STRUCTURAL DESIGN CALCULATIONS OF 33KV DOUBLE CIRCUIT

GANTRY (Area of Conductor =265Sq.mm)

REPORT PREPARED FOR:

ELECTRICITY COMPANY OF GHANA LIMITED

REPORT PREPARED BY:

ARVENSIS ENERGY PRIVATE LIMMITED


FOR
DELOVELY COMPANY LIMITED

CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REV 01
REGION.

1
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REV 01
REGION.

Table of Contents

1. DESIGN PARAMETERS ......................................................................................................... 3

2. INDEX OF LOADINGS............................................................................................................ 5

3. SAG TENSION CALCULATIONS .......................................................................................... 7

4. LOAD CALCULATIONS ....................................................................................................... 10

5. WIND LOAD ON GANTRY STRUCTURE .......................................................................... 17

6. DESIGN CALCULATIONS ................................................................................................... 22

7. FOUNDATION FORCES: ...................................................................................................... 25

8. SINGLE LINE DRAWING ..................................................................................................... 27

2
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REV 01
REGION.

1. DESIGN PARAMETERS
1.GENERAL

1. VOLTAGE/CIRCUIT 33KV (DOUBLE CIRCUIT)


2. TOWER CONFIGURATION HORIZONTAL
3.NO. OF EARTHWIRE ONE (OPGW)
4.NO. OF CONDUCTORS ONE PER PHASE

2) SPAN DETAILS (in meters)

NORMAL SPAN: 170m


WIND SPAN:
NC: 204m
BWC: 122m

WEIGHT SPAN:
MAX. WT. SPAN MIN. WT. OF SPAN
TOWER TYPE DE/DE90 DE/DE90
NC Max/ Min 290 0
BWC Max/Min 174 0

3) CONDUCTOR AND GROUNDWIRE PROPERTIES

CONDUCTOR
OVERALL DIAMETER - 21.1mm
CROSS SECTION AREA - 265 Sq.mm
WEIGHT - 0.731Kg/m
ULTIMATE TENSILE STRENGTH – 4119Kgs
MODULUS OF ELASTICITY - 6966Kg/Sq.mm
CO-EFFCIENT OF LINEAR EXPANSION - 23X10^-6 /  C

GROUNDWIRE (OPGW)
OVERALL DIAMETER - 16 mm
CROSS SECTION AREA - 58 Sq.mm
WEIGHT - 0.492 Kg/m
ULTIMATE TENSILE STRENGHT - 7322 Kgs
MODULUS OF ELASTICITY - 1211423 Kg/Sq.mm
CO-EFFCIENT OF LINEAR EXPANSION - 14.1X10^-6 /  C

3
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REV 01
REGION.

5) ELECTRICAL CLEARENCE:

MIN GROUND CLEARENCE 6000mm


HORIZONTAL CLEARENCE 2000mm

6) TOWER DESIGN DETAILS:

Leg Lattice X – Arm Redundant Ten. Memb


Main
Min. Thickness (mm) 5 4 5 4 5
KL/R 150 200 150 250 350

Steel Grade
Grade Yield (MPa)
Mid Steel BSEN 10025 S275 275
High Tensile BSEN 10025 S355 355

Bolts & Nuts


Dia Grade
16 5.8

7) WIND LOAD DETAILS

Wind Pressure = 680 N/sq.m

4
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT
NAME CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM KPANDO TO HOHOE AND REV 01
KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REGION.

2. INDEX OF LOADINGS

_________________________________________________________________________________________________________
Sl. Title Code Nature Category
_________________________________________________________________________________________________________
1 RELIABILITY NORMAL RN perm cate
2 SECURITY OPGW & TOP COND BROKEN SGB perm catb
3 SECURITY TOP & MIDD CONDUCTOR BROKEN STMB perm catb
4 SECURITY MIDDLE & BOTT CONDUCTOR BROKEN SMBB perm catb
5 SECURITY BOTTOM & TOP CONDUCTOR BROKEN SBTB perm catb
6 SAFETY NORMAL CONDITION SAN perm catn
7 DEAD END DE perm cate

5
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT
NAME CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM KPANDO TO HOHOE AND REV 01
KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REGION.

SAG TENSION CALCULATIONS

6
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT
NAME CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM KPANDO TO HOHOE AND REV 01
KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REGION.

