You are on page 1of 3

M/s.

SAGE Automation (Australia)


& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB
Project Office:
142-H Model Town, Lahore – Pakistan.
Phone: +92-42-35442443, 38931663

Ref: No. P-2057/SCADA-III/GM/20231218_RTU 12 January 2024

Attn: Chief Engineer / PD (PMU), SCADA-III Project


625 WAPDA House, Lahore.
SUBJECT: CONTRACT NO. ADB-202R-2019: PROCUREMENT OF PLANT - DESIGN, SUPPLY,
INSTALLATION, TESTING AND COMMISSIONING OF SCADA PHASE-3 AND REVENUE
METERING SYSTEM (RMS) FOR NTDCL -
Consultant Letter to Employer- RTU Site Report Week 50

Dear Sir,
Please find the site issues and observations as stated below.

1. Delayed delivery of Installation material at site (SR-027):

It has come to our attention that CMEC has not delivered the installation material i.e. cable
(20x1.0mm & 24x1.0mm) for laying up to RTU and the SIC cabinet. Moreover, the delay in delivery
of cable conduit has also delayed the schedule for the subject works. Employer, Consultant and
CMEC representative were present to witness the installation of subject work dated Dec 11, 2023.
CMEC’s inadequate manpower was observed resulting in slower progress.
M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB

Below is a summary of RTU site activities for different cables laying at 132kV side from Dec 11 - 17,
2023.

220kV Substation Bund Road (SR-027)


BOQ Items
Cable Termination
Cable Continuity
Date Marshalling RTU Local TAP Intermediate Marshalling
Laying Check
Box Panel Remote Transducer Relay Box
Switch
Dec 11, 2023 0% - - - - - - 100%

Dec 12, 2023 ≈ 5% - - - - - - -

Dec 13, 2023 ≈ 5% - - - - - - -

Dec 14, 2023 ≈ 5% - - - - - - -

Dec 15, 2023 ≈ 5% - - - - - - -

Dec 16, 2023 ≈ 3% - - - - - - -

Dec 17, 2023 ≈ 3% - - - - - - -

Total ≈ 26% 0% 0% 0% 0% 0% 0% 100%

Bay Type Length(s) Completed


132 kV E12 Q1 4×1.0 mm² 38 meter
132 kV E12 Q1 3×2.5 mm² 38 meter
132 kV E12 Q11 4×1.0 mm² 45 meter
132 kV E12 Q12 4×1.0 mm² 30 meter
132 kV E13 Q1 4×1.0 mm² 44 Meter
132 kV E13 Q1 3×2.5 mm² 44 meter
132 kV E13 Q11 4×1.0 mm² 53 meter
132 kV E13 Q12 4×1.0 mm² .35 meter
132 kV E14Q1 4×1.0 mm² 16 meter
132 kV E14 Q1 3×2.5 mm² 16 meter
132 kV E14 Q 11 4×1.0 mm² 35 meter
132 kV E14 Q12 4×1.0 mm² 15 meter
132 kV E6 106 Q10 4×1.0 mm² 106 Meter
132 kV General cable 24×1.0 mm² .232 meter
132 kV General cable 20×2.5 mm² .232 meter

Aforementioned works are related to the LDS-II missing RTU signals.


M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB
Sincerely,

Gibran Malik

LDPIII Consultant – Testing & Commissioning Manager

Ph: +61 407281998, 03062165858


Email: LDPIIIConsultant@sageautomation.com, Gibran.malik@sageautomation.com

You might also like