This document outlines the project schedule for installing grounding and retaining samples at PT. Company Chemical from October 10th to October 31st 2022. The project lead is J.D. Pooject and involves preparing administration, resources, equipment, materials, and work sites from October 10th to 17th. Installation work then takes place from October 20th to 26th, including safety training, piping, wiring, equipment installation. Completion activities like inspections and clean up occur from October 25th to 26th.
This document outlines the project schedule for installing grounding and retaining samples at PT. Company Chemical from October 10th to October 31st 2022. The project lead is J.D. Pooject and involves preparing administration, resources, equipment, materials, and work sites from October 10th to 17th. Installation work then takes place from October 20th to 26th, including safety training, piping, wiring, equipment installation. Completion activities like inspections and clean up occur from October 25th to 26th.
This document outlines the project schedule for installing grounding and retaining samples at PT. Company Chemical from October 10th to October 31st 2022. The project lead is J.D. Pooject and involves preparing administration, resources, equipment, materials, and work sites from October 10th to 17th. Installation work then takes place from October 20th to 26th, including safety training, piping, wiring, equipment installation. Completion activities like inspections and clean up occur from October 25th to 26th.
PT.Company Enter PARDIC JAYA Name CHEMICAL in cell B2. PA - SONY Mon, 10/10/2022 Enter the name of the Project Lead in cell B3. Enter the Project Start start date project in cell E3. Pooject Start: label is in cell C3. e 1 Oct 10, 2022 Oct 17, 2022 Oct 24, 2022 Oct 31, 2022 Di display minggu ell 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 is J.D P,I.C PROGRESS MULAI AKHIR M T W T F S S M T W T F S S M T W T F S S M T W T F S S ro ell B TAHAP PERSIAPAN ell B persiapan administrasi 100% 10/10/22 10/13/22 o w persiapan man power plan 100% 10/13/22 10/15/22
persiapan alat kerja 100% 10/15/22 10/16/22
persiapan material kerja 100% 10/16/22 10/17/22
persiapan lokasi kerja & survey 100% 10/17/22 10/20/22
e ce TAHAP PELAKSANAAN ( AREA DALAM )
safety induction 25% 10/20/22 10/21/22
pekerjaan marking pipe line 0% 10/21/22 10/22/22
pekerjaan piping dan wiring 0% 10/21/22 10/23/22
pekerjaan looping rack 0% 10/23/22 10/23/22
pekerjaan pemasangan PEB box 0% 10/23/22 10/23/22
TAHAP PELAKSANAAN ( AREA LUAR )
Sample phase title block
pekerjaan marking pipe line 0% 10/23/22 10/23/22
pekerjaan piping dan wiring 0% 10/24/22 10/24/22
pekerjaan tapping 0% 10/24/22 10/25/22
pekerjaan finishing dan perapihan kembali 0% 10/25/22 10/26/22