3. SAG TENSION CALCULATIONS

DATA :-

Basic Span (m) : 170.00


Wind Pressure (kg/sq.m) : 69.34

CONDUCTOR DETAILS :-

Type : 265 sq.mm


Overall Diameter (cm) : 2.6
Cross Sectional Area (sq.cm) : 4
Unit Weight (kg/m) : 1.102
Ultimate Tensile strength (kg) : 6526
Coef. of Thermal Expansion(/degC) : 0.000023
Modulus of Elasticity (kg/sq.cm) : 560844
Increase in Vertical sag (%) : 0
Shape factor : 1
Gust factor : 1
Drag factor : 1

Basic Condition:-
Temperature (deg C) : 27.0000
Wind factor : .0000
Ice thickness (cm) : .0000
Factor of Safety : 5.000

SAG_TENSION_FOS COMPUTATIONS :
________________________________________________________________________________________________________________

Sl. Environmental Wind Ice Vertical Tension FOS REMARKS


No. Temperature (deg.C) Factor Thickness (cm) Sag (m) (Kg)
________________________________________________________________________________________________________________

1. 27.00 .0000 .00 3.050 1305.20 5.000


2. 27.00 1.0000 .00 1.892 2103.98 3.102
3. 85.00 .0000 .00 4.647 856.70 7.618
4. 40.00 1.0000 .00 2.059 1933.81 3.375
5. 10.00 1.0000 .00 1.671 2382.10 2.740
________________________________________________________________________________________________________________

Max Vertical Sag (m) : 4.647


Max Tension (kg) : 2382.10

7
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT
NAME CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM KPANDO TO HOHOE AND REV 01
KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REGION.

DATA :-

Basic Span (m) : 170.00


Wind Pressure (kg/sq.m) : 69.34

SHIELD WIRE DETAILS :-

Type : OPGW
Overall Diameter (cm) : 1.6
Cross Sectional Area (sq.cm) : 1.27
Unit Weight (kg/m) : 0.615
Ultimate Tensile strength (kg) : 7036
Coef. of Thermal Expansion(/degC) : 0.0000185
Modulus of Elasticity (kg/sq.cm) : 958533
Increase in Vertical sag (%) : 0
Shape factor : 1
Gust factor : 1
Drag factor : 1

Basic Condition:-
Temperature (deg C) : 27.0000
Wind factor : .0000
Ice thickness (cm) : .0000
Factor of Safety : 8.6936

SAG_TENSION_FOS COMPUTATIONS :
________________________________________________________________________________________________________________

Sl. Environmental Wind Ice Vertical Tension FOS REMARKS


No. Temperature (deg.C) Factor Thickness (cm) Sag (m) (Kg)
________________________________________________________________________________________________________________

1. 27.00 .0000 .00 2.745 809.33 8.694 % GW/CON sag = 90.00


2. 27.00 1.0000 .00 1.685 1318.89 5.335 % GW/CON sag = 89.03
3. 53.00 .0000 .00 3.377 657.98 10.693 % GW/CON sag = 72.66
4. 40.00 1.0000 .00 1.807 1229.77 5.721 % GW/CON sag = 87.76
5. 10.00 1.0000 .00 1.525 1456.95 4.829 % GW/CON sag = 91.24
________________________________________________________________________________________________________________

Max Vertical Sag (m) : 3.377


Max Tension (kg) : 1456.95

8
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

CONDUCTOR AND GROUND WIRE LOAD CALCULATIONS

9
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

4. LOAD CALCULATIONS
DESIGN DATA
DESCRIPTION UNITS NC BWC ERECTION

SPANS :

WIND SPAN, Lwind m 204 122 122


WEIGHT SPAN ( MAX ), Lw1 m 290 174 174
WEIGHT SPAN ( MIN ), Lw2 m 0 0 0
WIND PRESSURES :

WIND PRESSURE ON CONDUCTOR, Pc Kg/m^2 70.8 28.3 17.7


WIND PRESSURE ON OPGW, Po Kg/m^2 70.8 28.3 17.7
WIND PRESSURE ON INSULATOR, Pi Kg/m^2 70.8 28.3 17.7

COND.,EW & INSULATORS :

DIA.OF.CONDUCTOR, Dc m 0.026 0.026 0.026


DIA.OF.OPGW, Do m 0.0155 0.0155 0.0155
DIA.OF.INSULATOR, Di m 0.25 0.25 0.25
LENGTH OF INSULATOR, Li m 0.99 0.99 0.99
NO OF SUB CONDUCTORS, Nc 1 1 1
NO OF INSULATOR SETS, Ni 1 1 1
WEIGHT OF CONDUCTOR, Wc Kg/m 1.16 1.16 1.16
WEIGHT OF INSULATOR PER SET, Wi Kg 81.58 81.58 81.58
WEIGHT OF OPGW, Wo Kg/m 0.887 0.887 0.887

