500KV TRANSMISSION LINES INTERCONNECTION ARRANGEMENT FOR POWER EVACUATION FROM SUKI KINARI, KOHALA AND MAHL HYDROPOWER PROJECTS IN 

NORTHERN AREAS OF PAKISTAN 
ASSIGNMENT – B : (DESIGN REVIEW, CONSTRUCTION SUPERVISION AND CONTRACT MANAGEMENT)

LOT-II: NJ Interconnection Point to 500kV Maira Switching Station (approx. 85km)

WBD Task Name Duration Start Finish 2019 2020 2021 2022


ID Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul
1 Priority Line Segment : LOT ‐ II (NJ Interconnection to MAIRA) 749 days Sep 11 '19 Jan 31 '22

1.1 Mobilization  15 days Sep 11 '19 Sep 27 '19


1.1.1 Mobilization of Contractor 15 days Sep 11 '19 Sep 27 '19 Sep 11 '19 Sep 27 '19
1.2 Design Review of Plant Data and Drawings 279 days Sep 28 '19 Aug 18 '20
1.2.1 Design Review of Plant Data and Drawings 279 days Sep 28 '19 Aug 18 '20 Sep 28 '19 Aug 18 '20
1.3 Tower Fabrication Drawings and Prototype Load Testing 223 days Nov 15 '19 Jul 31 '20
1.3.1 Tower Fabrication Drawings and Prototype Load Testing 223 days Nov 15 '19 Jul 31 '20 Nov 15 '19 Jul 31 '20
1.4 Procurement and Shipment of Material / Plant  326 days Dec 2 '19 Dec 15 '20
1.4.1 Procurement and Shipment of Material / Plant  326 days Dec 2 '19 Dec 15 '20 Dec 2 '19 Dec 15 '20
1.5 Construction of Transmission Line (~85km) 600 days Feb 1 '20 Dec 31 '21
1.5.1 Foundations 469 days Feb 1 '20 Jul 31 '21 Feb 1 '20 Jul 31 '21
1.5.2 Tower Erection 418 days Jul 1 '20 Oct 30 '21 Jul 1 '20 Oct 30 '21
1.5.3 Stringing 340 days Dec 1 '20 Dec 31 '21 Dec 1 '20 Dec 31 '21
1.6 Testing and Commissioning 132 days Aug 31 '21 Jan 31 '22
1.6.1 Testing and Commissioning 132 days Aug 31 '21 Jan 31 '22 Aug 31 '21 Jan 31 '22

Page 1 of 1  Annexure‐3
NESPAK Revision No.: 00
National Engineering Services of Pakistan Dated: Jan 18, 2019