Challenges:
Challenges/Site Activities:
• Slow rate of progress for BNR and overall
electro-mechanical works.
• No manpower on site to bring the project
to significant progress.
• Site condition deteriorating (Equipment
not properly secured, headwork structure
deteriorating and poor housekeeping)
• For issuance of Notice of Default
MUNTINLUPA CONVEYANCE SYSTEM
CONTRACTOR : DRAGONHART ACCOMPLISHMENT SOUTH AREA
• Notice of Termination issued last April 23, Description Unit Total Actual %
2021.
Pipelaying l.m. 4122.75 3,813.77 92.51%
• On-going quantification of remaining works.
Started the joint inspection of quantities last Manholes ea. 67 57 85.07
May 26, 2021 with LP representatives, ARUP
and PMD Construction. Pumping Station ea. 4 1 25