MODULE
ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 3.77% 3.77% 3.77% 3.77% 3.77% 3.51% 3.51% 0.00% 0.00% 10.14%
1.01 Layout, Batterboards & Excavation 0.71% 0.71% 0.71% 0.71% 0.71% 0.66% 0.66% 0.71%
1.02 2500psi RC Wall Footing 3.06% 3.06% 3.06% 3.06% 3.06% 2.85% 2.85% 3.06%
1.03 Wooden Zucallo Forms,600x2400mm 0.84%
1.04 2500psi RC Zucallo Wall 2.55%
1.05 Septic Vault,1200x2800x1600mm 2.98%
Module II GROUND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.07%
2.01 Wires & Conduits 0.68%
2.02 PVC Pipes & Fittings 0.51%
2.03 GF Wall Concreting 8.87%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.57%
3.01 2F Slab Concreting 6.57%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15%
4.01 Wires & Conduits 0.83%
4.02 2F Wall Concreting 10.33%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25%
5.01 Roof Framing 4.25%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08%
5.05 PVC Downspouts & Catchbasins 1.25%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27%
5.06 RC Kitchen Counter 0.49%
5.07 Concrete Stair Case 1.68%
5.08 Concrete Pads, 100x300x1000mm 0.10%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46%
5.09 Exterior Steel Doors & Jambs 2.79%
5.10 CHB Wall Masonry/ CR Flooring 2.58%
5.11 Wall & Concrete Finishes 6.43%
5.12 Concrete Mouldings & Canopy 0.66%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99%
1.06 2000psi Slab-on-Fill, 100mm 3.33%
1.07 PVC Pipe & Fittings 0.81%
1.08 Wires & Conduits 0.85%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05%
7.01 Ceilings, Eaves & Vents 3.69%
7.02 Dry Wall Partitions(Double-walled) 2.08%
7.03 Interior PVC Doors & Jambs 4.93%
7.04 Cabinet Doors 1.01%
7.04 Wires & Conduits 0.34%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25%
5.02 Stair Railings 0.54%
8.03 Aluminum Windows 5.22%
8.01 Tileworks 2.71%
8.02 1st Coat Painting 2.67%
8.04 Lot Levelling 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47%
8.05 Plumbing Fixtures 5.11%
8.06 Electrical Fixtures 2.05%
8.07 Final Coat Painting 2.92%
8.08 Clean-up & Turnover 0.09%
8.09 Tapping to main 0.30%
TOTAL 3.77% 3.77% 3.77% 3.77% 3.77% 3.51% 3.51% 0.00% 0.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 3.77% 3.77% 3.77% 3.77% 3.77% 3.51% 3.51% 0.00% 0.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3.00 % Weight BILLABLE THIS PERIOD 3.77% 3.77% 3.77% 3.77% 3.77% 3.51% 3.51% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 96.23% 96.23% 96.23% 96.23% 96.23% 96.49% 96.49% 100.00% 100.00%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 188.00 188.00 188.00 188.00 188.00 188.00 188.00 142.00 142.00
AT 100%
ACCOMPLISHMENT
CORNER DUPLEX
9.80%
0.66%
2.85%
0.80%
2.39%
3.10%
9.47%
0.71%
0.54%
8.22%
6.83%
6.83%
10.73%
0.86%
9.87%
4.43%
4.43%
4.88%
3.59%
1.30%
2.37%
0.51%
1.75%
0.11%
12.36%
2.90%
2.68%
6.09%
0.69%
5.19%
3.46%
0.84%
0.88%
12.54%
3.84%
2.16%
5.13%
1.05%
0.35%
11.14%
0.56%
5.43%
2.82%
2.22%
0.10%
10.26%
5.32%
2.13%
2.40%
0.10%
0.31%
100.00%
Subject : SERENE HOUSE MODEL CONSTRUCTION MONITORING
FA = 50.00sqm, CIP Wall System, 3BR, 2TB, LA = 80.00sqm
Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : ADD BUILDERS & ENGINEERING SERVICES NTP NO: 04 NO OF UNIT: 7
Date: : January 13, 2020
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100%
MODULE
ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 7.16% 3.77% 7.16% 7.16% 7.16% 6.70% 6.70% 3.77% 3.77% 10.14%
1.01 Layout, Batterboards & Excavation 0.71% 0.71% 0.71% 0.71% 0.71% 0.66% 0.66% 0.71% 0.71% 0.71%
1.02 2500psi RC Wall Footing 3.06% 3.06% 3.06% 3.06% 3.06% 2.85% 2.85% 3.06% 3.06% 3.06%
1.03 Wooden Zucallo Forms,600x2400mm 0.84% 0.84% 0.84% 0.84% 0.80% 0.80% 0.84%
1.04 2500psi RC Zucallo Wall 2.55% 2.55% 2.55% 2.55% 2.39% 2.39% 2.55%
1.05 Septic Vault,1200x2800x1600mm 2.98%
Module II GROUND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.07%
2.01 Wires & Conduits 0.68%
2.02 PVC Pipes & Fittings 0.51%
2.03 GF Wall Concreting 8.87%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.57%
3.01 2F Slab Concreting 6.57%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15%
4.01 Wires & Conduits 0.83%
4.02 2F Wall Concreting 10.33%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25%
5.01 Roof Framing 4.25%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08%
5.05 PVC Downspouts & Catchbasins 1.25%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27%
5.06 RC Kitchen Counter 0.49%
5.07 Concrete Stair Case 1.68%
5.08 Concrete Pads, 100x300x1000mm 0.10%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46%
5.09 Exterior Steel Doors & Jambs 2.79%
5.10 CHB Wall Masonry/ CR Flooring 2.58%
5.11 Wall & Concrete Finishes 6.43%
5.12 Concrete Mouldings & Canopy 0.66%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99%
1.06 2000psi Slab-on-Fill, 100mm 3.33%
1.07 PVC Pipe & Fittings 0.81%
1.08 Wires & Conduits 0.85%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05%
7.01 Ceilings, Eaves & Vents 3.69%
7.02 Dry Wall Partitions(Double-walled) 2.08%
7.03 Interior PVC Doors & Jambs 4.93%
7.04 Cabinet Doors 1.01%
7.04 Wires & Conduits 0.34%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25%
5.02 Stair Railings 0.54%
8.03 Aluminum Windows 5.22%
8.01 Tileworks 2.71%
8.02 1st Coat Painting 2.67%
8.04 Lot Levelling 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47%
8.05 Plumbing Fixtures 5.11%
8.06 Electrical Fixtures 2.05%
8.07 Final Coat Painting 2.92%
8.08 Clean-up & Turnover 0.09%
8.09 Tapping to main 0.30%
TOTAL 7.16% 3.77% 7.16% 7.16% 7.16% 6.70% 6.70% 3.77% 3.77% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 7.16% 3.77% 7.16% 7.16% 7.16% 6.70% 6.70% 3.77% 3.77%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 3.77% 3.77% 3.77% 3.77% 3.77% 3.51% 3.51% 0.00% 0.00%
3.00 % Weight BILLABLE THIS PERIOD 3.39% 0.00% 3.39% 3.39% 3.39% 3.19% 3.19% 3.77% 3.77%
