MUNTINLUPA WASTEWATER PROJECTS

(March 26 – April 01, 2021)


CUPANG STP
CONTRACTOR : JE MANALO –SUEZ JV Accomplishment SOUTH AREA

Completion Date Target % Actual% Variance%


Original 20 Jul 2016/ 100% 91.433% -8.567%
Contract October 15, 2020
Projected
Completion December 2022 (including PPP)

Challenges:

• Limited Manpower deployment due to


COVID-19 Pandemic
• Ongoing Enhanced Community
Quarantine
• Permanent Meralco power supply, on-
going process.
Site Activities:
CONTRACTOR : JE MANALO –SUEZ JV CUPANG STP SOUTH AREA
TUNASAN STP & BNR
CONTRACTOR : VA TECH WABAG ACCOMPLISHMENT SOUTH AREA

Completion Date Target% Actual% Variance%


Original / 08 Aug 2016/15 July 2019
Rev Original Contract 100% 85.7267% -14.2733%
Projected 100% 87.4582% -12.5418%
December 2019
Completion
BNR

Challenges:
• Slow rate of progress for BNR and overall
electro-mechanical works.
• Limited Manpower deployment due to
COVID-19 Pandemic
CONTRACTOR : VA TECH WABAG
TUNASAN STP SOUTH AREA
Site Activities:

Skim Coating of Beams and Columns


at ground floor level
of BNR MCC Bldg
MUNTINLUPA CONVEYANCE SYSTEM
CONTRACTOR : DRAGONHART ACCOMPLISHMENT SOUTH AREA

Completion Date Rev. Target Actual Variance


Original / 12 Dec 2015 /
Rev October 28, 2020
100% 87.984% -12.016%
Projected
Completion

Challenges: SUMMARY OF ACCOMPLISHMENT

• Limited Manpower deployment due to Description Unit Total Actual %


COVID-19 Pandemic
Pipelaying l.m. 4122.75 3,813.77 92.51%
• On-going acquisition of extension of
excavation permit and demolition permit Manholes ea. 67 57 85.07
(Bayanan PS)
• Strong seepage of water in the excavation at Pumping Station ea. 4 1 25
Bubogan Pipelaying
• Buendia St. pipelaying remaining (300 Interceptor Box ea. - - -
meters) due to soil condition
• Pending DCEI works to be accomplished Creek Interceptor ea. 5 4 80
affecting MEP works (LP)
Bridge Crossing l.m. 352 340 96.59%
CONTRACTOR : LP-DCEI JV MUNTINLUPA CONVEYANCE SOUTH AREA
Site Activities:

Completion of internal hydrotest of Completion of installation of monorail Installation of CEE Socket/Connector


dry pit pumps discharge line in Tunasan PS for Grit Removal Pumps
For Request for Hydro Static Testing
with PQC