TENSION OF WIRES :

TENSION OF CONDUCTOR, Tc Kg 470.8 298.6 276.6


TENSION OF OPGW, To Kg 438.25 313.75 300.5
TENSION DIFFERENCE OF CONDUCTOR, Tcd Kg 0 0 0
TENSION DIFFERENCE OF OPGW, Tod Kg 0 0 0

DEVIATION ANGLE - MAX. , Amax DEG 90 90 90


DEVIATION ANGLE - MIN., Amin DEG 60 60 60
LONG FACTOR FOR CONDUCTOR, Lf NIL 1 1 1
FACTOR OF SAFETY NIL 1 1 1

10
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

NORMAL CONDITION (WITH MAXIMUM WIND)

TRANSVERSE LOADS :

CONDUCTOR:-
WIND ON CONDUCTOR = 1 x 70.77 x 0.0260 x 204 = 376 =Nc*Pc* Dc*Lwind
WIND ON INSULATOR = = 61 =61
DUE TO ANGLE OF DEVIATION = 2 x 0.707 x 470.8 x 1 = 666 =2*Nc*sin(Amax/2)* Tc
TOTAL TRANSVERSE LOAD = = 1104 Kg

EARTH WIRE:-
WIND ON EARTH WIRE = 1 x 70.77 x 0.0155 x 204 = 224 =1*Po*Do*Lwind
DUE TO ANGLE OF DEVIATION = 2 x 0.707 x 438.25 x 1 = 620 =2*sin(Amax/2)*To
TOTAL TRANSVERSE LOAD = 844 Kg

VERTICAL LOADS :

CONDUCTOR:- MAX MIN


WEIGHT OF CONDUCTOR = 1 x 290 x 1.16 = 337 0 =Nc*Lw1*Wc
WEIGHT OF INSULATOR = 1 x 81.58 = 82 82 =Ni*Wi
WEIGHT OF LIGHTENING
ARRESTOR = 31 31
WEIGHT OF ISOLATOR = 102 102
WEIGHT OF THREE PHASE
SEALING = 102 102
WEIGHT OF LINE TRAP = 0 0
OTHER LOADS = 0 0
TOTAL VERTICAL LOAD = 654 317

EARTH WIRE:- MAX MIN


WEIGHT OF EARTH WIRE = 1 x 290 x 0.887 = 258 0 =1*Lw1*Wo
TOTAL VERTICAL LOAD = = 258 0

LONGITUDINAL LOADS :-

CONDUCTOR:-
LONGITUDINAL LOAD OF =Nc*Tcd*Lf
CONDUCTOR = 1 x 0 x 1 = 0 Kg

EARTH WIRE:-
LONGITUDINAL LOAD OF =Ni*Tod*Lf
EARTH WIRE = 1 x 0 = 0 Kg

Note: FOS for this load case is 2.0

11
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

SECURITY NORMAL CONDITION

TRANSVERSE LOADS :

CONDUCTOR:-
WIND ON CONDUCTOR = 1 x 28.31 x 0.0260 x 204 = 151 =Nc*Pc* Dc*Lwind
WIND ON INSULATOR = = 61 =61
DUE TO ANGLE OF DEVIATION = 2 x 0.707 x 298.6 x 1 = 423 =2*Nc*sin(Amax/2)* Tc
TOTAL TRANSVERSE LOAD = = 636 Kg

EARTH WIRE:-
WIND ON EARTH WIRE = 1 x 28.31 x 0.0155 x 204 = 90 =1*Po*Do*Lwind
DUE TO ANGLE OF DEVIATION = 2 x 0.707 x 313.75 x 1 = 444 =2*sin(Amax/2)*To
TOTAL TRANSVERSE LOAD = 534 Kg

VERTICAL LOADS :

CONDUCTOR:- MAX MIN


WEIGHT OF CONDUCTOR = 1 x 290 x 1.16 = 337 0 =Nc*Lw1*Wc
WEIGHT OF INSULATOR = 1 x 81.58 = 82 82 =Ni*Wi
WEIGHT OF LIGHTENING ARRESTOR = 31 31
WEIGHT OF ISOLATOR = 102 102
WEIGHT OF THREE PHASE SEALING = 102 102
WEIGHT OF LINE TRAP = 0 255
OTHER LOADS = 0 255
TOTAL VERTICAL LOAD = = 654 827