4.00 % Weight BALANCE AFTER THIS PERIOD 92.84% 96.23% 92.84% 92.84% 92.84% 93.30% 93.30% 96.23% 96.23%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 174.00 174.00 174.00 174.00 174.00 174.00 174.00 128.00 128.00
AT 100%
ACCOMPLISHMENT
CORNER DUPLEX
9.80%
0.66%
2.85%
0.80%
2.39%
3.10%
9.47%
0.71%
0.54%
8.22%
6.83%
6.83%
10.73%
0.86%
9.87%
4.43%
4.43%
4.88%
3.59%
1.30%
2.37%
0.51%
1.75%
0.11%
12.36%
2.90%
2.68%
6.09%
0.69%
5.19%
3.46%
0.84%
0.88%
12.54%
3.84%
2.16%
5.13%
1.05%
0.35%
11.14%
0.56%
5.43%
2.82%
2.22%
0.10%
10.26%
5.32%
2.13%
2.40%
0.10%
0.31%
100.00%
Subject : SERENE HOUSE MODEL CONSTRUCTION MONITORING
FA = 50.00sqm, CIP Wall System, 3BR, 2TB, LA = 80.00sqm
Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : ADD BUILDERS & ENGINEERING SERVICES NTP NO: 04 NO OF UNIT: 7 NO OF UNIT: 2
Date: : January 20, 2020
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 3.77% 10.14% 10.14% 10.14% 6.70% 6.70% 7.16% 7.16% 10.14% 9.80%
1.01 Layout, Batterboards & Excavation 0.71% 0.71% 0.71% 0.71% 0.71% 0.66% 0.66% 0.71% 0.71% 0.71% 0.66%
1.02 2500psi RC Wall Footing 3.06% 3.06% 3.06% 3.06% 3.06% 2.85% 2.85% 3.06% 3.06% 3.06% 2.85%
1.03 Wooden Zucallo Forms,600x2400mm 0.84% 0.84% 0.84% 0.84% 0.80% 0.80% 0.84% 0.84% 0.84% 0.80%
1.04 2500psi RC Zucallo Wall 2.55% 2.55% 2.55% 2.55% 2.39% 2.39% 2.55% 2.55% 2.55% 2.39%
1.05 Septic Vault,1200x2800x1600mm 2.98% 2.98% 2.98% 2.98% 2.98% 3.10%
Module II GROUND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 10.14% 3.77% 10.14% 10.14% 10.14% 6.70% 6.70% 7.16% 7.16% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 10.14% 3.77% 10.14% 10.14% 10.14% 6.70% 6.70% 7.16% 7.16%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 7.16% 3.77% 7.16% 7.16% 7.16% 6.70% 6.70% 3.77% 3.77%
3.00 % Weight BILLABLE THIS PERIOD 2.98% 0.00% 2.98% 2.98% 2.98% 0.00% 0.00% 3.39% 3.39%
4.00 % Weight BALANCE AFTER THIS PERIOD 89.86% 96.23% 89.86% 89.86% 89.86% 93.30% 93.30% 92.84% 92.84%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 167.00 167.00 167.00 167.00 167.00 167.00 167.00 121.00 121.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 6.70% 6.70% 10.14% 10.14% 10.14% 9.80%
1.01
Layout, Batterboards & Excavation 0.71% 0.71% 0.71% 0.71% 0.71% 0.66% 0.66% 0.71% 0.71% 0.71% 0.66%
1.02
2500psi RC Wall Footing 3.06% 3.06% 3.06% 3.06% 3.06% 2.85% 2.85% 3.06% 3.06% 3.06% 2.85%
1.03
Wooden Zucallo Forms,600x2400mm 0.84% 0.84% 0.84% 0.84% 0.84% 0.80% 0.80% 0.84% 0.84% 0.84% 0.80%
1.04
2500psi RC Zucallo Wall 2.55% 2.55% 2.55% 2.55% 2.55% 2.39% 2.39% 2.55% 2.55% 2.55% 2.39%
1.05
Septic Vault,1200x2800x1600mm 2.98% 2.98% 2.98% 2.98% 2.98% 2.98% 2.98% 2.98% 3.10%
Module II GROUND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.07% 10.07% 9.47%
2.01 Wires & Conduits 0.68% 0.68% 0.71%
2.02 PVC Pipes & Fittings 0.51% 0.51% 0.54%
2.03 GF Wall Concreting 8.87% 8.87% 8.22%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 10.14% 10.14% 10.14% 10.14% 10.14% 6.70% 6.70% 10.14% 20.21% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 10.14% 10.14% 10.14% 10.14% 10.14% 6.70% 6.70% 10.14% 20.21%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 10.14% 3.77% 10.14% 10.14% 10.14% 6.70% 6.70% 7.16% 7.16%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 6.37% 0.00% 0.00% 0.00% 0.00% 0.00% 2.98% 13.05%
4.00 % Weight BALANCE AFTER THIS PERIOD 89.86% 89.86% 89.86% 89.86% 89.86% 93.30% 93.30% 89.86% 79.79%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 160.00 160.00 160.00 160.00 160.00 160.00 160.00 114.00 114.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
1.01 Layout, Batterboards & Excavation 0.71% 0.71% 0.71% 0.71% 0.71% 0.66% 0.66% 0.71% 0.71% 0.71% 0.66%
1.02 2500psi RC Wall Footing 3.06% 3.06% 3.06% 3.06% 3.06% 2.85% 2.85% 3.06% 3.06% 3.06% 2.85%
1.03 Wooden Zucallo Forms,600x2400mm 0.84% 0.84% 0.84% 0.84% 0.84% 0.80% 0.80% 0.84% 0.84% 0.84% 0.80%
1.04 2500psi RC Zucallo Wall 2.55% 2.55% 2.55% 2.55% 2.55% 2.39% 2.39% 2.55% 2.55% 2.55% 2.39%
1.05 Septic Vault,1200x2800x1600mm 2.98% 2.98% 2.98% 2.98% 2.98% 3.10% 3.10% 2.98% 2.98% 2.98% 3.10%
Module II GROUND FLOOR RC WALL 0.00% 0.00% 10.07% 10.07% 0.00% 0.00% 0.00% 10.07% 10.07% 10.07% 9.47%
2.01 Wires & Conduits 0.68% 0.68% 0.68% 0.68% 0.68% 0.71%
2.02 PVC Pipes & Fittings 0.51% 0.51% 0.51% 0.51% 0.51% 0.54%
2.03 GF Wall Concreting 8.87% 8.87% 8.87% 8.87% 8.87% 8.22%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 10.14% 10.14% 20.21% 20.21% 10.14% 9.80% 9.80% 20.21% 26.78% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 10.14% 10.14% 20.21% 20.21% 10.14% 9.80% 9.80% 20.21% 26.78%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 10.14% 10.14% 10.14% 10.14% 10.14% 6.70% 6.70% 10.14% 20.21%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 10.07% 10.07% 0.00% 3.10% 3.10% 10.07% 6.57%
4.00 % Weight BALANCE AFTER THIS PERIOD 89.86% 89.86% 79.79% 79.79% 89.86% 90.20% 90.20% 79.79% 73.22%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 153.00 153.00 153.00 153.00 153.00 153.00 153.00 107.00 107.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
1.01 Layout, Batterboards & Excavation 0.71% 0.71% 0.71% 0.71% 0.71% 0.66% 0.66% 0.71% 0.71% 0.71% 0.66%
1.02 2500psi RC Wall Footing 3.06% 3.06% 3.06% 3.06% 3.06% 2.85% 2.85% 3.06% 3.06% 3.06% 2.85%
1.03 Wooden Zucallo Forms,600x2400mm 0.84% 0.84% 0.84% 0.84% 0.84% 0.80% 0.80% 0.84% 0.84% 0.84% 0.80%
1.04 2500psi RC Zucallo Wall 2.55% 2.55% 2.55% 2.55% 2.55% 2.39% 2.39% 2.55% 2.55% 2.55% 2.39%
1.05 Septic Vault,1200x2800x1600mm 2.98% 2.98% 2.98% 2.98% 2.98% 3.10% 3.10% 2.98% 2.98% 2.98% 3.10%
Module II GROUND FLOOR RC WALL 10.07% 0.00% 10.07% 10.07% 0.00% 0.00% 0.00% 10.07% 10.07% 10.07% 9.47%
2.01 Wires & Conduits 0.68% 0.68% 0.68% 0.68% 0.68% 0.68% 0.71%
2.02 PVC Pipes & Fittings 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.54%
