Professional Documents
Culture Documents
Note:
Packages for awarding / on-going bidding reflected in over-all project percentage computation.
Construction Packages Status - % Accomplishment
100%
100% 100%
98%
97%
75%
79%
50%
25%
47%
24%
22%
11%
Major packages
% Completion
Package Contractor
Actual Plan
Project Description 42.72% 37.82%
1. 10 MVA Substation Facility APSI 98.18% 98.78%
2. Site Development RTQCC 97.80% 100%
3. Deep Well #2 HYDROCK 100% 100%
4. Local Works for Material Handling & Steel Silos FABWERX 23.08% 30.37%
5. Grounding & Lightning Protection PEAM 4.67% 4.67%
6. Truck Scale System UPTOWN 92.0% 100%
7. Permeation Grouting (Flat Whse) GPI 100% 100%
8. Cleaning Tower VTLAO 47.18% 33.42%
9. Ship Unloader BUHLER 79.0% 79.0%
10. Silo Foundation RTQCC 24.25% 0.95%
11. Bulk Warehouse RTQCC 11.24% 6.11%
12. Ancillary Buildings For Awarding 0% 0%
13. Fire Pro and Water Distribution For Awarding 0% 0%
14. MV / LV Electrical System BARE 0% 1.13%
15. Supply & Manufacture of 5x10000MT Silos & Material N-LINE 85.0% 85.0%
Handling Equipment AGRICULTURE
16. Tower Foundations RTQCC No Schedule Submitted No Schedule Submitted
Note: Packages for awarding / on-going bidding reflected in over-all project percentage computation.
10MVA Substation – (On-going) Project
Accomplishment
98.18% Completed
47.18% Completed
Grinding of welded joints prior to painting. Cable pulling for power supply.
VT LAO
Construction 6.34% 0
Site Development – (On-going) Project
Accomplishment
97.80% Completed
79.00%
BUHLER
A.G 7.16%
Silo Foundation – (On-going) Project
Accomplishment
24.25%
Fabrication of rebar cage for bored pile. Installation of steel casing for bored piles.
RTQCC 17.79%
Bulk Storage Whse – (On-going) Project
Accomplishment
11.24%
RTQCC 15.65%
Progress Photos - Support Facilities
Truck Scale System – 92.00% Material Handling & Steel Silos – 23.08%
COMPLETED PACKAGES
Permeation Grouting for Bulk Storage Warehouse – 100% Completed
1 Permeation Grouting 11 Silo System & Aeration System 20 ArchEn Services Fee
4 Site Development
14 Electrical System (HV-MV)
10 10MVA Substation
Remaining Critical Packages for Awarding
ITEM PROJECT/ PACKAGES BUYER IN CHARGE STATUS NEXT STEPS IMPACT ON THE PROJECT
NO.
FIRE PROTECTION & DETECTION • Commercial May cause delay during the
1 SYSTEM
JK FALLER Technical Clarification Negotiation application of LGU Permits.
2 ANCILLARY BUILDINGS KM Fernandez Bidding Process • Technical Clarification Personnel office unavailability.
6
Issues and Concerns
Contractor Payment Issues
Item Project/ Packages Contractor PO Amount Amount for Issues Action Plan
No. Payment
5
PR-PO Monitoring
P.O Number Requester Description Status / Remark
ENGINEERING DESIGN FOR THE SITE Fully approved. Issued on June 28, 2022.
4110213356 JC HERIA DEVELOPMENT/SMFI/DAVAO GRAIN TERMINAL
PROJECT
4110213203 JC HERIA CLEANING TOWER Fully approved. Issued on June 26, 2022.
4110214531 JC HERIA SILO FOUNDATION Fully approved. Issued on July 14, 2022.
4110214529 JC HERIA BULK STORAGE WAREHOUSE Fully approved. Issued on July 14, 2022.
MEDIUM & LOW VOLTAGE POWER DISTRIBUTION Fully approved. Issued August 12, 2022.
4110216446 JC HERIA
SYSTEM
INSTALLATION OF ANCHOR BOLTS FOR TYPHOON Fully approved. Issued August 30, 2022
4110217327 JC HERIA
TOWER – DAVAO SHIP UNLOADER
TOWER & CONVEYOR SUPPORT FOUNDATION – Fully approved. Issued September 2, 2022
4110217602 JC HERIA
DAVAO GRAIN TERMINAL PROJECT
Issues and Concerns
Item Description Responsible Status / Remark