EARTH WIRE:- MAX MIN


WEIGHT OF EARTH WIRE = 1 x 290 x 0.887 = 258 0
TOTAL VERTICAL LOAD = = 258 0

LONGITUDINAL LOADS :-

CONDUCTOR:-
LONGITUDINAL LOAD OF
CONDUCTOR = 1 x 0 x 0.866 = 0 Kg

EARTH WIRE:-

LONGITUDINAL LOAD OF EARTH


WIRE = 1 x 0 x 0.866 = 0 Kg

12
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

SECURITY BROKEN WIRE CONDITION

TRANSVERSE LOADS :

CONDUCTOR:-
WIND ON CONDUCTOR = 1 x 28.31 x 0.0260 x 122 = 91 =Nc*Pc* Dc*Lwind
WIND ON INSULATOR = = 61 =61
DUE TO ANGLE OF DEVIATION = 2 x 0.707 x 298.6 x 0.5 = 212 =2*Nc*sin(Amax/2)* Tc
TOTAL TRANSVERSE LOAD = = 365 Kg

EARTH WIRE:-
WIND ON EARTH WIRE = 1 x 28.31 x 0.0155 x 122.4 = 54 =1*Po*Do*Lwind
DUE TO ANGLE OF DEVIATION = 2 x 0.707 x 313.75 x 0.5 = 222 =2*sin(Amax/2)*To
TOTAL TRANSVERSE LOAD = 276 Kg

VERTICAL LOADS :

CONDUCTOR:- MAX MIN


WEIGHT OF CONDUCTOR = 1 x 174 x 1.16 = 202 0 =Nc*Lw1*Wc
WEIGHT OF INSULATOR = 1 x 81.58 = 82 82 =Ni*Wi
WEIGHT OF LIGHTENING
ARRESTOR = 31 31
WEIGHT OF ISOLATOR = 102 102
WEIGHT OF THREE PHASE
SEALING = 102 102
WEIGHT OF LINE TRAP = 0 255
OTHER LOADS = 0 255
TOTAL VERTICAL LOAD = = 519 827

EARTH WIRE:- MAX MIN


WEIGHT OF EARTH WIRE = 1 x 174 x 0.887 = 155 0 =1*Lw1*Wo
TOTAL VERTICAL LOAD = = 155 0

LONGITUDINAL LOADS :-

CONDUCTOR:-
LONGITUDINAL LOAD OF =Nc*Tcd*Cos(Amin/2)*Lf
CONDUCTOR = 1 x 298.6 x 0.866 x 1 = 259 Kg

EARTH WIRE:-
LONGITUDINAL LOAD OF EARTH =1*Tod*Cos(Amin/2)*Lf
WIRE = 1 x 313.8 x 0.866 x 1 = 272 Kg

Note: FOS for this load case is 1.5

13
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

ERECTION & MAINTENANCE LOADS

TRANSVERSE LOADS :

CONDUCTOR:-
WIND ON CONDUCTOR = 1 x 28.31 x 0.0260 x 122 = 91 =Nc*Pc* Dc*Lwind
WIND ON INSULATOR = = 61
=2*Nc*sin(Amax/2)*
DUE TO ANGLE OF DEVIATION = 2 x 0.707 x 276.6 x 1 = 392 Tc
TOTAL TRANSVERSE LOAD = = 545 Kg

EARTH WIRE:-
WIND ON EARTH WIRE = 1 x 28.31 x 0.0155 x 122 = 54 =1*Po*Do*Lwind
DUE TO ANGLE OF DEVIATION = 2 x 0.707 x 300.5 x 1 = 425 =2*sin(Amax/2)*To
TOTAL TRANSVERSE LOAD = 479 Kg

VERTICAL LOADS :

CONDUCTOR:- MAX
WEIGHT OF CONDUCTOR = 1 x 290 x 1.16 x 2 = 673 =Nc*Lwind*Wc*2
WEIGHT OF INSULATOR = 1 x 81.58 x 2 = 164 =Ni*Wi*2
= 357
ERECTION LOADS = 153
WEIGHT OF LIGHTENING
ARRESTOR = 31
WEIGHT OF ISOLATOR = 102
WEIGHT OF THREE PHASE SEALING = 102
WEIGHT OF LINE TRAP = 0
OTHER LOADS = 0
TOTAL VERTICAL LOAD = = 1581

