CADANGAN MEMBINA SEMULA BAGI PEMBANGUNAN PUSAT LATIHAN JABATAN KEMAJUAN ORANG ASLI (JAKOA) FASA 1

DI ATAS LOT 21261,JALAN KUANTAN - MARAN, PAYA BUNGOR, MUKIM LEPAR, DAERAH KUANTAN, PAHANG.
Deadline Sch. % Complete Percentage (%)
Task Notes
start finish 1-Aug 15-Jul 1-Aug 15-Aug 1-Sep 15-Sep 1-Oct 15-Oct 31-Oct
EOT 07 Dateline 31.10.22
Phase 1 revised completion date 30.10.22 Depending on the completion of the
Original RE-MOBILIZATION WORKS 30.04.22 water recticulation by FELCRA BINA
Contract Sanitization of Site & Site Office
Site Reinspection & Reevaluation Depending on the completion of the
Preventive and corrective action plan Telekom Trenches by FELCRA BINA
Special Provisions to the Conditions of Contract (VOP)
Re-mobilization of Machineries to Site Depending on the completion of the
Re-deployment of Workers to Site Excess Road by FELCRA BINA
Re-appoint sub contractors (M&E, ICT, STP)
Re-appoint Safety & Health Officer Depending on the completion of the
Purchase of Building Materials connection of Sewerage pipe from
BLOK KULIAH 30.10.22 95.75% 95.00% 95.00% building to main Sewerage pipe by
Carpet 15.10.22 23.10.22 0% 0% 0% FELCRA BINA
Mesin Jahit 20.10.22 30.10.22 0% 0% 0%
Cold water underground fixtures 10.08.22 14.08.22 0% 0% 0% Depending on the completion of the
Internal testing 24.10.22 30.10.22 0% 0% 0% Landscape Work by FELCRA BINA
PEJABAT PENTADBIRAN 23.10.22 98.28% 98.00% 98.00%
Carpet 15.10.22 23.10.22 0% 0% 0%
Cold water underground fixtures 10.08.22 14.08.22 0% 0% 0% Work that has been
Main controller PA system 08.10.22 10.10.22 0% 0% 0% delayed until 01.08.22
Underground cable for Alarm Panel 04.10.22 06.10.22 0% 0% 0%
Internal testing 17.10.22 23.10.22 0% 0% 0%
BLOK PENGINAPAN PELAJAR 29.09.22 99.14% 99.00% 99.00%
Cold water underground fixtures 20.08.22 22.08.22 0% 0% 0%
Underground cable for Alarm Panel 08.09.22 10.09.22 0% 0% 0%
Internal testing 11.09.22 22.09.22 0% 0% 0%
DEWAN MAKAN 29.09.22 98.28% 98.00% 98.00%
Cold water underground fixtures 23.08.22 25.08.22 0% 0% 0%
LPG Tankage 14.09.22 16.09.22 0% 0% 0%
Underground cable for Alarm Panel 11.09.22 13.09.22 0% 0% 0%
Internal testing 18.09.22 29.09.22 0% 0% 0%
RUMAH PENYELIA 17.09.22 97.42% 97.00% 97.00%
Cold water underground fixtures 27.08.22 28.08.22 0% 0% 0%
Internal testing 11.09.22 17.09.22 0% 0% 0%
GUARD HOUSE 17.09.22 94.00% 93.00% 93.00%
Cold water underground fixtures 27.08.22 28.08.22 0% 0% 0%
Underground cable for Alarm Panel 11.09.22 13.09.22 0% 0% 0%
Internal testing 18.09.22 29.09.22 0% 0% 0%
TNB SUBSTATION 27.10.22 99.14% 99.00% 99.00%
Mobilization for TNB inspection 20.07.22 23.07.22 100% 0% 0%
Application for TNB inspection 23.07.22 21.08.22 30% 0% 0%
TNB Equipment (by others) 22.08.22 20.10.22 0% 0% 0%
TNB Internal testing 21.10.22 27.10.22 0% 0% 0%
CADANGAN MEMBINA SEMULA BAGI PEMBANGUNAN PUSAT LATIHAN JABATAN KEMAJUAN ORANG ASLI (JAKOA) FASA 1
DI ATAS LOT 21261,JALAN KUANTAN - MARAN, PAYA BUNGOR, MUKIM LEPAR, DAERAH KUANTAN, PAHANG.