2.03 GF Wall Concreting 8.87% 8.87% 8.87% 8.87% 8.87% 8.87% 8.22%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 6.57% 0.00% 0.00% 0.00% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 20.21% 10.14% 20.21% 26.78% 10.14% 9.80% 9.80% 26.78% 26.78% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 20.21% 10.14% 20.21% 26.78% 10.14% 9.80% 9.80% 26.78% 26.78%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 10.14% 10.14% 20.21% 20.21% 10.14% 9.80% 9.80% 20.21% 26.78%
3.00 % Weight BILLABLE THIS PERIOD 10.07% 0.00% 0.00% 6.57% 0.00% 0.00% 0.00% 6.57% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 79.79% 89.86% 79.79% 73.22% 89.86% 90.20% 90.20% 73.22% 73.22%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 146.00 146.00 146.00 146.00 146.00 146.00 146.00 100.00 100.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
1.01 Layout, Batterboards & Excavation 0.71% 0.71% 0.71% 0.71% 0.71% 0.66% 0.66% 0.71% 0.71% 0.71% 0.66%
1.02 2500psi RC Wall Footing 3.06% 3.06% 3.06% 3.06% 3.06% 2.85% 2.85% 3.06% 3.06% 3.06% 2.85%
1.03 Wooden Zucallo Forms,600x2400mm 0.84% 0.84% 0.84% 0.84% 0.84% 0.80% 0.80% 0.84% 0.84% 0.84% 0.80%
1.04 2500psi RC Zucallo Wall 2.55% 2.55% 2.55% 2.55% 2.55% 2.39% 2.39% 2.55% 2.55% 2.55% 2.39%
1.05 Septic Vault,1200x2800x1600mm 2.98% 2.98% 2.98% 2.98% 2.98% 3.10% 3.10% 2.98% 2.98% 2.98% 3.10%
Module II GROUND FLOOR RC WALL 10.07% 0.00% 10.07% 10.07% 0.00% 0.00% 0.00% 10.07% 10.07% 10.07% 9.47%
2.01 Wires & Conduits 0.68% 0.68% 0.68% 0.68% 0.68% 0.68% 0.71%
2.02 PVC Pipes & Fittings 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.54%
2.03 GF Wall Concreting 8.87% 8.87% 8.87% 8.87% 8.87% 8.87% 8.22%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 6.57% 6.57% 0.00% 0.00% 0.00% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 20.21% 10.14% 26.78% 26.78% 10.14% 9.80% 9.80% 26.78% 37.93% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 20.21% 10.14% 26.78% 26.78% 10.14% 9.80% 9.80% 26.78% 37.93%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 20.21% 10.14% 20.21% 26.78% 10.14% 9.80% 9.80% 26.78% 26.78%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 6.57% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15%
4.00 % Weight BALANCE AFTER THIS PERIOD 79.79% 89.86% 73.22% 73.22% 89.86% 90.20% 90.20% 73.22% 62.07%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 139.00 139.00 139.00 139.00 139.00 139.00 139.00 93.00 93.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 0.00% 0.00% 0.00% 10.07% 10.07% 10.07% 9.47%
2.01 Wires & Conduits 0.68% 0.68% 0.68% 0.68% 0.68% 0.68% 0.68% 0.71%
2.02 PVC Pipes & Fittings 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.54%
2.03 GF Wall Concreting 8.87% 8.87% 8.87% 8.87% 8.87% 8.87% 8.87% 8.22%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 0.00% 0.00% 0.00% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 26.78% 26.78% 26.78% 26.78% 10.14% 9.80% 9.80% 37.93% 42.19% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 26.78% 26.78% 26.78% 26.78% 10.14% 9.80% 9.80% 37.93% 42.19%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 20.21% 10.14% 26.78% 26.78% 10.14% 9.80% 9.80% 26.78% 37.93%
3.00 % Weight BILLABLE THIS PERIOD 6.57% 16.63% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 4.25%
4.00 % Weight BALANCE AFTER THIS PERIOD 73.22% 73.22% 73.22% 73.22% 89.86% 90.20% 90.20% 62.07% 57.81%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 125.00 125.00 125.00 125.00 125.00 125.00 125.00 79.00 79.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 0.00% 0.00% 10.07% 10.07% 10.07% 9.47%
2.01 Wires & Conduits 0.68% 0.68% 0.68% 0.68% 0.68% 0.68% 0.68% 0.68% 0.71%
2.02 PVC Pipes & Fittings 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51% 0.54%
2.03 GF Wall Concreting 8.87% 8.87% 8.87% 8.87% 8.87% 8.87% 8.87% 8.87% 8.22%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 0.00% 0.00% 0.00% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 26.78% 26.78% 26.78% 26.78% 20.21% 9.80% 9.80% 42.19% 42.19% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 26.78% 26.78% 26.78% 26.78% 20.21% 9.80% 9.80% 42.19% 42.19%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 26.78% 26.78% 26.78% 26.78% 10.14% 9.80% 9.80% 37.93% 42.19%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 10.07% 0.00% 0.00% 4.25% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 73.22% 73.22% 73.22% 73.22% 79.79% 90.20% 90.20% 57.81% 57.81%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 118.00 118.00 118.00 118.00 118.00 118.00 118.00 72.00 72.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 0.00% 10.07% 10.07% 10.07% 9.47%
2.01 Wires & Conduits 0.68% 0.68% 0.68% 0.68% 0.68% 0.71% 0.68% 0.68% 0.68% 0.71%
2.02 PVC Pipes & Fittings 0.51% 0.51% 0.51% 0.51% 0.51% 0.54% 0.51% 0.51% 0.51% 0.54%
2.03 GF Wall Concreting 8.87% 8.87% 8.87% 8.87% 8.87% 8.22% 8.87% 8.87% 8.87% 8.22%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 0.00% 0.00% 0.00% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 11.15% 0.00% 0.00% 0.00% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 4.99% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 26.78% 26.78% 26.78% 42.92% 20.21% 19.27% 9.80% 42.19% 42.19% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 26.78% 26.78% 26.78% 42.92% 20.21% 19.27% 9.80% 42.19% 42.19%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 26.78% 26.78% 26.78% 26.78% 20.21% 9.80% 9.80% 42.19% 42.19%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 16.14% 0.00% 9.47% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 73.22% 73.22% 73.22% 57.08% 79.79% 80.73% 90.20% 57.81% 57.81%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 20.00 20.00 20.00 20.00 20.00 20.00 20.00 -26.00 -26.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
