Excel Project Plan Template

Excel Template by ProjectPlanTemplate.Net

Info Excel Project Plan Template for Project Planning and Management
Advanced Templates4

Usage
Enter the Project Details and the Project Timelines in the Required Columns of the Data Table
And the Gantt chart is created automatically based on your data.

ProjectPlanTemplate.Net is created for making useful templates for Project Management and
Planning.
Please
Share
Please share our file with your colleagues and friends, it helps us to create better tools and
motivates us to build more templates based on the user suggestions.

Visit us ProjectPlanTemplate.Net
mplate
ate.Net Get our Prem
Project Management Te
Advanced Templates4

Columns of the Data Table.

r Project Management and

o create better tools and


ns.

4 Download Now
late.Net
ur Premium
nagement Templates
Project Name EOT Crane Installation Schedule of Compresor Shelter T
TOTAL TASKS 15 Duration
Completed 0 Project Start
In progress 2 Project End
Not Started 13

Tasks Responsible Start Date End Date

Steel Structure installation Civil 1/11/2023 3/10/2023


Submission and approval of SIKA Person 2 2/2/2023 3/6/2023
Install Scaffolding on booth side Person 3 3/21/2023 4/15/2023
Survey of Corbel elevation & pos Person 4 4/16/2023 4/17/2023
Line marking of Runway profile in Person 5 4/18/2023 4/19/2023
Ground assembly of Trolley and H Person 6 4/20/2023 4/22/2023
runway profile installation & co Person 7 4/23/2023 4/28/2023
Runway girder level check (if req Person 8 4/29/2023 4/30/2023
Tie-back connection of Runway p Person 9 5/1/2023 5/8/2023
Block rail pre-install and check l Person 10 5/8/2023 5/9/2023
Block rail welding Person 1 5/10/2023 5/16/2023
End stopper install Person 2 5/10/2023 5/13/2023
Lifting Bridge girder onto the Bloc Person 3 5/15/2023 5/16/2023
Busbar install Inspection (if requ Person 4 5/17/2023 5/19/2023
Statutory inspection / Functional Person 5 5/20/2023 5/22/2023
of Compresor Shelter TM 335-02
132 Overall
1/11/2023 Progress

5/22/2023
5%
95%

Progress Status Duration Completed Pending Steel Structure installation

Submission and approval of SIKA


50% In progress 59 30 29
Install Scaffolding on booth side
30% In progress 33 10 23
0% Not Started 26 0 26 Survey of Corbel elevation & position

0% Not Started 2 0 2
Line marking of Runway profile install position
0% Not Started 2 0 2
Ground assembly of Trolley and Hoist on the Bridge girder
0% Not Started 3 0 3
0% Not Started 6 0 6 runway profile installation & connection
0% Not Started 2 0 2
Runway girder level check (if required insert shim plate)
0% Not Started 8 0 8
0% Not Started 2 0 2 Tie-back connection of Runway profile

0% Not Started 7 0 7 Block rail pre-install and check level & diagonal
0% Not Started 4 0 4
Block rail welding
0% Not Started 2 0 2
0% Not Started 3 0 3 End stopper install
0% Not Started 3 0 3
Lifting Bridge girder onto the Block rail

Busbar install Inspection (if required,

Statutory inspection / Functional test / Load test


Gantt Chart

10/16/2022

3/15/2023
12/5/2022

1/24/2023

6/23/2023
5/4/2023
Steel Structure installation

Submission and approval of SIKA

Install Scaffolding on booth side

Survey of Corbel elevation & position

Line marking of Runway profile install position

assembly of Trolley and Hoist on the Bridge girder

runway profile installation & connection

ay girder level check (if required insert shim plate)

Tie-back connection of Runway profile

Block rail pre-install and check level & diagonal

Block rail welding

End stopper install

Lifting Bridge girder onto the Block rail

Busbar install Inspection (if required,

Statutory inspection / Functional test / Load test


5/4/2023

6/23/2023