Professional Documents
Culture Documents
Dear Sir,
Please find the site issues and observations as stated below.
It has come to our attention that CMEC has not delivered the complete versions of CR-P product
i.e., ABB interface relay, as per approved product order code. The relay and socket are only
provided, whereas function module and holder are missing from the packing. CMEC has been
advised to rectify the issue as function module is necessary to avoid reverse polarity of power
supply to the relay.
Interface relay
delivered at site,
relay and socket
only.
Interface relay to be
provided as per
approved Order code
- Cable laying at 220kV side has been completed i.e. from marshalling kiosk to marshalling box
and from marshalling box to RTU panel.
The cables laying for D03Q1, D03Q2, D03Q3, D03Q10, and D03E10 was completed.
The cables laying for D04Q1, D04Q2, D04Q3, D04Q10, D04E10 and D04Q20 was
completed.
The cables laying for D05Q1, D05Q2, D05Q3, D05Q10, D05E10 and D05Q20 was
completed.
- Cable termination in 220kV marshalling box is in progress whereas, for 132kV cable
termination has been completed.
- Cable termination is also started in RTU panel.
220k
132kV Marshalling Box Cable termination V Marshalling Box Cable laying and terminations
Below mentioned works are percentage progress of the works related to the LDS-II missing RTU signals.
M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB
Sincerely,
Gibran Malik