M/s.

SAGE Automation (Australia)


& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB
Project Office:
142-H Model Town, Lahore – Pakistan.
Phone: +92-42-35442443, 38931663

Ref: No. P-2057/SCADA-III/GM/20231218_RTU 12 January 2024

Attn: Chief Engineer / PD (PMU), SCADA-III Project


625 WAPDA House, Lahore.
SUBJECT: CONTRACT NO. ADB-202R-2019: PROCUREMENT OF PLANT - DESIGN, SUPPLY,
INSTALLATION, TESTING AND COMMISSIONING OF SCADA PHASE-3 AND REVENUE
METERING SYSTEM (RMS) FOR NTDCL -
Consultant Letter to Employer- RTU Site Report Week 51

Dear Sir,
Please find the site issues and observations as stated below.

1. 220kV Grid Station Bund Road (SR-027):

It has come to our attention that CMEC has not delivered the complete versions of CR-P product
i.e., ABB interface relay, as per approved product order code. The relay and socket are only
provided, whereas function module and holder are missing from the packing. CMEC has been
advised to rectify the issue as function module is necessary to avoid reverse polarity of power
supply to the relay.

Interface relay
delivered at site,
relay and socket
only.

Interface relay to be
provided as per
approved Order code

Function module and Holder is missing


Consultant and CMEC representative were present to witness the progress of subject work dated
M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB
Dec 21, 2023. CMEC’s inadequate manpower was observed resulting in slower progress. Below is a
summary of RTU site activities from Dec 18 - 25, 2023:

- Cable laying at 220kV side has been completed i.e. from marshalling kiosk to marshalling box
and from marshalling box to RTU panel.
 The cables laying for D03Q1, D03Q2, D03Q3, D03Q10, and D03E10 was completed.
 The cables laying for D04Q1, D04Q2, D04Q3, D04Q10, D04E10 and D04Q20 was
completed.
 The cables laying for D05Q1, D05Q2, D05Q3, D05Q10, D05E10 and D05Q20 was
completed.
- Cable termination in 220kV marshalling box is in progress whereas, for 132kV cable
termination has been completed.
- Cable termination is also started in RTU panel.

220k
132kV Marshalling Box Cable termination V Marshalling Box Cable laying and terminations

Cable termination in RTU panel Cable in RTU panel

Below mentioned works are percentage progress of the works related to the LDS-II missing RTU signals.
M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB

220kV Substation Bund Road (SR-027)

Cable Termination BOQ Items Installation


Cable Continuity
Date Local
Laying Marshalling RTU Check TAP Intermediate Marshalling
Remote
Box Panel Transducer Relay Box
Switch
Dec 18, 2023 ≈ 10% - - - - - - -

Dec 19, 2023 ≈ 10% - - - - - - -

Dec 20, 2023 ≈ 20% - - - - - - -

Dec 21, 2023 ≈ 20% ≈ 20% - - - - - -

Dec 22, 2023 ≈ 14% ≈ 50% ≈ 5% - - - ≈ 5% -

Dec 23, 2023 ≈ 0% 0% 0% - - - - -

Dec 24, 2023 ≈ 0% 0% 0% - - - - -


Previous
≈ 26% 0% 0% 0% 0% 0% 0% 100%
Progress

Total ≈ 100% ≈ 70% ≈ 5% 0% 0% 0% ≈ 5% 100%

Sincerely,

Gibran Malik

LDPIII Consultant – Testing & Commissioning Manager

Ph: +61 407281998, 03062165858