2.01 Wires & Conduits 0.68% 0.68% 0.68% 0.68% 0.68% 0.71% 0.71% 0.68% 0.68% 0.68% 0.71%
2.02 PVC Pipes & Fittings 0.51% 0.51% 0.51% 0.51% 0.51% 0.54% 0.54% 0.51% 0.51% 0.51% 0.54%
2.03 GF Wall Concreting 8.87% 8.87% 8.87% 8.87% 8.87% 8.22% 8.22% 8.87% 8.87% 8.87% 8.22%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 0.00% 6.83% 0.00% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 11.15% 0.00% 0.00% 0.00% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 0.00% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.27% 0.00% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 4.99% 0.00% 0.00% 0.00% 0.00% 0.00% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 26.78% 26.78% 26.78% 42.92% 20.21% 26.10% 19.27% 48.78% 42.19% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 26.78% 26.78% 26.78% 42.92% 20.21% 26.10% 19.27% 48.78% 42.19%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 26.78% 26.78% 26.78% 42.92% 20.21% 19.27% 9.80% 42.19% 42.19%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 6.83% 9.47% 6.60% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 73.22% 73.22% 73.22% 57.08% 79.79% 73.90% 80.73% 51.22% 57.81%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays 13.00 13.00 13.00 13.00 13.00 13.00 13.00 -33.00 -33.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 0.00% 11.15% 11.15% 0.00% 0.00% 0.00% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 4.25% 4.25% 0.00% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 1.68% 0.00% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 4.99% 0.00% 0.00% 0.00% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.03% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.22% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 37.93% 26.78% 42.19% 48.86% 26.78% 26.10% 26.10% 66.23% 75.48% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 37.93% 26.78% 42.19% 48.86% 26.78% 26.10% 26.10% 66.23% 75.48%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 26.78% 26.78% 26.78% 42.92% 20.21% 26.10% 19.27% 48.78% 42.19%
3.00 % Weight BILLABLE THIS PERIOD 11.15% 0.00% 15.41% 5.94% 6.57% 0.00% 6.83% 17.45% 33.29%
4.00 % Weight BALANCE AFTER THIS PERIOD 62.07% 73.22% 57.81% 51.14% 73.22% 73.90% 73.90% 33.77% 24.52%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -8.00 -8.00 -8.00 -8.00 -8.00 -8.00 -8.00 -54.00 -54.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 0.83% 0.00% 0.00% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 10.33% 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 4.25% 4.25% 0.00% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 4.33% 0.00% 0.00% 0.00% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 2.27% 0.00% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 4.99% 0.00% 0.00% 0.00% 4.99% 4.99% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.03% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.22% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 37.93% 37.93% 42.19% 53.77% 27.61% 26.10% 26.10% 66.23% 75.48% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 37.93% 37.93% 42.19% 53.77% 27.61% 26.10% 26.10% 66.23% 75.48%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 37.93% 26.78% 42.19% 48.86% 26.78% 26.10% 26.10% 66.23% 75.48%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 11.15% 0.00% 4.91% 0.83% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 62.07% 62.07% 57.81% 46.23% 72.39% 73.90% 73.90% 33.77% 24.52%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -15.00 -15.00 -15.00 -15.00 -15.00 -15.00 -15.00 -61.00 -61.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
3.01 2F Slab Concreting 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 0.00% 0.00% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 10.33% 10.33% 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 4.25% 0.00% 4.25% 4.25% 0.00% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 0.00% 4.33% 4.33% 0.00% 0.00% 0.00% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 0.00% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 4.99% 0.00% 0.00% 0.00% 4.99% 4.99% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.03% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.22% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 48.78% 37.93% 48.78% 53.77% 37.93% 26.10% 26.10% 66.23% 75.48% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 48.78% 37.93% 48.78% 53.77% 37.93% 26.10% 26.10% 66.23% 75.48%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 37.93% 37.93% 42.19% 53.77% 27.61% 26.10% 26.10% 66.23% 75.48%
3.00 % Weight BILLABLE THIS PERIOD 10.85% 0.00% 6.60% 0.00% 10.33% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 51.22% 62.07% 51.22% 46.23% 62.07% 73.90% 73.90% 33.77% 24.52%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -22.00 -22.00 -22.00 -22.00 -22.00 -22.00 -22.00 -68.00 -68.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 0.00% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.83% 0.83% 0.86% 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 10.33% 10.33% 9.87% 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 4.25% 0.00% 4.25% 4.25% 4.25% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.25% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 0.00% 4.33% 4.33% 4.33% 0.00% 0.00% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 0.00% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 4.99% 4.99% 0.00% 0.00% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.03% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.22% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.26%