Deadline Sch. % Complete Percentage (%)
Task Notes
start finish 1-Aug 15-Jul 1-Aug 15-Aug 1-Sep 15-Sep 1-Oct 15-Oct 31-Oct
EOT 07 Dateline 31.10.22
Phase 1 STP (Sewerage Treatment Plan) 20.10.22 73.42% 69.00% 69.00%
Original Fencing & gate 23.07.22 06.09.22 20% 0% 0%
Contract Steel works 16.08.22 05.09.22 0% 0% 0%
M&E works 04.09.22 02.10.22 0% 0% 0%
Premix 02.10.22 06.10.22 0% 0% 0%
Internal testing 08.10.22 14.10.22 0% 0% 0%
Application for IWK inspection 01.10.22 14.10.22 0% 0% 0%
IWK Internal testing 15.10.22 20.10.22 0% 0% 0%
EXTERNAL & INFRA WORKS
Sewerage Works 20.10.22 99.14% 100.00% 100.00%
Flushing test 08.10.22 14.10.22 0% 0% 0%
IWK Internal testing 15.10.22 20.10.22 0% 0% 0%
Underground LV Cable 30.09.22 50.28% 42.00% 42.00%
Fasa 2 cable route 21.07.22 09.08.22 60% 0% 0%
SSB-DS, FP-GL1 & GL2, FP-SL1 & SL2, FP-GSL 02.09.22 21.09.22 0% 0% 0%
Internal testing 23.09.22 30.09.22 0% 0% 0%
Underground ELV Cable 23.09.22 14.00% 0.00% 0.00%
PA system cable route (run thru telecom trenches) 18.09.22 23.09.22 0% 0% 0%
Fire Fighting Services 27.10.22 70.00% 65.00% 65.00%
Fire hose reel system 19.07.19 19.08.19 42% 0% 0%
Fire alarm underground fixtures (run thru telecom trenches) 25.09.22 30.09.22 0% 0% 0%
Fire extinguishers (ABC & CO2) 01.10.22 08.10.22 0% 0% 0%
Internal testing 08.10.22 15.10.22 0% 0% 0%
Application for BOMBA inspection 11.10.22 17.10.22 0% 0% 0%
BOMBA Internal testing 22.10.22 27.10.22 0% 0% 0%
Flag Post 26.10.22 0.00% 0.00% 0.00%
CADANGAN MEMBINA SEMULA BAGI PEMBANGUNAN PUSAT LATIHAN JABATAN KEMAJUAN ORANG ASLI (JAKOA) FASA 1
DI ATAS LOT 21261,JALAN KUANTAN - MARAN, PAYA BUNGOR, MUKIM LEPAR, DAERAH KUANTAN, PAHANG.
Deadline Sch. % Complete Percentage (%)
Task Notes
start finish 1-Aug 15-Jul 1-Aug 15-Aug 1-Sep 15-Sep 1-Oct 15-Oct 31-Oct
EOT 07 Dateline 31.10.22
Phase 1 RUMAH PAM 28 days 99.14% 99.00% 99.00%
Additional Ceiling works 12.09.22 14.09.22 0% 0% 0%
Contract Painting works 08.09.22 11.09.22 0% 0% 0%
Lattice cement board 11.09.22 16.09.22 0% 0% 0%
Cold water underground fixtures 28.08.22 30.08.22 0% 0% 0%
Electrical fittings 15.09.22 16.09.22 0% 0% 0%
Distribution Board (DB) 18.09.22 19.09.22 0% 0% 0%
Underground cable for Alarm Panel 15.09.22 19.09.22 0% 0% 0%
Internal Testing 20.09.22 24.09.22 0% 0% 0%
PUSAT PENGUMPULAN SAMPAH 31 days 70.00% 64.00% 64.00%
Concrete ramp 07.08.22 09.08.22 0% 0% 0%
Floor & wall finishes 24.07.22 29.07.22 100% 0% 0%
Roller shutter 09.08.22 13.08.22 0% 0% 0%
Ceiling works 04.08.22 07.08.22 0% 0% 0%
Painting works 13.08.22 15.08.22 0% 0% 0%
Cold water underground fixtures 15.08.22 17.08.22 0% 0% 0%
Electrical fittings 10.08.22 11.08.22 0% 0% 0%
