BOBOT PEKERJAAN

PEKERJAAN BAJA PENGGANTIAN ATAP SENG DAN TALANG AIR PADA BANGUNAN BLEACING EARTH

PEKERJAAN : Pemasangan Dan Pembongkaran Atap


LOKASI : IBP Bukit Kapur
MINGGU : -
TAHUN : 2022

PEMASANGAN DAN PEMBONGKARAN ATAP BUKIT KAPUR


006/IBP/DMI-BKR/MAIN/XI/2021

Progress Percentage Progress Weight


No Task Description Qt'y Bobot Price ( Rp ) Remarks
Previous To date This Previous To date This
A Pekerjaan Persiapan
1 Listrik Kerja ( by Owner ) 1.00 0.00%
2 Air Kerja ( by Owner ) 1.00 0.00%
3 Pembersihan Lokasi pada awal dan akhir pekerjaan 1.00 0.00%
4 Pekerjaan Persiapan 1.00 4.0337% 0.00% 50.00% 50.00% 4.03% 2.02% 2.02%
5 Perizinan dan Keamanan 1.00 3.8620% 0.00% 100.00% 100.00% 3.86% 3.86% 3.86%
6 Mobilisasi Manpower 6.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Mobilisasi Peralatan Kerja 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Mess Pekerja 1.00 2.1456% 0.00% 100.00% 100.00% 2.15% 2.15% 2.15%
9 Scaffolding 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

B Pekerjaan Bongkar
1 Upah Pekerjaan pembongkaran atap seng galvalume tb. 0.4mm eksisting 2.00 20.2802% 60.00% 160.00% 100.00% 80.28% 32.45% 20.28%
Atap Seng Area Aging Bay 7
Seng galvalume tebal = 0.4mm 228.00
Rabung seng galvalume tebal = 0.4mm 13.64
Atap Seng area Formula
Seng galvalume tebal 0.4mm 76.00
Rabung seng galvalume tebal = 0.4mm 4.55
Atap seng area Robot / Produksi
Seng galvalume tebal 0.4mm 4,408.00
Flassing Seng galvalume tebal = 0.4mm 313.64

HARGA BORONGAN
Atap Seng area Brick Plant
Seng galvalume tebal 0.4mm 5,104.00
Flassing Seng galvalume tebal = 0.4mm 354.55
2 Upah Pekerjaan Pembongkaran talang plate MS 3,188.43 6.1569% 0.00% 100.00% 100.00% 6.16% 6.16% 6.16%
Talang Area Robot/produksi
Plate MS 2mm 4' X 8' 1,477.57
Talang area Brick Plant
Plate MS 2mm 4' X 8' 1,710.87

C Pekerjaan Pasang
1 Upah pekerjaan pemasangan atap seng galvalume tb. 0.4mm Kembali 10,502.36 40.5604% 60.00% 160.00% 100.00% 100.56% 64.90% 40.56%
Atap Seng Area Aging Bay
Seng galvalume tebal = 0.4mm 228.00
Rabung seng galvalume tebal = 0.4mm 13.64
Atap Seng area Formula
Seng galvalume tebal 0.4mm 76.00
Rabung seng galvalume tebal = 0.4mm 4.55
Atap seng area Robot / Produksi
Seng galvalume tebal 0.4mm 4,408.00
Flassing Seng galvalume tebal = 0.4mm 313.64
Atap Seng area Brick Plant
Seng galvalume tebal 0.4mm 5,104.00
Flassing Seng galvalume tebal = 0.4mm 354.55
Scrupe 12mm x 45 mm hexagon head (material by contractor ) 7,853.00 4.0438% 45.00% 145.00% 100.00% 49.04% 5.86% 4.04%

2 Upah pekerjaan pabrikasi dan pemasangan talang plate SS304 2,419.00 15.5704% 0.00% 70.00% 70.00% 15.57% 10.90% 10.90%
Talang area Robot/produksi
SS 304 Plate 1.5mm 4' X 8' 1,121.00
Talang area brick plant
SS 304 Plate 1.5mm 4' X 8' 1,298.00

3 Pekerjaan perapian atap seng setelah dipasang kembali 1.00 3.3471% 0.00% 70.00% 70.00% 3.35% 2.34% 2.34%

Total 100.00% 90.32% 40.47% 92.31% 30,000,000.00


Total Out Cash 27,692,400.00