PROGRESS STATUS REPORT

As of 31 Dec, 2023

Client: AL INMA BANK Contractor: ANSAQ CONTRACTING Co.


Project Name AL RABEA GADEER BRANCH Area:
Project Code. 23406 City: RIYADH
Contract No. District

Contract Value

Original Contract Value SR. 4,281,389.55


Approved Change Orders -
New Contract Value SR. 4,281,389.55

Contract Completion Date

Contract Duration (Branch) 139 Days

Site Delivery Date (Branch Building) 06 Dec 2023

Work Commence date (as per site delivery.) 22 Apr.2024

Original Completion Date (Branch Bldg.)

Days Elapsed (Branch Building) 26 Days

Days Remaining (Branch Building) 113 Days

A-Change orders and stop duration

Change Orders

Approved Approved Approved


No. Description Reasons Remarks
Value Time Ext.
MBCE Client

Stop Duration

No. Description Reasons Approved Duration Remarks

Report as of 31 Dec 2023 Page 1 of 3 AL RABEA GADEER BRANCH


B - Project Progress

B Activities Progress
Const. as
No. Description Previous This period Total Status
per contract
BOQ Progress Progress Progress
AL RABEA GADEER BRANCH
OVER ALL PROGRESS 3.20% 6% 9.20% Ongoing

1 MAIN BUILDING 3.20% 9.75% 9.95% In progress


1.1 Structural / Architectural Works. 5.60% 4.52% 10.12% In progress
DEMOLITION WORKS AND SITE WORKS 59.00% 28.5% 87.5% In progress
CONCRETE 19.20% 6.3% 25.5% In progress
MASONRY WORKS 0% 0% 0% In progress
METAL WORKS 0% 0.36% 0.36% In progress
WOOD AND PLASTIC 0% 0% 0% In progress
THERMAL & MOISTURE PROTECTION 0% 0% 0% In progress
DOORS, WINDOWS & GLASS 0% 1% 1%
In progress
PARTITIONS
FINISHES 2.00% 2.6% 4.6% In progress
FLOOR FINISHES 6.37% 8.09% 14.46% In progress
WALL FINISHES 0% 0% 0% In progress
CEILING FINISHES 0% 0% 0% In progress
PAINTING 0% 0% 0% In progress
SPECIALTIES 0% 0% 0% In progress
EQUIPMENT 0% 0% 0% In progress
1.2 MECHANICAL WORKS MAIN BUILDING 0% 5.4% 5.4% In progress
MECHANICAL - PLUMBING WORKS 0% 5% 5% In progress
MECHANICAL-H.V.A.C. WORKS 0% 5.81% 5.81% In progress
MECHANICAL- FIRE PROTECTION 0% 3.42% 3.42% In progress
1.3 ELECTRICAL WORKS 0% 10% 10% In progress

Report as of 31 Dec 2023 Page 2 of 3 AL RABEA GADEER BRANCH


C- Delayed Activities

No. Delayed Activities Justification Recovery Action

1.

2.

Attached Documents
1. Pictures

AL-MUTLAQ & BU-NUHAYAH

Project Manager : Eng. Alvin H. Aragon

Supervision Head : Arch. Vinod Chaku

Structural Engineer : Eng. Gerald Pecaoco

Architect : Arch. Ali Saleh Alami

Electrical Engineer : Eng. Imran Mohammad Abdul

Mechanical Engineer : Eng. Mohammed Kashif

Sincerely yours,

Al-Mutlaq & Bu-Nuhayah

Engr. Mohammad Bu-Nuhayah


Asst. General Manager
CC: MM/FA/GB/VC/File

Report as of 31 Dec 2023 Page 3 of 3 AL RABEA GADEER BRANCH