EARTH WIRE:- MAX


WEIGHT OF EARTH WIRE = 1 x 290 x 0.887 x 2 = 515 =1*Lw1*Wo
TOTAL VERTICAL LOAD = = 515

LONGITUDINAL LOADS :-
CONDUCTOR:-
LONGITUDINAL LOAD OF
CONDUCTOR = = 0 Kg

EARTH WIRE:-
LONGITUDINAL LOAD OF EARTH
WIRE = = 0 Kg
Note: FOS for this load case is 2.0

14
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

DEAD END CONDITION

TRANSVERSE LOADS :

CONDUCTOR:-
WIND ON CONDUCTOR = 1 x 28.31 x 0.0260 x 122 = 91 =Nc*Pc* Dc*Lwind
WIND ON INSULATOR = = 61 =61
DUE TO ANGLE OF
DEVIATION = 1 x 0 x 1493 x 1 = 0 =2*Nc*sin(Amax/2)* Tc
TOTAL TRANSVERSE LOAD = = 153 Kg

EARTH WIRE:-
WIND ON EARTH WIRE = 1 x 28.31 x 0.0155 x 122.4 = 54
DUE TO ANGLE OF
DEVIATION = 1 x 0 x 1255 x 1 = 0 =1*Po*Do*Lwind
TOTAL TRANSVERSE LOAD = 54 Kg =2*sin(Amax/2)*To

VERTICAL LOADS :

CONDUCTOR:- MAX MIN


WEIGHT OF CONDUCTOR = 1 x 174 x 1.16 = 202 0 =Nc*Lw1*Wc
WEIGHT OF INSULATOR = 1 x 81.58 = 82 82 =Ni*Wi
WEIGHT OF LIGHTENING
ARRESTOR = 31 31
WEIGHT OF ISOLATOR = 102 102
WEIGHT OF THREE PHASE
SEALING = 102 102
WEIGHT OF LINE TRAP = 255 255
OTHER LOADS = 255 255
TOTAL VERTICAL LOAD = = 1029 827

EARTH WIRE:- MAX MIN


WEIGHT OF EARTH WIRE = 1 x 174 x 0.887 = 155 0 =1*Lw1*Wo
TOTAL VERTICAL LOAD = = 155 0

LONGITUDINAL LOADS :-

CONDUCTOR:-
LONGITUDINAL LOAD OF =Nc*Tcd*Cos(Amin/2)*Lf
CONDUCTOR = 1 x 2354 x 1 x 1 = 2354 Kg

EARTH WIRE:-
LONGITUDINAL LOAD OF =1*Tod*Cos(Amin/2)*Lf
EARTH WIRE = 1 x 1753 x 1 x 1 = 1753 Kg

Note: FOS for this load case is 2.0

15
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

WIND ON GANTRY BODY

16
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

5. WIND LOAD ON GANTRY STRUCTURE


BASIC BODY
Point Loads for Load Case "RN : NORMAL CONDITION MAX WIND":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 12827 21653 0
T2XY 12827 21653 0
T3XY 12827 21653 0
T1X 12827 21653 0
T2X 12827 21653 0
T3X 12827 21653 0

Section Load Case Information (Standard) for "RN : NORMAL CONDITION MAX WIND":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
----------------------------------------------------------------------------------------
3 10.50 7.95 9.22 1388.00 1388.00 1.000 6232.2 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 1388.00 1388.00 1.000 4780.7 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 1388.00 1388.00 1.000 3920.5 0.00 1.000 0.0 0 6149

Point Loads for Load Case "ERR - ERECTION & MAINTENANCE LOADING":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 5000 12592 0
T2XY 5000 12592 0
T3XY 5000 12592 0
T1X 5000 12592 0
T2X 5000 12592 0
T3X 5000 12592 0

Section Load Case Information (Standard) for "ERR - ERECTION & MAINTENANCE LOADING":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------
3 10.50 7.95 9.22 416.40 416.40 1.000 1869.7 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 416.40 416.40 1.000 1434.2 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 416.40 416.40 1.000 1176.1 0.00 1.000 0.0 0 6149

Point Loads for Load Case "RND - NORMAL CONDITION FOR DEFLECTION":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 11415 12464.5 0
T2XY 11415 12464.5 0
T3XY 11415 12464.5 0
T1X 11415 12464.5 0
T2X 11415 12464.5 0
T3X 11415 12464.5 0

Section Load Case Information (Standard) for "RND - NORMAL CONDITION FOR DEFLECTION":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------

17
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

3 10.50 7.95 9.22 694.00 694.00 1.000 3116.1 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 694.00 694.00 1.000 2390.3 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 694.00 694.00 1.000 1960.2 0.00 1.000 0.0 0 6149

