Progress:
Site Development (EV Galvez) 2x 5,184 sqm Warehouse (BCDC)
Projected: 82.81% Projected: 50.40%
Actual: 82.51% Actual: 13.00% Previous: 12.00%
Variance: (-) 0.3% Variance: (-)37.4%
Manpower: 4 workers Manpower: 30 workers
On-site Activities:
BCDC:
• Excavated footing foundation: 76 out of 115
• Concreted footing foundation: 69 out of 115
• 1st lift of column: 69 out of 115
• Tie beam: 360 LM
On-going gravel bedding and • Last Lift: 34 out of 115
compaction for footing tie beam at Pre-fab footing foundation for • For concrete pouring of first lift of pre cast footing foundation for GL-13
GL 17-19 A & GL 19 B-C concreting of first lift • RCP laying at GL 1 A-M
• For concrete pouring of last lift at GL 3-10 M, GL 8-9 A & GL 10 A-M
• On-going gravel bedding and compaction for footing tie beam at GL 17-
19 A & GL 19 B-C
• 1st batch of steel structures delivery: 11 out of 13 delivered
Progress Photos
Excavation Works
On-going: 7
Footing Foundation
On-going:
Concreted: 69 out of 115
2 x 5,184 sqm Warehouse Hub San Ildefonso, Bulacan
On-going: 0
Concreted: 69 out of 115
2 x 5,184 sqm Warehouse Hub San Ildefonso, Bulacan
Tie Beam
Last Lift
On-going: 30
Concreted: 34 out of 115