MUNTINLUPA WASTEWATER PROJECTS

(April 23-29, 2021)


CUPANG STP
CONTRACTOR : JE MANALO –SUEZ JV Accomplishment SOUTH AREA

Completion Date Target % Actual% Variance%


Original 20 Jul 2016/ 100% 91.605% -8.395%
Contract October 15, 2020
Projected
Completion December 2022 (including PPP)

Challenges:

• Limited Manpower deployment due to


COVID-19 Pandemic
• Permanent Meralco power supply, on-
going process.
Site Activities:
CONTRACTOR : JE MANALO –SUEZ JV CUPANG STP SOUTH AREA
TUNASAN STP & BNR
CONTRACTOR : VA TECH WABAG ACCOMPLISHMENT SOUTH AREA

Completion Date Target% Actual% Variance%


Original / 08 Aug 2016 / 15 July 2019
Rev Original/BNR 100% 85.7267% -14.2733%
Projected 100% 87.4582% -12.5418%
December 2021
Completion
Original/BNR

Challenges:
• Slow rate of progress for BNR and overall
electro-mechanical works.
• No manpower on site to bring the project
to significant progress.
• Site condition deteriorating (Equipment
not properly secured, headwork structure
deteriorating and poor housekeeping)
MUNTINLUPA CONVEYANCE SYSTEM
CONTRACTOR : DRAGONHART ACCOMPLISHMENT SOUTH AREA

Completion Date Rev. Target Actual Variance


Original / 12 Dec 2015 /
Rev October 28, 2020
100% 87.984% -12.016%
Projected
Completion December 2021

Challenges: SUMMARY OF ACCOMPLISHMENT

• Limited Manpower deployment due to Description Unit Total Actual %


COVID-19 Pandemic
Pipelaying l.m. 4122.75 3,813.77 92.51%
• Acquisition of extension of excavation permit
and demolition permit (Bayanan PS) Manholes ea. 67 57 85.07
• Pending DCEI works to be accomplished
affecting MEP works (LP) Pumping Station ea. 4 1 25
• Notice of Default issued last March 31, 2021.
Given 14 days upon receipt for remedy. Interceptor Box ea. - - -

Creek Interceptor ea. 5 4 80

Bridge Crossing l.m. 352 340 96.59%