------------------- $30000
$30000
$20000
Fee $50,000