Point Loads for Load Case "SB1 - SECURITY BROKEN WIRE CONDITION - 1ST CONDUCTOR":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 15137 6134 4766
T2XY 17122 10900 0
T3XY 17122 10900 0
T1X 17122 10900 0
T2X 17122 10900 0
T3X 17122 10900 0

Section Load Case Information (Standard) for "SB1 - SECURITY BROKEN WIRE CONDITION - 1ST CONDUCTOR":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------
3 10.50 7.95 9.22 416.40 416.40 1.000 1869.7 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 416.40 416.40 1.000 1434.2 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 416.40 416.40 1.000 1176.1 0.00 1.000 0.0 0 6149

Point Loads for Load Case "SB2 - SECURITY BROKEN WIRE CONDITION - 2ND CONDUCTOR":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 17122 10900 0
T2XY 15137 6134 4766
T3XY 17122 10900 0
T1X 17122 10900 0
T2X 17122 10900 0
T3X 17122 10900 0

Section Load Case Information (Standard) for "SB2 - SECURITY BROKEN WIRE CONDITION - 2ND CONDUCTOR":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------
3 10.50 7.95 9.22 416.40 416.40 1.000 1869.7 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 416.40 416.40 1.000 1434.2 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 416.40 416.40 1.000 1176.1 0.00 1.000 0.0 0 6149

Point Loads for Load Case "SB3 - SECURITY BROKEN WIRE CONDITION - 3RD CONDUCTOR":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 17122 10900 0
T2XY 17122 10900 0
T3XY 15137 6134 4766
T1X 17122 10900 0
T2X 17122 10900 0
T3X 17122 10900 0

Section Load Case Information (Standard) for "SB3 - SECURITY BROKEN WIRE CONDITION - 3RD CONDUCTOR":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------
3 10.50 7.95 9.22 416.40 416.40 1.000 1869.7 0.00 1.000 0.0 0 10319

18
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

2 7.95 3.50 5.72 416.40 416.40 1.000 1434.2 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 416.40 416.40 1.000 1176.1 0.00 1.000 0.0 0 6149

Point Loads for Load Case "SB4 - SECURITY BROKEN WIRE CONDITION - 4TH CONDUCTOR":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 17122 10900 0
T2XY 17122 10900 0
T3XY 17122 10900 0
T1X 15137 6134 4766
T2X 17122 10900 0
T3X 17122 10900 0

Section Load Case Information (Standard) for "SB4 - SECURITY BROKEN WIRE CONDITION - 4TH CONDUCTOR":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------
3 10.50 7.95 9.22 416.40 416.40 1.000 1869.7 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 416.40 416.40 1.000 1434.2 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 416.40 416.40 1.000 1176.1 0.00 1.000 0.0 0 6149

Point Loads for Load Case "SB5 - SECURITY BROKEN WIRE CONDITION - 5TH CONDUCTOR":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 17122 10900 0
T2XY 17122 10900 0
T3XY 17122 10900 0
T1X 17122 10900 0
T2X 15137 6134 4766
T3X 17122 10900 0

Section Load Case Information (Standard) for "SB5 - SECURITY BROKEN WIRE CONDITION - 5TH CONDUCTOR":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------
3 10.50 7.95 9.22 416.40 416.40 1.000 1869.7 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 416.40 416.40 1.000 1434.2 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 416.40 416.40 1.000 1176.1 0.00 1.000 0.0 0 6149

Point Loads for Load Case "SB6 - SECURITY BROKEN WIRE CONDITION - 6TH CONDUCTOR":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 17122 10900 0
T2XY 17122 10900 0
T3XY 17122 10900 0
T1X 17122 10900 0
T2X 17122 10900 0
T3X 15137 6134 4766

Section Load Case Information (Standard) for "SB6 - SECURITY BROKEN WIRE CONDITION - 6TH CONDUCTOR":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------
3 10.50 7.95 9.22 416.40 416.40 1.000 1869.7 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 416.40 416.40 1.000 1434.2 0.00 1.000 0.0 0 7380

19
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

1 3.50 0.00 1.75 416.40 416.40 1.000 1176.1 0.00 1.000 0.0 0 6149

Point Loads for Load Case "SECURITY BROKEN WIRE CONDITION ALL CONDUCTORS":

Joint Vertical Transverse Longitudinal Load


Label Load Load Load Comment
(N) (N) (N)
-----------------------------------------------
T1XY 15137 6134 4766
T2XY 15137 6134 4766
T3XY 15137 6134 4766
T1X 15137 6134 4766
T2X 15137 6134 4766
T3X 15137 6134 4766