TOTAL 48.78% 37.93% 48.78% 53.77% 51.50% 36.83% 26.10% 66.23% 75.48% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 48.78% 37.93% 48.78% 53.77% 51.50% 36.83% 26.10% 66.23% 75.48%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 48.78% 37.93% 48.78% 53.77% 37.93% 26.10% 26.10% 66.23% 75.48%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 13.57% 10.73% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 51.22% 62.07% 51.22% 46.23% 48.50% 63.17% 73.90% 33.77% 24.52%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -29.00 -29.00 -29.00 -29.00 -29.00 -29.00 -29.00 -75.00 -75.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
4.01 Wires & Conduits 0.83% 0.83% 0.83% 0.83% 0.83% 0.86% 0.86% 0.83% 0.83% 0.83% 0.86%
4.02 2F Wall Concreting 10.33% 10.33% 10.33% 10.33% 10.33% 9.87% 9.87% 10.33% 10.33% 10.33% 9.87%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.25% 4.25% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 0.00% 0.00% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 1.68% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 0.00% 0.00% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.04% 4.03% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
8.05 Plumbing Fixtures 5.11% 5.32%
8.06 Electrical Fixtures 2.05% 2.13%
8.07 Final Coat Painting 2.92% 2.92% 2.40%
8.08 Clean-up & Turnover 0.09% 0.10%
8.09 Tapping to main 0.30% 0.31%
TOTAL 53.77% 51.50% 53.77% 53.77% 53.18% 36.83% 36.83% 71.27% 84.33% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 51.50% 53.77% 53.77% 53.18% 36.83% 36.83% 71.27% 84.33%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 48.78% 37.93% 48.78% 53.77% 51.50% 36.83% 26.10% 66.23% 75.48%
3.00 % Weight BILLABLE THIS PERIOD 4.99% 13.57% 4.99% 0.00% 1.68% 0.00% 10.73% 5.04% 8.85%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 48.50% 46.23% 46.23% 46.82% 63.17% 63.17% 28.73% 15.67%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -34.00 -34.00 -34.00 -34.00 -34.00 -34.00 -34.00 -80.00 -80.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 0.00% 0.00% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 0.00% 0.00% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 1.68% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 0.00% 0.00% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.04% 4.03% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
8.05 Plumbing Fixtures 5.11% 5.32%
8.06 Electrical Fixtures 2.05% 2.13%
8.07 Final Coat Painting 2.92% 2.92% 2.40%
8.08 Clean-up & Turnover 0.09% 0.10%
8.09 Tapping to main 0.30% 0.31%
TOTAL 53.77% 51.50% 53.77% 53.77% 53.18% 36.83% 36.83% 71.27% 84.33% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 51.50% 53.77% 53.77% 53.18% 36.83% 36.83% 71.27% 84.33%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 51.50% 53.77% 53.77% 53.18% 36.83% 36.83% 71.27% 84.33%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 48.50% 46.23% 46.23% 46.82% 63.17% 63.17% 28.73% 15.67%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -50.00 -50.00 -50.00 -50.00 -50.00 -50.00 -50.00 -96.00 -96.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.08% 3.08% 3.59% 3.59% 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.25% 1.25% 1.30% 1.30% 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 1.68% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.04% 4.03% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
8.05 Plumbing Fixtures 5.11% 5.32%
8.06 Electrical Fixtures 2.05% 2.13%
8.07 Final Coat Painting 2.92% 2.92% 2.40%
8.08 Clean-up & Turnover 0.09% 0.10%
8.09 Tapping to main 0.30% 0.31%
TOTAL 53.77% 51.50% 53.77% 53.77% 53.18% 51.33% 51.33% 71.27% 84.33% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 51.50% 53.77% 53.77% 53.18% 51.33% 51.33% 71.27% 84.33%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 51.50% 53.77% 53.77% 53.18% 36.83% 36.83% 71.27% 84.33%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 14.50% 14.50% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 48.50% 46.23% 46.23% 46.82% 48.67% 48.67% 28.73% 15.67%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -57.00 -57.00 -57.00 -57.00 -57.00 -57.00 -57.00 -103.00 -103.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.08% 3.08% 3.59% 3.59% 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.25% 1.25% 1.30% 1.30% 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 2.27% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 12.46% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.04% 4.03% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
TOTAL 53.77% 51.50% 53.77% 66.23% 53.77% 51.33% 51.33% 71.27% 84.33% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 51.50% 53.77% 66.23% 53.77% 51.33% 51.33% 71.27% 84.33%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 51.50% 53.77% 53.77% 53.18% 51.33% 51.33% 71.27% 84.33%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 12.46% 0.59% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 48.50% 46.23% 33.77% 46.23% 48.67% 48.67% 28.73% 15.67%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -64.00 -64.00 -64.00 -64.00 -64.00 -64.00 -64.00 -110.00 -110.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
5.01 Roof Framing 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
5.04 Prepainted GI Roof and Accessories (Brown) 3.08% 3.08% 3.08% 3.08% 3.08% 3.59% 3.59% 3.08% 3.08% 3.08% 3.59%
5.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25% 1.25% 1.25% 1.30% 1.30% 1.25% 1.25% 1.25% 1.30%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 2.27% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 12.46% 0.00% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.04% 4.03% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.15% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