Internal Testing 20.08.22 23.08.22 0% 0% 0%
PEJABAT PENYELENGGARAAN 20 days 80.28% 77.00% 77.00%
Ceiling works 07.08.22 11.08.22 0% 0% 0%
Door & ironmongery 13.08.22 14.08.22 0% 0% 0%
Painting works 15.08.22 17.08.22 0% 0% 0%
Cold water underground fixtures 15.08.22 18.08.22 0% 0% 0%
Electrical fittings 18.08.22 21.08.22 0% 0% 0%
Internal Testing 23.08.22 26.08.22 0% 0% 0%
SURAU 70 days 82.85% 80.00% 80.00%
Door & ironmongery 05.09.22 10.09.22 0% 0% 0%
Carpet 15.10.22 23..10.22 0% 0% 0%
Ceiling works 13.08.22 29.08.22 0% 0% 0%
Painting works 20.08.22 07.09.22 0% 0% 0%
Sanitary fittings 07.09.22 14.09.22 0% 0% 0%
Cold water underground fixtures 04.09.22 07.09.22 0% 0% 0%
Distribution Board (DB) 02.10.22 03.10.22 0% 0% 0%
Electrical fittings 04.10.22 17.10.22 0% 0% 0%
Public address system (PA) 10.10.22 17.10.22 0% 0% 0%
Internal testing 18.10.22 21.10.22 0% 0% 0%
CADANGAN MEMBINA SEMULA BAGI PEMBANGUNAN PUSAT LATIHAN JABATAN KEMAJUAN ORANG ASLI (JAKOA) FASA 1
DI ATAS LOT 21261,JALAN KUANTAN - MARAN, PAYA BUNGOR, MUKIM LEPAR, DAERAH KUANTAN, PAHANG.
Deadline Sch. % Complete Percentage (%)
Task Notes
start finish 1-Aug 15-Jul 1-Aug 15-Aug 1-Sep 15-Sep 1-Oct 15-Oct 31-Oct
EOT 07 Dateline 31.10.22
Phase 1 BLOK PENGINAPAN JANGKA PENDEK 107 days 67.42% 62.00% 62.00%
Additional Sanitary underground services 21.08.22 16.09.22 0% 0% 0% 6 months
Contract Apron & perimeter drain 01.09.22 20.09.22 0% 0% 0%
RWDP & RWHT 01.09.22 20.09.22 0% 0% 0%
Window installation 10.09.22 11.10.22 0% 0% 0%
Door & ironmongery 18.09.22 23.10.22 0% 0% 0%
Screeding works 16.07.22 31.07.22 100% 0% 0% .
Tiling works 20.07.22 08.09.22 26% 0% 0%
Ceiling works 23.07.22 14.09.22 26% 0% 0%
Cement board plank 16.07.22 31.07.22 100% 0% 0%
Painting works 21.08.22 20.09.22 0% 0% 0%
Handrailing, RHS MS fin & Glass Skylight 02.10.22 15.10.22 0% 0% 0%
Sanitary fittings 01.10.22 30.10.22 0% 0% 0%
Cold water speed drive pump (duty & standby) 13.08.22 28.08.22 0% 0% 0%
Cold water underground fixtures 08.09.22 14.09.22 0% 0% 0%
Repair & rewiring works (works suspension defect) 05.08.22 14.09.22 0% 0% 0%
Sub switch board (SSB) & Distribution board (DB) 14.10.22 27.10.22 0% 0% 0%
Underground cable for Alarm Panel 21.10.22 27.10.22 0% 0% 0%
Electrical fittings 16.08.22 10.10.22 0% 0% 0%
Air conditioning split unit 06.09.22 26.10.22 0% 0% 0%
Toilet ceiling mounted exhaust fan 06.09.22 21.09.22 0% 0% 0%
Earthing system 05.09.22 20.09.22 0% 0% 0%
Lightning protection system 05.09.22 20.09.22 0% 0% 0%
SMATV 14.10.22 21.10.22 0% 0% 0%
Internal testing 27.10.22 30.10.22 0% 0% 0%
TESTING & COMMISSIONING
Anticipated date of completion 31.10.22