Lestari Banten Energi


Banten Power Plant

WEEKLY PROGRESS MEETING


Responsible: person Issue Date : Revision No. : File No. PAGE

IMS-MR 10/10/2017 0 518417524.docx 1 of 4

Date: 23 Juni 2020


Time: 10.00 Wib

Attendees :
1. Ayus S,Aji S (LBE)
2. Jaelani, Nur (SSM)

No. This Week Next Week


0 Summary
Overall Progress : 36,44 % Taggeted Progress : 40 %

Coalyard B Side: Coalyard B Side:


 Retaining wall : Completes ( Finishing )  Retaining wall : Completes
 Pile Cutting : 82 of 82  Pile Cutting : 82 of 82
 Line Concrate : 90 mtr of 100 mtr  Line Concrate : 100 mtr of 100 mtr
 Rib Bar install : 12 of 25 ea  Rib Bar install : 22 of 25 ea
 Pilecap Concrete #1 : 2 of 25 ea  Pilecap Concrete #1 : 12 of 25 ea
 Pile repair (pradhana): 0 of 4 ea  Pile repair (pradhana): 2 of 4 ea

Coalyard A Side: Coalyard A Side:


 Soil Exavation : 100 of 100 mtr  Soil Exavation : 100 of 100 mtr
 Pile Cutting : 81 of 81 ea  Pile Cutting : 81 of 81 ea
 Pile repair (pradhana): 0 of 2 ea  Line Concrate : 100 mtr of 100 mtr
 Rib Bar install : 5 of 25 ea
 Pilecap Concrete#1 : 2 of 25 ea
 Pile repair (pradhana): 2 of 2 ea

I. Safety and Environment


Selalu melakukan kordinasi terhadap Safety LBE tekait Selalu melakukan kordinasi terhadap Safety LBE tekait kehadiran dan
jam kerja
kehadiran dan jam kerja
II Progress of Works & Plan
PT. Lestari Banten Energi
Banten Power Plant

WEEKLY PROGRESS MEETING


Responsible: person Issue Date : Revision No. : File No. PAGE

IMS-MR 10/10/2017 0 518417524.docx 2 of 4

2.1 Preparation
Perakitan besi CT1-3 titik dan CT2-7 titik Rencana kerja perakitan CT2 sebanyak 12 titik.

2.2 Stake out / Measuring


 Pembuatan elevasi pilecap sisi utara ( A ) 81 titik
Maping pilecap di sisi utara (A) dan selatan (B)
 Maping pilecap
2.3 Soil Excavate / Soil dispose
Penggalian tanah pilecap sisi utara sepanjang 100 M
<Tidak ada aktifitas>
2.4 Pile Head Cutting
Pemotongan Borpile 81 titik .
2.5 Sand Fill / Lean Concrete
Pembuatan lantai kerja bagian pilecap sepanjang 100M
Pembuatan lantai kerja bagian pilecap sepanjang 89 M
sisi selatan (B)
2.6 Rebar / Formwork
Pemasangan bekesting untuk CT1-3 unit dan CT2-2 unit Pemasangan bekesting untuk CT 1 dan CT 2 sebanyak 12 unit tediri
dari B1,B4,B5,B6,B7,B8,B9,B10,B11,B12,B13,B14.
2.7 Concrete Pouring
Rencana Pengecoran pilecap B-02 dan B-03 18,5 m3 Rencana pengecoran 69 m3 tediri dari
 21 m3 (B-01,B-05 dan B-07)
 18 m3 (B-08,B-10 dan B-11)
 30 m3 rencana kedepan

III Tools and Support


 Total Station  Total Station
 Excavator Cat PC 75  Excavator Cat PC 75
PT. Lestari Banten Energi
Banten Power Plant

WEEKLY PROGRESS MEETING


Responsible: person Issue Date : Revision No. : File No. PAGE

IMS-MR 10/10/2017 0 518417524.docx 3 of 4

 Excavator Hitaci PC 200  Excavator Hitaci PC 200


 Dump truck 3 unit  Dump truck 3 unit

IV Manpower
Total jumlah pekerja PT.SSM adalah 62 orang Total jumlah pekerja PT.SSM adalah 62 orang
 Staf 4 orang  Staf 4 orang
 Keamanan 5 orang  Keamanan 5 orang
 Logistic 3 orang  Logistic 3 orang
 Pekeja Besi 9 orang  Pekeja Besi 9 orang
 Pekeja Sipil 27 orang  Pekeja Sipil 27 orang

 Driver 1 orang  Driver 1 orang


 Operator Mobile crane 1  Operator Mobile crane 1
 Operator Excavator 2 orang  Operator Excavator 2 orang
 Supir dum truck 3 orang  Supir dum truck 3 orang
 Scaffolder 3 orang  Scaffolder 3 orang
 Pengawas Excavator 1 orang  Pengawas Excavator 1 orang
 Mekanik 2 orang  Mekanik 2 orang
 Rigger 1 orang  Rigger 1 orang

V Delivery Material

 Concrete C250 Qty : 18,5 M³  Concrete C250 Qty : 69 M³


 Concrete LC Qty : ±40 M³  Concrete LC Qty : ±40 M³

VI Others
Penyebab Delay Project.
PT. Lestari Banten Energi
Banten Power Plant

WEEKLY PROGRESS MEETING


Responsible: person Issue Date : Revision No. : File No. PAGE

IMS-MR 10/10/2017 0 518417524.docx 4 of 4

- Man Power
- PT. SSM mengalami keterlambatan erection di karenakan masa pandemic Covid-19 dan PSBB.

Action Untuk meningkatkan progress


- Penambahan Jam Kerja
- Hari libur tetap Kerja
- System kerja yang effective

VII Others
1. PT. SSM mengajukan untuk pengecoran pilecap
1. PT.SSM megajukan untuk rencana pengecoran pilecap 69 m3
18,5 m3
2. PT.SSM mengajukan inspeksi strukur besi
2. PT. SSM Mengajukan inspeksi struktur besi.
3. PT.SSM Mengajukan Area Rokok
3. PT. SSM mengalami keterlambatan erection di
4. PT.SSM Menargekan pilecap sisi selatan 12 titik selesai.
karenakan masa pandemic Covid-19 dan PSBB.
4. PT.SSM mengajukan Area Rokok .
5. PT.SSM menemukan pekerjaan dari PT.Pradana
harus di perbaiki dengan total saat ini 6 titik
borpile ,sisi utara(A) baru ditemukan 2 titik di sisi
selatan (B) 4 titik .