Project Start Date 07th July-2022

BQIP-022 Calendar
Completion Date : 16th October-2023
Project Start Date 7th July, 2022

BQIP-022 Calendar
Completion Date 16th October, 2023

PROJECT BASELINE MILESTONES

OVERALL PROJECT
132/11 kV PIDC Grid Station, Extension Start: 7th July, 2022
works at Remote end & associated D/C Finish: 16th October, 2023
DESIGN PHASE
132 kV Transmission Line at BQIP Start: 7th July, 2022
Finish: 01st November, 2022

▪ BQIP Grid Station PROCUREMENT PHASE


Start: 03rd August, 2022
▪ Pipri West (Remote End) Finish: 12th September,2023

CONSTRUCTION
▪ Transmission Line Start: 18th July, 2022
Finish: 16th October, 2023

Boundary Wall Progress Update


Boundary Wall Weightage Distribution Boundary Wall Progress Status
17% 120%
100%
Substructure Works 100% 90%
Substructure Works
Superstructure Works 80%
Superstructure Works
Finishes Works 60%
Finishes Works
40% 30%
55% 20%
28%
0%

Progress Highlights:
• Completed work is approved by the Engineer/Employer with signed RFIs.
• First progress invoice was submitted and approved by the Employer.
• Remaining activities of the boundary wall construction are being fast tracked to be completed in Mar, 23.
Project Start Date: 07- July-2022

BQIP-022 Calendar
Completion Date : 16th October-2023

GIS Building Progress Update

GIS Building Weightage Distribution Substructure Works WBS


10%
10%

10% 30%

10%
Substructure
40%
Superstructure
5% Foundation Works
Walls
Short Columns
Cable Trench
Situ Concrete
Finishes
3% Plinth Beam
Overhead Gantry Crane
HVAC Works

12% 40%
30%

Progress Highlights:
• Survey and Marking of Substructure Foundations is complete.
• Excavation of Structural foundations is complete.
• Formwork for Lean concrete is in progress.
• Steel fixing for footings is in progress.