TOTAL 53.77% 51.50% 53.77% 66.23% 53.77% 51.33% 51.33% 71.27% 84.33% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 51.50% 53.77% 66.23% 53.77% 51.33% 51.33% 71.27% 84.33%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 51.50% 53.77% 66.23% 53.77% 51.33% 51.33% 71.27% 84.33%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 48.50% 46.23% 33.77% 46.23% 48.67% 48.67% 28.73% 15.67%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -71.00 -71.00 -71.00 -71.00 -71.00 -71.00 -71.00 -117.00 -117.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 2.27% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 12.46% 12.46% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
TOTAL 53.77% 51.50% 53.77% 66.23% 66.23% 51.33% 51.33% 78.28% 92.45% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 51.50% 53.77% 66.23% 66.23% 51.33% 51.33% 78.28% 92.45%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 51.50% 53.77% 66.23% 53.77% 51.33% 51.33% 71.27% 84.33%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 12.46% 0.00% 0.00% 7.01% 8.12%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 48.50% 46.23% 33.77% 33.77% 48.67% 48.67% 21.72% 7.55%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -78.00 -78.00 -78.00 -78.00 -78.00 -78.00 -78.00 -124.00 -124.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 2.27% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 12.46% 12.46% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 12.05% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10% 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
TOTAL 53.77% 51.50% 53.77% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 51.50% 53.77% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 51.50% 53.77% 66.23% 66.23% 51.33% 51.33% 78.28% 92.45%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 12.05% 0.00% 0.00% 0.00% 11.25% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 48.50% 46.23% 21.72% 33.77% 48.67% 48.67% 10.47% 7.55%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -86.00 -86.00 -86.00 -86.00 -86.00 -86.00 -86.00 -132.00 -132.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 0.00% 2.27% 2.27% 2.27% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 12.05% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10% 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
TOTAL 53.77% 51.50% 66.23% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 51.50% 66.23% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 51.50% 53.77% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 12.46% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 48.50% 33.77% 21.72% 33.77% 48.67% 48.67% 10.47% 7.55%
Target date of Completion 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 5-Jul-20 20-May-20 20-May-20
No of days remaining/ delays -92.00 -92.00 -92.00 -92.00 -92.00 -92.00 -92.00 -138.00 -138.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 0.00% 0.00% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 0.00% 0.00% 12.46% 12.46% 12.46% 12.36%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 12.05% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10% 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
TOTAL 53.77% 53.77% 66.23% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 53.77% 66.23% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 51.50% 66.23% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 2.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 46.23% 33.77% 21.72% 33.77% 48.67% 48.67% 10.47% 7.55%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 436.00 436.00 102.00 436.00 391.00 436.00 133.00 26.00 26.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 0.00% 2.37% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.51% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.75% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.11% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 0.00% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 0.00% 12.05% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 10.47% 10.26%
8.05 Plumbing Fixtures 5.11% 5.32%
8.06 Electrical Fixtures 2.05% 2.13%
8.07 Final Coat Painting 2.92% 2.92% 2.40%
8.08 Clean-up & Turnover 0.09% 0.10%
8.09 Tapping to main 0.30% 0.31%
TOTAL 53.77% 53.77% 66.23% 78.28% 66.23% 51.33% 66.06% 89.53% 92.45% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 53.77% 66.23% 78.28% 66.23% 51.33% 66.06% 89.53% 92.45%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 53.77% 66.23% 78.28% 66.23% 51.33% 51.33% 89.53% 92.45%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 14.73% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 46.23% 33.77% 21.72% 33.77% 48.67% 33.94% 10.47% 7.55%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 427.00 427.00 93.00 427.00 382.00 427.00 124.00 17.00 17.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.51% 0.51% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.75% 1.75% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.11% 0.11% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 0.00% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.11% 2.92% 10.47% 10.26%
8.05 Plumbing Fixtures 5.11% 5.11% 5.32%
8.06 Electrical Fixtures 2.05% 2.13%
8.07 Final Coat Painting 2.92% 2.92% 2.40%
8.08 Clean-up & Turnover 0.09% 0.10%
8.09 Tapping to main 0.30% 0.31%
TOTAL 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 94.64% 92.45% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 94.64% 92.45%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 53.77% 66.23% 78.28% 66.23% 51.33% 66.06% 89.53% 92.45%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 12.05% 0.00% 0.00% 2.37% 0.00% 5.11% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 46.23% 21.72% 21.72% 33.77% 46.30% 33.94% 5.36% 7.55%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 420.00 420.00 86.00 420.00 375.00 420.00 117.00 10.00 10.00
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
5.06 RC Kitchen Counter 0.49% 0.49% 0.49% 0.49% 0.49% 0.51% 0.51% 0.49% 0.49% 0.49% 0.51%
5.07 Concrete Stair Case 1.68% 1.68% 1.68% 1.68% 1.68% 1.75% 1.75% 1.68% 1.68% 1.68% 1.75%
