Generation Completion
Name of Project Cost as per Allocation Expenditures Physical/
Capacity Date
PC-I 2021-22 (Rs. Million) Financial
(Rs. Million) (Rs. Million) Progress
Contract
Agreement for
Civil Works
Tarbela 5th 9,514.630
82,361.600 1,530 MW May 2026 8,159.000 signed on
Extension HPP (117%)
06.05.2021
and work in
progress
Total 84,517.000 20,192.306 (24%)
Detailed
Engineering
Design &
Dec 2022 18.851
Harpo HPP 9,522.801 34.5 MW 1,960.000 Preparation
(Phase-I) (1%)
(PC-I) of Tender
Documents is
in progress