You are on page 1of 7

September 19, 2022

Additional 2 x 5,184 sqm Flat Warehouse – San Ildefonso, Bulacan


Weather Monitoring: Overall Accomplishments
Projected: 57.62%
• Cloudy Actual: 28.49%
Previous: 27.71 %
Variance: (-) 29.13%

Progress:
Site Development (EV Galvez) 2x 5,184 sqm Warehouse (BCDC)
Projected: 82.81% Projected: 50.40%
Actual: 82.51% Actual: 13.00% Previous: 12.00%
Variance: (-) 0.3% Variance: (-)37.4%
Manpower: 4 workers Manpower: 30 workers

On-site Activities:
BCDC:
• Excavated footing foundation: 76 out of 115
• Concreted footing foundation: 69 out of 115
• 1st lift of column: 69 out of 115
• Tie beam: 360 LM
On-going gravel bedding and • Last Lift: 34 out of 115
compaction for footing tie beam at Pre-fab footing foundation for • For concrete pouring of first lift of pre cast footing foundation for GL-13
GL 17-19 A & GL 19 B-C concreting of first lift • RCP laying at GL 1 A-M
• For concrete pouring of last lift at GL 3-10 M, GL 8-9 A & GL 10 A-M
• On-going gravel bedding and compaction for footing tie beam at GL 17-
19 A & GL 19 B-C
• 1st batch of steel structures delivery: 11 out of 13 delivered

Status of Remaining Packages:


• Land Reclassification – cost proposal by BCDC and justification letter
Delivered steel structures for Delivered steel structures for already submitted to BPG last March 31, 2022; for AOD PRS approval
Warehouse 03 Warehouse 03 • Electrical Package – pre-bidded last June 20, 2022
• Fire Pro – for TOR creation by Archen SPM
2 x 5,184 sqm Warehouse Hub San Ildefonso, Bulacan

Progress Photos

Delivered steel structures for Warehouse 03

Delivered steel structures for Warehouse 03


2 x 5,184 sqm Warehouse Hub San Ildefonso, Bulacan

Excavation Works

On-going: 7

Excavated: 76 out of 115


2 x 5,184 sqm Warehouse Hub San Ildefonso, Bulacan

Footing Foundation

On-going:
Concreted: 69 out of 115
2 x 5,184 sqm Warehouse Hub San Ildefonso, Bulacan

1st Lift of Column

On-going: 0
Concreted: 69 out of 115
2 x 5,184 sqm Warehouse Hub San Ildefonso, Bulacan

Tie Beam

For Concrete Pouring


Concreted: 360 LM
2 x 5,184 sqm Warehouse Hub San Ildefonso, Bulacan

Last Lift

On-going: 30
Concreted: 34 out of 115

You might also like