5.08 Concrete Pads, 100x300x1000mm 0.10% 0.10% 0.10% 0.10% 0.10% 0.11% 0.11% 0.10% 0.10% 0.10% 0.11%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 0.00% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.47% 10.47% 10.26%
8.05 Plumbing Fixtures 5.11% 5.11% 5.11% 5.32%
8.06 Electrical Fixtures 2.05% 2.05% 2.05% 2.13%
8.07 Final Coat Painting 2.92% 2.92% 2.92% 2.40%
8.08 Clean-up & Turnover 0.09% 0.09% 0.09% 0.10%
8.09 Tapping to main 0.30% 0.30% 0.30% 0.31%
TOTAL 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 94.64% 92.45%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.36% 7.55%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 46.23% 21.72% 21.72% 33.77% 46.30% 33.94% 0.00% 0.00%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 415.00 415.00 81.00 415.00 370.00 415.00 112.00 31-Oct-20 31-Oct-20
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 0.00% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.47% 10.47% 10.26%
8.05 Plumbing Fixtures 5.11% 5.11% 5.11% 5.32%
8.06 Electrical Fixtures 2.05% 2.05% 2.05% 2.13%
8.07 Final Coat Painting 2.92% 2.92% 2.92% 2.40%
8.08 Clean-up & Turnover 0.09% 0.09% 0.09% 0.10%
8.09 Tapping to main 0.30% 0.30% 0.30% 0.31%
TOTAL 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 46.23% 21.72% 21.72% 33.77% 46.30% 33.94% 0.00% 0.00%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 406.00 406.00 72.00 406.00 361.00 406.00 103.00 31-Oct-20 31-Oct-20
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 0.00% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 0.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 11.25% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10% 0.10% 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.47% 10.47% 10.26%
8.05 Plumbing Fixtures 5.11% 5.11% 5.11% 5.32%
8.06 Electrical Fixtures 2.05% 2.05% 2.05% 2.13%
8.07 Final Coat Painting 2.92% 2.92% 2.92% 2.40%
8.08 Clean-up & Turnover 0.09% 0.09% 0.09% 0.10%
8.09 Tapping to main 0.30% 0.30% 0.30% 0.31%
TOTAL 53.77% 53.77% 89.53% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 53.77% 89.53% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 53.77% 78.28% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 11.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 46.23% 10.47% 21.72% 33.77% 46.30% 33.94% 0.00% 0.00%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 392.00 392.00 58.00 392.00 347.00 392.00 89.00 31-Oct-20 31-Oct-20
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 0.00% 12.36% 12.46% 12.46% 12.46% 12.36%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 6.00% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.84% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.16% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 11.25% 0.00% 0.00% 0.00% 0.00% 11.25% 11.25% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.47% 10.47% 10.26%
TOTAL 53.77% 53.77% 89.53% 78.28% 66.23% 53.70% 72.06% 100.00% 100.00% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 53.77% 89.53% 78.28% 66.23% 53.70% 72.06% 100.00% 100.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 53.77% 89.53% 78.28% 66.23% 53.70% 66.06% 100.00% 100.00%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 46.23% 10.47% 21.72% 33.77% 46.30% 27.94% 0.00% 0.00%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 387.00 387.00 53.00 387.00 342.00 387.00 84.00 31-Oct-20 31-Oct-20
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 0.00% 0.00% 12.46% 12.46% 12.46% 12.36% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.90% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.68% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.09% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.69% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 6.36% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.84% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.16% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.35% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 11.25% 8.53% 0.00% 0.00% 2.22% 11.25% 11.25% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.54% 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.22% 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.22% 2.67% 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10% 0.10% 0.10% 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.47% 10.47% 10.26%
TOTAL 53.77% 53.77% 89.53% 86.81% 66.23% 66.06% 74.63% 100.00% 100.00% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 53.77% 53.77% 89.53% 86.81% 66.23% 66.06% 74.63% 100.00% 100.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 53.77% 89.53% 78.28% 66.23% 53.70% 72.06% 100.00% 100.00%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 8.53% 0.00% 12.36% 2.57% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 46.23% 46.23% 10.47% 13.19% 33.77% 33.94% 25.37% 0.00% 0.00%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 380.00 380.00 46.00 380.00 335.00 380.00 77.00 31-Oct-20 31-Oct-20
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 12.46% 0.00% 12.46% 12.46% 12.46% 12.36% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.79% 2.90% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.58% 2.68% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.43% 6.09% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.66% 0.69% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 12.54% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.84% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.16% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 5.13% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.05% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.35% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 11.25% 8.53% 0.00% 0.00% 2.22% 11.25% 11.25% 11.25% 11.14%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.47% 10.47% 10.26%