Section Load Case Information (Standard) for "SECURITY BROKEN WIRE CONDITION ALL CONDUCTORS":

Section Z Z Ave. Res. Tran Tran Tran Long Long Long Ice Total
Label of of Elev. Adj. Adj. Drag Wind Adj. Drag Wind Weight Weight
Top Bottom Above Wind Wind Coef Load Wind Coef Load
Ground Pres. Pres. Pres.
(m) (m) (m) (Pa) (Pa) (N) (Pa) (N) (N) (N)
--------------------------------------------------------------------------------------
3 10.50 7.95 9.22 416.40 416.40 1.000 1869.7 0.00 1.000 0.0 0 10319
2 7.95 3.50 5.72 416.40 416.40 1.000 1434.2 0.00 1.000 0.0 0 7380
1 3.50 0.00 1.75 416.40 416.40 1.000 1176.1 0.00 1.000 0.0 0 6149

20
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT NAME CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM KPANDO TO HOHOE AND REV 01
KADJEBI TO HOHOE SUBSTATIONS IN THE VOLTA REGION.

DESIGN CALCULATIONS

21
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT
NAME CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM KPANDO TO HOHOE AND KADJEBI TO HOHOE REV 01
SUBSTATIONS IN THE VOLTA REGION.

6. DESIGN CALCULATIONS
Group Summary (Compression Portion):

Comp. Comp.
Max Comp.
Steel Max Usage Comp. Comp. L/r Connect. Connect. No. Of
Group Angle Angle Use In Control Curve
Row Strength Usage Cont- Control Force Capacity Shear Bearing RLX RLY RLZ L/r KL/r Bolts
Label Type Size Comp. Load No.
(MPa) % rol Member (kN) (kN) Capacity Capacity Comp.
% Case
(kN) (kN)
1 L1 SAE 90*90*6 355 84.96 Comp 84.96 g1Y -237.895 RN 280.024 314.1 361.267 2 1 1 36.17 36.17 1 4
2 L2 SAE 90*90*6 355 82.18 Comp 82.18 g2Y -193.59 RN 280.671 235.575 270.95 2 1 1 35.7 35.7 1 3
3 L3 SAE 60*60*5 355 1.16 Comp 1.16 g315P -1.279 SBWC 109.983 157.05 150.528 0.5 0.5 0.5 82.55 82.55 1 2
4 D1 SAE 45*45*5 275 58.1 Comp 58.1 g23R -22.813 RN 51.993 39.263 62.976 1 1 1 100.92 110.46 3 1
5 D2 SAE 45*45*5 275 87.35 Comp 87.35 g108P -34.298 RN 52.803 39.263 62.976 1 1 1 98.51 109.25 3 1
6 H1 SAE 80*80*6 275 75.81 Comp 75.81 FFg206X -89.299 RN 156.471 117.788 226.714 1 1 1 42.47 81.23 3 3
7 H2 SAE 45*45*5 275 29.09 Comp 29.09 g220P -11.422 RN 58.958 39.263 62.976 1 1 1 80.46 100.23 3 1
8 H3 SAE 45*45*5 275 5.96 Comp 5.96 g236X -2.342 RN 58.958 39.263 62.976 1 1 1 80.46 100.23 3 1
9 H4 SAE 45*45*5 275 84.76 Comp 84.76 g240P -33.28 RN 58.958 39.263 62.976 1 1 1 80.46 100.23 3 1
10 H5 SAE 45*45*5 275 73.03 Comp 73.03 g273P -35.58 SBWC 48.724 78.525 125.952 1 1 1 110.78 115.39 3 2
11 HR1 SAE 45*45*5 275 19.75 Comp 19.75 g308P -7.756 RN 47.742 39.263 62.976 1 1 1 113.79 116.89 3 1

22
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT
NAME CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM KPANDO TO HOHOE AND KADJEBI TO HOHOE REV 01
SUBSTATIONS IN THE VOLTA REGION.

