a Electrical Drawing, VIE Details Sharing by C&ES Completed 1/1/2023 05/.01/2023 Ibrahim/Nahin 100%
CHALLENGES
SLD not found from CMES .Rangpur Site team help us to create SLD based on
physical status..
Done
Done
MOC approved from All TS.Rest of the job will be caried out by deliver in the
system
MOC approved from PGOE and other TS
Tentative date after receiving the VIE tank
Need update from CMES. PO from Procurement done
After Installation tank 15 days required to completed piping job
End of January
as per DoE visit date
as per DoE license issue date
Completed
Completed
Completed
SC released. And work has been started
Platform Casting Done.Around 21 days required for curing .
BOQ Raised to Procurement for Quotation
Done
Curing is completed . After VIE installation that Shed work will be started
Need to get quotation ,SC permission and PO from Procurement
In Progress
Done
Done
waiting for VIE installation
Done
TARGET
SL# TASK/ACTIVITY DETAILS ISSUES DISCUSSED/CONCERN AREA CLOSURE DRI UPDATE ON 13th November
DATE
Capex raised for previous Rupgnaj PCC
1 CAPEX APPROVAL NA NAHIN
prjoject.
3 MOC Application Doc require from C&ES 31/Oct NAHIN Need Site layout, SLD, VIE details to initiate MOC
LICENSE & LEGAL
4 Ammendment of 20 KL VIE 15/Jan IBRAHIM After recival of 10 KL INOX VIE ammendmend application will be submitted
COMPLIANCE
FOUNDATION CONSTRUCTION
5 VIE Foundation IBRAHIM-NAHIN BOQ sharing with Proc
& CIVIL WORKS
6 ELECTRICAL WORKS IBRAHIM-NAHIN
EQUIPMENT INSTALLATION-
7 IBRAHIM-NAHIN
TANK
10 PROJECT HANDOVER