WEEKLY ACCOMPLISHMENT REPORT

PROJECT : PROPOSED 3-STOREY RESIDENTIAL BUILDING


LOCATION : K-7th St., Brgy. East Kamias, Quezon City

I. ACCOMPLISHED WORK
Period : From July 26, 2022 to December 16, 2022
118
Covered: Day #
348
START DATE: 25-Jul-22
END DATE: 31-Aug-23

WORK ITEMS PREVIOUS THIS WEEK TO DATE


PERCENTAGE OF WORK ACCOMPLISHMENT
1.0 General Requirements 4.87% 4.87%
2.0 Site Works -
2.1 Site Preparation 0.91% 0.91%
2.2 Demolition Works 0.80% 0.80%
2.3 Excavation 0.49% 0.49%
2.4 Backfill and Compaction 0.30% 0.30%
2.5 Gravel Bedding 0.38% 0.38%
2.6 Soil Poisoning 0.20% 0.20%
3.0 Structural Works -
3.1 Reinforcement 9.45% 9.45%
3.2 Formworks 6.08% 6.08%
Concreting (footing, ftb, beams, columns,
3.3
stairs, and floor slabs) 6.08% 6.08%
3.4 Vapor Barrier Installation - -
3.5 Roof Framing - -
3.6 Masonry Works 2.89% 2.89%
4.0 Architectural Works -
4.1 Carpentry Works - -
4.2 Ceiling Works - -
4.3 Tiling Works - -
4.4 Cementitious Waterproofing - -
4.5 Painting Works - -
4.6 Wall Finishes - -
4.7 Roofing Works - -
5.0 Plumbing Works -
5.1 Septic Tank, Catch Basin and Trench Drain 0.92% 0.92%
5.2 Roughing-ins 0.70% 0.70%
5.3 Chipping Works 0.02% 0.02%
5.4 Concrete Restoration - -
5.5 Installation of Plumbing Fixtures - -
6.0 Electrical Works -
6.1 Roughing-ins 0.77% 0.77%
6.2 Chipping Works 0.06% 0.06%
6.3 Concrete Restoration - -
6.4 Wire Pulling - -
6.5 Panel Board - -
6.6 Installation of convenience outlet and switches - -
6.7 Installation of lighting fixtures - -
6.8 Installation of strip lights - -
6.9 testing and commissioning - -
TOTAL 0.00% 34.91% 34.91%
COMMULATIVE ACTUAL WEEKLY ACCOMPLISHMENT 34.91%
COMMULATIVE PLANNED WEEKLY ACCOMPLISHMENT 45.89%
SLIPPAGE -10.99%
II. REASON/S FOR NEGATIVE SLIPPAGE
1.0 Primary reason for slippage or project delay was the weather condition during the month
August. Heavy rains and typhoons causes work stoppage and flood water on excavated areas
consumed time for draining and pumping out.
2.0 Problems encountered stated in item III also contributed to project delays.

III. PROBLEMS ENCOUNTERED ACTIONS TAKEN


Water seepage along the perimeter of After locating all the sources of water seepage that
property. passes thru subsoil, the contractor provide
reinforcements along the property lines by
applying water proofing on poured concrete, to
prevent running water that may cause soil caving
in the future.
Shared septic tank of Lot D Repeated siphoning of Septic Tank contents by
Malabanan and Manila Waters.
Work selection (sometimes stoppage) due to The contractor seeks assistance from the Office of
noise complaints from neighbors. Baranggay Captain by submitting a justification
letter, which was approved this December 2, 2022
only. The said noise complaints from neighbors
causes us to limit working hours, hence resulting
to further project delays.

IV. REQUISITION OF CONSTRUCTION FUNDS


May we request the amount of Two Million Thirty-One Thousand Four Hundred Forty-Two &
29/100 as scheduled by contract to supplement up to 46% of work progress

Item No. Item Description Amount


1.00 Billing No. 1 2,138,360.31
less: Retention as per contract 106,918.02

TOTAL AMOUNT DUE 2,031,442.29

V. LIST OF WORK VARIATIONS/ CHANGE ORDER

The contractor is constantly in coordination with the designer, Ar. Alvin Matias, it is inevitable
for changes and revisions as the construction work progresses. As stated in the contract, we will
present all work variations, additions, and revisions with corresponding deductive and additive
amounts, which will serve as a reference to the overall project completion. Kindly refer to the
attachments please for the said work variation and change orders.

Prepared by:

Dasmin Anne Depacaquibo


JKL Design Group Co., Project Manager

Noted by: Conforme:

Ar. Sheree Ann Acutina Mr. Michael Gallego and Luther Gumia
JKL Design Group Co., Principal Architect Project Owners