Dear Sir,
Please find the site issues and observations as stated below.
It has come to our attention that CMEC has not delivered the installation material i.e. cable
(20x1.0mm & 24x1.0mm) for laying up to RTU and the SIC cabinet. Moreover, the delay in delivery
of cable conduit has also delayed the schedule for the subject works. Employer, Consultant and
CMEC representative were present to witness the installation of subject work dated Dec 11, 2023.
CMEC’s inadequate manpower was observed resulting in slower progress.
M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB
Below is a summary of RTU site activities for different cables laying at 132kV side from Dec 11 - 17,
2023.
Gibran Malik