Ref: No. P-2057/SCADA-III/GM/20231218_RTU 12 January 2024

Attn: Chief Engineer / PD (PMU), SCADA-III Project


625 WAPDA House, Lahore.
SUBJECT: CONTRACT NO. ADB-202R-2019: PROCUREMENT OF PLANT - DESIGN, SUPPLY,
INSTALLATION, TESTING AND COMMISSIONING OF SCADA PHASE-3 AND REVENUE
METERING SYSTEM (RMS) FOR NTDCL -
Consultant Letter to Employer- RTU Site Report Week 52

Dear Sir,
Please find the site issues and observations as stated below:

1. 220kV Grid Station Bund Road (SR-027):

We have noticed that despite our repeated notifications, CMEC has yet to install the function
module (diode) and holder for ABB interface relays. There is concern that the absence of a diode
may lead to the occurrence of reverse polarity in the power supply.

Below mentioned is a summary of RTU site activities from Dec 25 – Dec 31, 2023:

- Due to fog outdoor activities could not be carried out on Dec 26 th & 27th, whereas interface
relay installation and termination has been carried out in SIC panel. One interface relay has
been successfully tested by operating a field device i.e. E14Q12 (Isolator)

ABB interface relay installation, cable termination and tagging in SIC panel
M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB
- Cable termination is also started in SIC panel. Only indication (status) signals termination in
SIC panel had been completed, whereas the terminations for alarm, control and
measurement signals is remaining.
- Cable termination and tagging for 220kV marshalling box had been completed.

220kV Marshalling Box Cable termination Cable termination in Marshalling kiosk

Below mentioned works are percentage progress of the works related to the LDS-II missing RTU signals:

220kV Substation Bund Road (SR-027)

Cable Termination BOQ Items Installation


Cable Continuity
Date Local
Laying Marshalling Check TAP Intermediate Marshalling
SIC Panel Remote
Box Transducer Relay Box
Switch
Dec 25, 2023 - - - - - - - -

Dec 26, 2023 - ≈ 20% ≈ 10% - - - ≈ 50% -

Dec 27, 2023 - ≈ 10% ≈ 10% - - - ≈ 45% -

Dec 28, 2023 - 0% ≈ 8% - - - - -

Dec 29, 2023 - 0% 0% - - - - -

Dec 30, 2023 - 0% 0% - - - - -

Dec 31, 2023 - 0% 0% - - - - -


Previous
≈ 100% ≈ 70% ≈ 5% 0% 0% 0% ≈ 5% 100%
Progress

Total ≈ 100% ≈ 100% ≈ 33% 0% 0% 0% ≈ 100% 100%


M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB

Sincerely,

Gibran Malik

LDPIII Consultant – Testing & Commissioning Manager