500kV TRANSMISSION LINES INTERCONNECTION ARRANGEMENT FOR POWER EVACUATION FROM SUKI KINARI, KOHALA AND MAHL HYDROPOWER PROJECTS IN NORTHERN AREAS OF PAKISTAN

ASSIGNMENT – A : ENGINEERING DESIGN AND TENDERING

Suki Kinari to Maira 500kV DC T/L (approx. 170km)

ASSIGNMENT – B : (DESIGN REVIEW, CONSTRUCTION SUPERVISION AND CONTRACT MANAGEMENT + DLP)
PRIORITY SECTION: Suki Kinari to In/Out Neelum Jhelum (70km)
WBS ID Task Name Baseline Dur. Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half
Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4
1 500kV Transmission Lines for Suki Kinari,  1229 days Oct 29 '18 Sep 30 '22

Kohala & Mahl HPPs
1.A Line Segment (Suki Kinari ‐ Maira) 272 days Oct 29 '18 Sep 10 '19
1.A.1 Commencement of Services 0 days Oct 29 '18 Oct 29 '18 Oct 29 '18
1.A.1.1 Commencement of Services 0 days Oct 29 '18 Oct 29 '18 Oct 29 '18
1.A.2 Review of existing information and data  26 days Nov 1 '18 Nov 30 '18
1.A.2.1 Review of existing information and data  26 days Nov 1 '18 Nov 30 '18 Nov 1 '18 Nov 30 '18
1.A.3 Transmission Line route alignment and  116 days Nov 1 '18 Mar 15 '19
detailed survey
1.A.3.1 Transmission Line route alignment and  116 days Nov 1 '18 Mar 15 '19 Nov 1 '18 Mar 15 '19
detailed survey
1.A.4 Geotechnical, geohazard and soil resistivity  72 days Jan 22 '19 Apr 15 '19
investigations
1.A.4.1 Geotechnical and geohazard  72 days Jan 22 '19 Apr 15 '19 Jan 22 '19 Apr 15 '19
1.A.4.2 Soil resistivity investigations 58 days Jan 22 '19 Mar 29 '19 Jan 22 '19 Mar 29 '19
1.A.5 Transmission Line Plan and Profile and  25 days Feb 15 '19 Mar 15 '19
Structure List
1.A.5.1 Transmission Line Plan and Profile and  25 days Feb 15 '19 Mar 15 '19 Feb 15 '19 Mar 15 '19
Structure List
1.A.6 Conductor and Span Utilization 50 days Nov 1 '18 Dec 28 '18
1.A.6.1 Conductor and Span Utilization 50 days Nov 1 '18 Dec 28 '18 Nov 1 '18 Dec 28 '18
1.A.7 Preparation of Engineering Design 145 days Oct 29 '18 Apr 15 '19
1.A.7.1 Collection of Data and Investigations 132 days Oct 29 '18 Mar 30 '19 Oct 29 '18 Mar 30 '19
1.A.7.2 Insulation Coordination Study 102 days Dec 3 '18 Mar 30 '19 Dec 3 '18 Mar 30 '19
1.A.7.3 Design of Hardware and Damping System 102 days Dec 3 '18 Mar 30 '19 Dec 3 '18 Mar 30 '19
1.A.7.4 Design of Tower Family and Foundations 102 days Dec 3 '18 Mar 30 '19 Dec 3 '18 Mar 30 '19
1.A.7.5 Preparation of Project Specifications 102 days Dec 3 '18 Mar 30 '19 Dec 3 '18 Mar 30 '19
1.A.7.6 Preparation of BoQ and Costing 29 days Mar 13 '19 Apr 15 '19 Mar 13 '19 Apr 15 '19
1.A.8 Preparation of Tender Documents 90 days Jan 1 '19 Apr 15 '19
1.A.8.1 Preparation of Tender Documents 90 days Jan 1 '19 Apr 15 '19 Jan 1 '19 Apr 15 '19
1.A.9 Tendering (Bidding Period) 60 days Apr 16 '19 Jun 14 '19
1.A.9.1 Tendering (Bidding Period) 60 days Apr 16 '19 Jun 14 '19 Apr 16 '19 Jun 14 '19
1.A.10 Evaluation and Award of Contract(s) 75 days Jun 15 '19 Sep 10 '19
1.A.10.2 Evaluation 60 days Jun 15 '19 Aug 23 '19 Jun 15 '19 Aug 23 '19
1.A.10.1 Award of Contract(s) 15 days Aug 24 '19 Sep 10 '19 Aug 24 '19 Sep 10 '19
1.B Assignment‐B : Priority Line Segment (Suki Kinari  644 days Sep 11 '19 Sep 30 '21
to NJ Interconnection)
1.B.1 Mobilization  15 days Sep 11 '19 Sep 27 '19
1.B.1.1 Mobilization of Contractor 15 days Sep 11 '19 Sep 27 '19 Sep 11 '19 Sep 27 '19
1.B.2 Design Review of Plant Data and Drawings 279 days Sep 28 '19 Aug 18 '20
1.B.2.1 Design Review of Plant Data and Drawings 279 days Sep 28 '19 Aug 18 '20 Sep 28 '19 Aug 18 '20
1.B.3 Tower Fabrication Drawings and Prototype  223 days Nov 15 '19 Jul 31 '20
Load Testing
1.B.3.1 Tower Fabrication Drawings and Prototype  223 days Nov 15 '19 Jul 31 '20 Nov 15 '19 Jul 31 '20
Load Testing
1.B.4 Procurement and Shipment of Plant and  326 days Dec 2 '19 Dec 15 '20
Equipment
1.B.4.1 Procurement and Shipment of Plant and  326 days Dec 2 '19 Dec 15 '20 Dec 2 '19 Dec 15 '20
Equipment
1.B.5 Construction of Transmission Line (approx.  495 days Feb 1 '20 Aug 31 '21
70km; approx. 210 Towers)
1.B.5.1 Foundations 390 days Feb 1 '20 Apr 30 '21 Feb 1 '20 Apr 30 '21

Page 1 of 1 
NESPAK Revision No.: 00
National Engineering Services of Pakistan Dated: Jan 21 '19
500kV TRANSMISSION LINES INTERCONNECTION ARRANGEMENT FOR POWER EVACUATION FROM SUKI KINARI, KOHALA AND MAHL HYDROPOWER PROJECTS IN NORTHERN AREAS OF PAKISTAN
ASSIGNMENT – A : ENGINEERING DESIGN AND TENDERING

Suki Kinari to Maira 500kV DC T/L (approx. 170km)

ASSIGNMENT – B : (DESIGN REVIEW, CONSTRUCTION SUPERVISION AND CONTRACT MANAGEMENT + DLP)
PRIORITY SECTION: Suki Kinari to In/Out Neelum Jhelum (70km)
WBS ID Task Name Baseline Dur. Start Finish 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half
Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4
1.B.5.2 Tower Erection 313 days Jul 1 '20 Jun 30 '21 Jul 1 '20 Jun 30 '21
1.B.5.3 Stringing 235 days Dec 1 '20 Aug 31 '21 Dec 1 '20 Aug 31 '21
1.B.6 Testing and Commissioning 27 days Aug 31 '21 Sep 30 '21
1.B.6.1 Testing and Commissioning 27 days Aug 31 '21 Sep 30 '21 Aug 31 '21 Sep 30 '21
1.C Defect Liability Period 365 days Oct 1 '21 Sep 30 '22

Page 2 of 2 
NESPAK Revision No.: 00
National Engineering Services of Pakistan Dated: Jan 21 '19