INITIAL COST

Projek Jalan dari Bukit Balau ke Banting Sri Aman Sarawak


BRIDGE OVER BATANG KALUH
DESCRIPTION Quantity COST (RM)
A MOBILISATION
1 Excavator 2unit
2 Lorry 1unit
3 Containa 2unit
4 Bar cutter 1unit
5 Bar bender 1unit
6 Water pump (big) 1unit
7 Water pump (small) 2unit
180,000.00
8 Generator (big) 1unit
9 Generator (small) 3unit
10 Welding set gen 1unit
11 Equipment tools 2 set each
12 Stagging/temporary clossing materials 187pcs

B MATERIAL/OTHERS
B.1 Stagging/Temporary clossing
1 Steelplate 25mm 20pcs
2 I-Beam 25pcs
3 Sheetpile 60pcs
4 Round steel pipe 400mm 20pcs
5 Spun pile (from Gedung) 62pcs
250,000.00
B.2 Labours neccessity
1 Hostel 8pax
2 Construction tools appx

C Administration for first 6 months


1 Project Manager @RM6500/m 1pax
2 Supervisor @RM2700/m 1pax
3 Operator @RM2500/m 1pax 180,000.00
4 General worker @RM65-RM75/d 8pax
5 Petty cash @RM4000/m

TOTAL 610,000.00