1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 AT 100% ACCOMPLISHMENT
MODULE
PAY ITEMS B06L03 B06L04 B08L01 B08L02 B08L03 B08L04 B12L05 B12L06
NO. DUPLEX UNIT
DUPLEX UNIT DUPLEX UNIT DUPLEX UNIT DUPLEX UNIT DUPLEX UNIT DUPLEX UNIT DUPLEX UNIT DUPLEX UNIT
Module I SUB - STRUCTURE 9.18% 9.18% 9.18% 9.18% 9.18% 9.18% 9.18% 9.18% 9.18%
1.01 Layout, Batterboards & Excavation 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62%
1.02 2500psi RC Wall Footing 2.68% 2.68% 2.68% 2.68% 2.68% 2.68% 2.68% 2.68% 2.68%
1.03 Wooden Zucallo Forms,600x2400mm 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83%
1.04 2500psi RC Zucallo Wall 2.43% 2.43% 2.43% 2.43% 2.43% 2.43% 2.43% 2.43% 2.43%
1.05 Septic Vault,1200x2800x1600mm 2.63% 2.63% 2.63% 2.63% 2.63% 2.63% 2.63% 2.63% 2.63%
Module II GROUND FLOOR RC WALL 10.26% 10.26% 10.26% 10.26% 10.26% 10.26% 10.26% 10.26% 10.26%
Module III SECOND FLOOR SUSPENDED SLAB 7.25% 7.25% 7.25% 7.25% 7.25% 7.25% 7.25% 7.25% 7.25%
3.01 2F Slab Concreting 7.25% 7.25% 7.25% 7.25% 7.25% 7.25% 7.25% 7.25% 7.25%
Module IV SECOND FLOOR RC WALL 11.49% 11.49% 11.49% 11.49% 11.49% 11.49% 11.49% 11.49% 11.49%
Module VA STEEL FRAMING WORKS 3.77% 3.77% 3.77% 3.77% 3.77% 3.77% 3.77% 3.77% 3.77%
5.01 Roof Framing 3.77% 3.77% 3.77% 3.77% 3.77% 3.77% 3.77% 3.77% 3.77%
Module VB ROOFING & ACCESSORIES 4.15% 4.15% 4.15% 4.15% 4.15% 4.15% 4.15% 4.15% 4.15%
Module VC MISCELLANEOUS CONCRETE 2.40% 2.40% 2.40% 2.40% 2.40% 2.40% 2.40% 2.40% 2.40%
Module VD MASONRY FINISHES 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48% 12.48%
Module VI SLAB-ON-FILL 5.14% 5.14% 5.14% 5.14% 5.14% 5.14% 5.14% 5.14% 5.14%
1.06 2000psi Slab-on-Fill, 100mm 3.48% 3.48% 3.48% 3.48% 3.48% 3.48% 3.48% 3.48% 3.48%
1.07 PVC Pipe & Fittings 0.72% 0.72% 0.72% 0.72% 0.72% 0.72% 0.72% 0.72% 0.72%
1.08 Wires & Conduits 0.94% 0.94% 0.94% 0.94% 0.94% 0.94% 0.94% 0.94% 0.94%
Module VII CARPENTRY 13.39% 13.39% 13.39% 13.39% 13.39% 13.39% 13.39% 13.39% 13.39%
Module VIIIA FINISHING WORKS 9.89% 9.89% 9.89% 9.89% 9.89% 9.89% 9.89% 0.00% 9.89%
Module VIIIB MOVE-IN-WORKS 10.59% 10.59% 10.59% 0.00% 10.59% 10.59% 10.59% 0.00% 10.59%
8.05 Plumbing Fixtures 4.51% 4.51% 4.51% 4.51% 4.51% 4.51% 4.51%
8.06 Electrical Fixtures 2.33% 2.33% 2.33% 2.33% 2.33% 2.33% 2.33%
8.07 Final Coat Painting 3.40% 3.40% 3.40% 3.40% 3.40% 3.40% 3.40%
8.08 Clean-up & Turnover 0.08% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08%
8.09 Tapping to main 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26%
TOTAL 100.00% 100.00% 100.00% 89.41% 100.00% 100.00% 100.00% 79.53% 100.00%
1.00 % Weight TOTAL ACCOMPLISHMENT 100.00% 100.00% 100.00% 89.41% 100.00% 100.00% 100.00% 79.53%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 89.41% 100.00% 100.00% 79.53% 100.00% 100.00% 100.00% 79.53%
3.00 % Weight BILLABLE THIS PERIOD 10.59% 0.00% 0.00% 9.89% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 0.00% 0.00% 0.00% 10.59% 0.00% 0.00% 0.00% 20.47%
Target date of Completion 20-Jan-22 20-Sep-21 5-Aug-21 20-Jan-22 5-Oct-21 5-Oct-21 20-Sep-21 20-Jan-22
No of days remaining/ delays 35.00 18-Oct-21 5-Jul-21 35.00 4-Oct-21 5-Aug-21 22-Nov-21 35.00