Group Summary (Tension Portion):

Tension Tension
Tension Net Length
Steel Max Usage Max Tension Tension Connect. Connect. No. Of Hole
Group Angle Angle Control Section Tens. No. Of
Row Strength Usage Cont- Use In Control Force Shear Bearing Bolts Diameter
Label Type Size Load Capacity Member Holes
(MPa) % rol Tens. % Member (kN) Capacity Capacity Tens. (cm)
Case (kN) (m)
(kN) (kN)
1 L1 SAE 90*90*6 355 84.96 Comp 67.51 g1X 212.036 RN 335.475 314.1 361.267 0.501 4 1 1.75
2 L2 SAE 90*90*6 355 82.18 Comp 72 g2X 169.619 RN 335.475 235.575 270.95 0.494 3 1 1.75
3 L3 SAE 60*60*5 355 1.16 Comp 0.74 g315X 1.121 SBWC 179.156 157.05 150.528 1.915 2 1 1.75
4 D1 SAE 45*45*5 275 58.1 Comp 54.13 g23P 21.253 RN 78.528 39.263 62.976 0.878 1 1 1.75
5 D2 SAE 45*45*5 275 87.35 Comp 86.65 g109P 34.022 RN 78.528 39.263 62.976 0.857 1 1 1.75
6 H1 SAE 80*80*6 275 75.81 Comp 51.01 Fg206214P 60.086 RN 190.035 117.788 226.714 0.662 3 1 1.75
7 H2 SAE 45*45*5 275 29.09 Comp 15.55 g218P 6.104 RN 78.528 39.263 62.976 0.7 1 1 1.75
8 H3 SAE 45*45*5 275 5.96 Comp 5.57 g236P 2.188 RN 78.528 39.263 62.976 0.7 1 1 1.75
9 H4 SAE 45*45*5 275 84.76 Comp 47.71 g266P 18.734 RN 78.528 39.263 62.976 0.7 1 1 1.75
10 H5 SAE 45*45*5 275 73.03 Comp 55.1 g275P 43.267 RN 78.528 78.525 125.952 0.964 2 1 1.75
11 HR1 SAE 45*45*5 275 19.75 Comp 16.15 g305P 6.34 RN 78.528 39.263 62.976 0.99 1 1 1.75

23
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

FOUNDATION FORCES

24
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

7. FOUNDATION FORCES:

NORMAL TOWER:-
NORMAL CONDITION:-

TYPE OF FORCE UNIT(kgs)


COMPRESSION 2340.955
UPLIFT 2087.25
LONGITUDINAL SHEAR 98.93
TRANSVERSE SHEAR 135.73

NOTE: 1) ALL THE ABOVE FORCES ARE IN KGS WITHOUT FOS.


2) COMPRESSION AND UPLIFT ARE ALONG THE TOWER SLOPE.

BROKEN WIRE CONDITION:

NORMAL TOWER:-

TYPE OF FORCE UNIT(kgs)


COMPRESSION 1366.36
UPLIFT 1186.73
LONGITUDINAL SHEAR 56.59
TRANSVERSE SHEAR 80.71

NOTE: 1) ALL THE ABOVE FORCES ARE IN KGS WITHOUT FOS.


2) COMPRESSION AND UPLIFT ARE ALONG THE TOWER SLOPE.

25
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

SINGLE LINE DRAWING

26
CLIENT Electricity Company of Ghana limited DATE 03/02/2022

PROJECT CONSTRUCTION OF 2X40MVA 33kv ON A DOUBLE CIRCUIT TOWER FROM


NAME KPANDO TO HOHOE AND KADJEBI TO HOHOE SUBSTATIONS IN THE REV 01
VOLTA REGION.

8. SINGLE LINE DRAWING

4
1
A

A
B

B
C

C
D

C L IE N T :
E le c t r ic it y C o m p a n y o f G h a n a L im it e d , G h a n a
PRO JECT :

C USTO M ER :
D E L O V E L Y C O M P A N Y L IM IT E D , G H A N A
M ANU FA CTURER:
M / s . A R V E N S IS E N E R G Y P R IV A T E L IM IT E D .
K o l lu r i H o u s e ,# 8 - 3 - 3 1 8 / 1 1 /3 ,P l o t N o . 3 , J a ip r a k a s h N a g a r ,
Y e l la r e d d y g u d a , A m e e r p e t , H y d e r a b a d - 5 0 0 0 7 3 ,T e l a n g a n a ,I n d ia .
E

D E S IG N VASU 0 1 . 0 2 .2 2 D e s c r i p t io n : S CALE
D RA W N P R A T H A P 0 2 .0 2 . 2 2 33K V GA NT RY STR U C TU R E NTS
C H E C KE D
A P PR O V ED
P R A T H A P 0 2 .0 2 . 2 2
M U THU 0 2 .0 2 . 2 2
F O R D O U B L E C IR C U IT S HEET
1 OF 1
S IZ E REV
D R G . No.
A3 0

R EL E A S E D FO R P R E L I M IN A R Y TENDER I N F O R M A T IO N A PPRO VAL C O N S T R U C T IO N


1

27