TOTAL 66.23% 53.77% 89.53% 86.81% 66.23% 66.06% 80.82% 100.00% 100.00% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 66.23% 53.77% 89.53% 86.81% 66.23% 66.06% 80.82% 100.00% 100.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 53.77% 53.77% 89.53% 86.81% 66.23% 66.06% 74.63% 100.00% 100.00%
3.00 % Weight BILLABLE THIS PERIOD 12.46% 0.00% 0.00% 0.00% 0.00% 0.00% 6.19% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 33.77% 46.23% 10.47% 13.19% 33.77% 33.94% 19.18% 0.00% 0.00%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 371.00 371.00 37.00 371.00 326.00 371.00 68.00 31-Oct-20 31-Oct-20
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 12.46% 0.00% 12.46% 12.46% 12.46% 12.36% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.79% 2.90% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.58% 2.68% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.43% 6.09% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.66% 0.69% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 12.54% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.84% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.16% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 5.13% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.05% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.35% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 11.25% 8.53% 0.00% 0.00% 2.22% 11.25% 11.25% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.54% 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.22% 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.71% 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.22% 2.67% 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10% 0.10% 0.10% 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.47% 10.47% 10.26%
TOTAL 66.23% 53.77% 89.53% 86.81% 66.23% 66.06% 80.82% 100.00% 100.00% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 66.23% 53.77% 89.53% 86.81% 66.23% 66.06% 80.82% 100.00% 100.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 66.23% 53.77% 89.53% 86.81% 66.23% 66.06% 80.82% 100.00% 100.00%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 33.77% 46.23% 10.47% 13.19% 33.77% 33.94% 19.18% 0.00% 0.00%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 345.00 345.00 11.00 345.00 300.00 345.00 42.00 31-Oct-20 31-Oct-20
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 AT 100% AT 100%
MODULE
ACCOMPLISHMENT ACCOMPLISHMENT
PAY ITEMS B1101 B1102 B1103 B1105 B1107 B1109 B1111 B1433 B1701
NO. SINGLE UNIT CORNER DUPLEX
SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT SINGLE UNIT CORNER DUPLEX CORNER DUPLEX SINGLE UNIT SINGLE UNIT
Module I SUB - STRUCTURE 10.14% 10.14% 10.14% 10.14% 10.14% 9.80% 9.80% 10.14% 10.14% 10.14% 9.80%
Module II GROUND FLOOR RC WALL 10.07% 10.07% 10.07% 10.07% 10.07% 9.47% 9.47% 10.07% 10.07% 10.07% 9.47%
Module III SECOND FLOOR SUSPENDED SLAB 6.57% 6.57% 6.57% 6.57% 6.57% 6.83% 6.83% 6.57% 6.57% 6.57% 6.83%
Module IV SECOND FLOOR RC WALL 11.15% 11.15% 11.15% 11.15% 11.15% 10.73% 10.73% 11.15% 11.15% 11.15% 10.73%
Module VA STEEL FRAMING WORKS 4.25% 4.25% 4.25% 4.25% 4.25% 4.43% 4.43% 4.25% 4.25% 4.25% 4.43%
Module VB ROOFING & ACCESSORIES 4.33% 4.33% 4.33% 4.33% 4.33% 4.88% 4.88% 4.33% 4.33% 4.33% 4.88%
Module VC MISCELLANEOUS CONCRETE 2.27% 2.27% 2.27% 2.27% 2.27% 2.37% 2.37% 2.27% 2.27% 2.27% 2.37%
Module VD MASONRY FINISHES 12.46% 0.00% 12.46% 12.46% 12.46% 12.36% 12.36% 12.46% 12.46% 12.46% 12.36%
5.09 Exterior Steel Doors & Jambs 2.79% 2.79% 2.79% 2.79% 2.90% 2.90% 2.79% 2.79% 2.79% 2.90%
5.10 CHB Wall Masonry/ CR Flooring 2.58% 2.58% 2.58% 2.58% 2.68% 2.68% 2.58% 2.58% 2.58% 2.68%
5.11 Wall & Concrete Finishes 6.43% 6.43% 6.43% 6.43% 6.09% 6.09% 6.43% 6.43% 6.43% 6.09%
5.12 Concrete Mouldings & Canopy 0.66% 0.66% 0.66% 0.66% 0.69% 0.69% 0.66% 0.66% 0.66% 0.69%
Module VI SLAB-ON-FILL 4.99% 4.99% 4.99% 4.99% 4.99% 5.19% 5.19% 4.99% 4.99% 4.99% 5.19%
1.06 2000psi Slab-on-Fill, 100mm 3.33% 3.33% 3.33% 3.33% 3.33% 3.46% 3.46% 3.33% 3.33% 3.33% 3.46%
1.07 PVC Pipe & Fittings 0.81% 0.81% 0.81% 0.81% 0.81% 0.84% 0.84% 0.81% 0.81% 0.81% 0.84%
1.08 Wires & Conduits 0.85% 0.85% 0.85% 0.85% 0.85% 0.88% 0.88% 0.85% 0.85% 0.85% 0.88%
Module VII CARPENTRY 0.00% 0.00% 12.05% 12.05% 0.00% 0.00% 12.54% 12.05% 12.05% 12.05% 12.54%
7.01 Ceilings, Eaves & Vents 3.69% 3.69% 3.84% 3.69% 3.69% 3.69% 3.84%
7.02 Dry Wall Partitions(Double-walled) 2.08% 2.08% 2.16% 2.08% 2.08% 2.08% 2.16%
7.03 Interior PVC Doors & Jambs 4.93% 4.93% 5.13% 4.93% 4.93% 4.93% 5.13%
7.04 Cabinet Doors 1.01% 1.01% 1.05% 1.01% 1.01% 1.01% 1.05%
7.04 Wires & Conduits 0.34% 0.34% 0.35% 0.34% 0.34% 0.34% 0.35%
Module VIIIA FINISHING WORKS 0.00% 0.00% 11.25% 8.53% 0.00% 0.00% 11.14% 11.25% 11.25% 11.25% 11.14%
5.02 Stair Railings 0.54% 0.54% 0.56% 0.54% 0.54% 0.54% 0.56%
8.03 Aluminum Windows 5.22% 5.22% 5.43% 5.22% 5.22% 5.22% 5.43%
8.01 Tileworks 2.71% 2.82% 2.71% 2.71% 2.71% 2.82%
8.02 1st Coat Painting 2.67% 2.67% 2.22% 2.67% 2.67% 2.67% 2.22%
8.04 Lot Levelling 0.10% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.47% 10.47% 10.47% 10.26%
TOTAL 66.23% 53.77% 89.53% 86.81% 66.23% 66.06% 89.74% 100.00% 100.00% 100.00% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 66.23% 53.77% 89.53% 86.81% 66.23% 66.06% 89.74% 100.00% 100.00%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 66.23% 53.77% 89.53% 86.81% 66.23% 66.06% 80.82% 100.00% 100.00%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.92% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 33.77% 46.23% 10.47% 13.19% 33.77% 33.94% 10.26% 0.00% 0.00%
Target date of Completion 20-Dec-21 20-Dec-21 20-Jan-21 20-Dec-21 5-Nov-21 20-Dec-21 20-Feb-21 5-Nov-20 5-Nov-20
No of days remaining/ delays 338.00 338.00 4.00 338.00 293.00 338.00 35.00 31-Oct-20 31-Oct-20